C06: INDUSTRIALISED BUILDING SYSTEM (IBS) SECTION A: 40 MARKS BAHAGIAN A: 40 MARKAH INSTRUCTION: This section consists of TEN (10) short questions. Answer ALL questions. ARAHAN: Bahagian ini mengandungi SEPULUH (10) soalan pendek. Jawab SEMUA soalan. C1 QUESTION 1 SOALAN 1 List FOUR (4) aims of IBS Roadmap 2003-2010. Senaraikan EMPAT (4) matlamat Pelan Halatuju IBS 2003-2010. QUESTION 2 SOALAN 2 The usage of IBS components is more expensive than the conventional method. Explain TWO (2) scenarios that caused to this matter. Penggunaan komponen IBS adalah lebih mahal berbanding kaedah konvensional. Terangkan DUA (2) senario yang menyebabkan keadaan ini berlaku. C1 QUESTION 3 SOALAN 3 List FOUR (4) types of creativity precast panel in IBS. Senaraikan EMPAT (4) jenis panel kreatif pratuang dalam IBS. 2 SULIT
C06: INDUSTRIALISED BUILDING SYSTEM (IBS) QUESTION 4 SOALAN 4 Explain TWO (2) advantages of using precast concrete. Huraikan DUA (4) kebaikan penggunaan konkrit pratuang. C1 QUESTION 5 SOALAN 5 Define the Modular Coordination. Takrifkan definasi Koordinasi Modular. QUESTION 6 SOALAN 6 Discuss TWO (2) benefits of Modular Coordination. Bincangkan DUA (2) kebaikan Koordinasi Modular. QUESTION 7 SOALAN 7 Explain FOUR (4) types of reference systems to determine coordinating space and zone for building element and installation. Terangkan EMPAT (4) jenis sistem rujukan untuk menentukan ruang dan zon penyelaras bagi elemen bangunan dan pemasangan. 3 SULIT
C06: INDUSTRIALISED BUILDING SYSTEM (IBS) C1 QUESTION 8 SOALAN 8 List FOUR (4) principles of IBS Score. Senaraikan EMPAT (4) prinsip Skor IBS. QUESTION 9 SOALAN 9 IBS Content Scoring System (IBS Score) is a systematic and structured assessment system. Explain the following terms: Sistem Pemarkahan Kandungan IBS (Skor IBS) adalah penilaian yang sistematik dan sistem berstruktur. Jelaskan istilah-istilah berikut: a) IBS Scoring System / Sistem Pemarkahan IBS b) MS 1064 QUESTION 10 SOALAN 10 Explain briefly the formula for IBS Scoring System to determine score for Structural and Wall System. Huraikan formula untuk Sistem Pemarkahan IBS untuk menentukan skor Sistem Struktur dan Dinding. 4 SULIT
C06: INDUSTRIALISED BUILDING SYSTEM (IBS) SECTION B: 60 MARKS BAHAGIAN B: 60 MARKAH INSTRUCTION: This section consists of FOUR (4) structured questions. Answer THREE (3) questions only. ARAHAN: Bahagian ini mengandungi EMPAT (4) soalan berstruktur. Jawab TIGA (3) soalan sahaja. QUESTION 1 SOALAN 1 a) Describe how IBS can contribute to a sustainable and green construction in the future based on the following aspects: Jelaskan bagaimana IBS boleh menyumbang kepada pembinaan yang mampan dan hijau pada masa depan berdasarkan aspek-aspek berikut: i. Sustainability from controlled production environment. Kelestarian dari persekitaran pengeluaran dikawal. ii. IBS and waste IBS dan sisa iii. IBS and logistic IBS dan logistik iv. IBS and economic sustainability IBS dan kemampanan ekonomi [20 marks] [20 markah] 5 SULIT
C06: INDUSTRIALISED BUILDING SYSTEM (IBS) QUESTION 2 SOALAN 2 a) Precast Flooring has been used widely in commercial, industrial and domestic building. Describe THREE (3) characteristics of Precast flooring. Lantai pratuang telah digunakan secara meluas dalam pembinaan bangunan komersial, industri dan tempatan. Huraikan TIGA (3) ciri-ciri lantai pratuang. [6 marks] [6 markah] b) Half slab is a precast floor which comprises precast and in situ concrete method. Sistem Papak Separuh merupakan lantai pratuang yang menggunakan kaedah pratuang dan konkrit di tapak. i. Describe half slab using the aid of diagram. Huraikan papak separuh dengan bantuan gambarajah. ii. Explain FOUR (4) benefits of half slab in a construction. Terangkan EMPAT (4) kebaikan menggunakan papak separuh dalam pembinaan. [10 marks] [10 markah] 6 SULIT
C06: INDUSTRIALISED BUILDING SYSTEM (IBS) QUESTION 3 SOALAN 3 a) Modular Coordination has been introduced in Malaysia in April 1986. Explain the purpose of Modular Coordination. Koordinasi Modular telah diperkenalkan di Malaysia pada April 1986. Terangkan tujuan Koordinasi Modular. [2 marks] [2 markah] b) Many construction methods have been introduced in Malaysia because of the innovation and improvement of construction technology such as modular coordination. Explain clearly FOUR (4) importances of using Modular Coordination. Pelbagai kaedah pembinaan diperkenalkan di Malaysia kerana inovasi dan peningkatan teknologi pembinaan seperti Koordinasi Modular. Huraikan dengan jelas EMPAT (4) kepentingan menggunakan Modular Koordinasi. [8 marks] [8 markah] c) The modular reference system defines coordinating space and zone for building element and installation. Illustrate FOUR (4) types of references in locating building element and installation. Sistem rujukan modular adalah untuk menentukan ruang dan zon penyelaras bagi elemen bangunan dan pemasangan. Lakarkan EMPAT (4) jenis rujukan dalam mencari elemen bangunan dan pemasangan. [10 marks] [10 markah] 7 SULIT
C06: INDUSTRIALISED BUILDING SYSTEM (IBS) QUESTION 4 SOALAN 4 Figure B4 shows the typical layout floor plan for one unit of Single Storey Bungalow House. Rajah B4 menunjukkan pelan lantai bagi Rumah Banglo Setingkat. Figure B4 / Rajah B4 a) Describe THREE (3) principles to be followed in order to calculate the IBS score. Huraikan TIGA (3) prinsip yang diambil kira dalam pengiraan skor IBS. [6 marks] [6 markah] 8 SULIT
C06: INDUSTRIALISED BUILDING SYSTEM (IBS) C3 b) Calculate the IBS content score of a single storey bungalow house as in Figure B4 (fill in the IBS Score Form). Hitung kandungan skor IBS bagi rumah banglo setingkat seperti di Rajah B4 (Isikan Borang IBS Score). 1) Construction Area / Luas Binaan Construction area Luas binaan i. Construction floor area : 140 m 2 Luas binaan lantai : 140 m 2 ii. Construction roof area : 140 m 2 Luas binaan bumbung : 140 m 2 2) Structural System / Sistem Struktur i. Beam : Precast concrete beam Rasuk :Rasuk konkrit pratuang ii. Column : In-situ concrete using steel formworks Tiang : Konkrit in-situ menggunakan acuan keluli iii. Floor slab : Precast concrete slabs Papak : Papak lantai pratuang iv. Roof truss : Prefabricated timber roof truss. Kekuda bumbung : Kekuda bumbung prefabrikasi kayu 3) Wall System / Sistem Dinding i. Internal wall : Precast concrete panel = 160 m length Dinding dalam ii. External wall : Precast blockwork = 220 m length Dinding luar 9 SULIT
C06: INDUSTRIALISED BUILDING SYSTEM (IBS) 4) Other simplified construction solutions / Lain-lain kaedah kebolehbinaan i. Beam : 60% complies to MS 1064 Rasuk ii. Column : 100% complies to MS 1064 Tiang iii. Wall and slab : Less than 50% complies to MS 1064 Dinding dan lantai iv. Doors : 100% complies to MS 1064 Pintu v. Window: 0% complies to MS 1064 Tingkap vi. Horizontal repetition of structure = 90% Pengulangan struktur secara mengufuk [14 marks] [14 markah] SOALAN TAMAT 10 SULIT
C06: INDUSTRIALISED BUILDING SYSTEM (IBS) BORANG IBS SCORE NO SIRI :... ELEMENTS AREA (m 2 )/ Length (m) IBS FACTOR COVERAGE IBS SCORE Part 1: Structural Elements Total Part 1 Part 2: Wall System Total Part 2 Part 3: Other Simplified Construction Solutions Total Part 3 IBS CONTENTS SCORE OF PROJECT (PART1 + PART2 + PART3 ) 11 SULIT