Clay Sewer Pipe-Joint Infiltration Leak-Rate Testing

Similar documents
Potential Use of FGD as a Flowable-Fill

AK FIXATOR SYSTEM AK1

B. Stipulated Price (Lump Sum). If Contract is Stipulated Price Contract, payment for Work in this Section is included in total Stipulated Price.

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

FLOWABLE FILL Controlled Low-Strength Materials

Appendix B. Shallow Foundations Report

comprehensive Design Rationale shoulder system Knees Hips Extremities Cement and Accessories PMI TEchnology

INSTALLATION INSTRUCTIONS

Heart and Circulation

Flume Installation Instructions

Identifying Number MPC-354. Project Title: Geotechnical Limit to Scour at Spill-through Abutments. University: The University of Wyoming

DURASEAL. High Integrity, Double Block and Bleed Plug Valve.

Maximizing Machinery Reliability vibration awareness

MUE247 Alignment Methods and Application H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

OWNER S MANUAL and INSTALLATION INSTRUCTIONS

MICHIGAN STATE UNIVERSITY CONSTRUCTION STANDARDS

ATTACHMENT B8 Incident History

Dry Directional Drilling

MONTANA FLUME. User s Manual. Montana (Short Parshall) Flume User s Manual

MDH GOLD S TANDARD - B UYERS GUIDE

COWLEY COLLEGE & Area Vocational Technical School

STRUCTURAL STABILITY ASSESSMENT

PdM-101: Introduction to Vibration and Detection Analysis

Update on Seismic Behavior and Design of

Presentation Goals. Project Goals. ISS Presentation Final 1. Cushion Characterization ISS 2011

(12) Patent Application Publication (10) Pub. No.: US 2003/ A1

Pipeline Technology Conference 2007

1. Introduction. 2. API 5.7 Testing Protocol for Differential Pressure Flow Measurement Devices

Prefabricated Vertical Drain with Fabric

Scovell J.M., Barrera E.V., Leihui G., Perito P.E., Wilson S.K., Carrion R.E., Hakky T.S.

2011 BRIDGE INSPECTION REPORT

Service Life of Aluminized Type 2 Coated Steel Pipe: Predictions vs. Actual

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

DESIGN CONSIDERATIONS AND ECONOMIC IMPACTS OF NEAR FREEZING SOIL TEMPERATURES ON SOIL COMPACTION

ULTRASONIC ARRAY APPROACH FOR THE EVALUATION OF ELECTROFUSION JOINTS OF POLYETHYLENE GAS PIPING

ACFT EQUIPMENT LIST (1 X LANE REQUIREMENT)

Use of Dilute Flowable Backfill for Corrosion Mitigation of Buried Pipe

GENERAL FRACTURE CONTROL REQUIREMENTS FOR MANNED SPACEFLIGHT SYSTEMS

Standard Practice for Verification of Testing Frame and Specimen Alignment Under Tensile and Compressive Axial Force Application 1

THE DEVELOPMENT AND MANUFACTURE OF FIXED- ULTRASONIC INSPECTION REFERENCE REFLECTORS AND TRANSDUCERS FOR COMPRESSOR BLADE DOVETAILS

Reprocessing Guide. Autoclavable Arthroscope and Hardware Sterilization Tray

Effect of Pile Orientation in Skewed Integral Abutment Bridges

LANDFILL STABILITY ISSUES

21 st Century Challenges in Fertilizer Coatings

FEASIBILITY REPORT UNITY AVENUE STREET IMPROVEMENTS

Developments in Ultrasonic Inspection II

ADA Signage Guidelines

2013 Annual Report June 30, 2014

Advanced Ergonomic Benefits of Pneumatic Scissors

Assessing potential cracking zones in embankment dams

Connect with EatSmart

Anomaly Assessment and Repair Panel

DIGITAL RADIOGRAPHY OF PE JOINTS

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA

CYBEX INTERNATIONAL, INC.

AN EXPERIMENTAL INVESTIGATION ON BEHAVIOR OF RC PARAPET WALL OF ABUTMENT UNDER COLLISION

Case Study of Pipe Bursting In Shreveport, LA

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017

Pro 01: Development and In Vitro Evaluation of a Hydraulic System for a Mini axial Flow Blood Pump

Total Gym Elevate Line Bring a NEW Total Body Workout to Your Gym

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014

Seismic Analysis of Bridge Abutment-Soil Systems

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

CRACK DETECTION AND PIPELINE INTEGRITY SOLUTIONS

Fracture Initiation from Perforations

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes

5 DAMAGE TO TRANSPORTATION FACILITIES

Using the sharp-crested weir formula the outflow was:

Dental Intraoral X-ray Systems

The New S in SSES. Erin Hawkins, CFM, City of Lynchburg Ben Custalow, PE, Greeley and Hansen

ADDENDUM 1. This Addendum forms part of and modifies Proposal Documents dated, May 6, 2016, with amendments and additions noted below.

ANSI API RP-754 Quarterly Webinar. June 21, Process Safety Performance Indicators for the Refining and Petrochemical Industries

Corrigendum. 1. Last date of bid document downloading and submission Date:- 21/2/2017, Upto Hrs.

SureFlow. Oxygen Flow Station PROVIDER TECHNICAL MANUAL

Eyewash and Safety Showers HM 20 Page 1

MANUFACTURING OPERATING STANDARDS AND RESTRICTIONS FOR COMMERCIAL CANNABIS OPERATIONS IN CITY OF CARSON

Bengt H. Fellenius. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot. Amsterdam.

The Do s and Don ts of Pressure Transducers

EFFECTS OF SPATIAL VARIATION OF SEISMIC INPUTS ON BRIDGE LONGITUDINAL RESPONSE

Instructions for Use. IJ Catheter Ultrasound Model Version 2400 Series

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

Sensing of Lateral Seismic Earth Pressures in Geotechnical Centrifuge Models

Safety Meeting. Meeting Leader Instructions. Safety, Teamwork & Our Customer s 1 st Choice

Cerus P-Series General Specifications Section 15172

International Symposium on Children's Environmental Health

Fibrlok II 2529 Universal Optical Fiber Splice

Growth Capable. Mike 6 tall in a Granstand III MSS. Nichole 42 tall in a Kidstand III MSS

Dear Valued Customer,

Shifting the Canning Bus Bridge Sideways

A novel method to set up and calibrate goniophotometer

ULTR A SERIES G7-S75

Flaw Assessment Using Shear wave Phased array Ultrasonic Transducer

AGGREGATE WAQTC FOP AASHTO T 2 (16) PERFORMANCE EXAM CHECKLIST (ORAL) Participant Name Exam Date

Bimodal PE s Contribution to the Life Expectancy Extension of Gas Distribution Pipelines

Systems Engineering Guide for Systems of Systems. Essentials. December 2010

Instructions. Fibrlok Optical Fiber Splicing System. Issue 6, August 1991

Wick Drains and Piling for Cai Mep Container Port, Vietnam. Bengt H. Fellenius. Sower's Lecture Atlanta May 8, 2012

Innovative Use of Flowable Fill for Short-Span Bridge Rehabilitation

Transcription:

Clay Sewer Pipe-Joint Infiltration Leak-Rate Testing 1. ABSTRACT While numbers of small to large older cities are undertaking repairs and maintenance, several other newer cities are planning on installing wastewater systems. Infiltration due to ing pipes, manholes, laterals and other components of a wastewater system will add to the problem of overflow and substantially load the treatment facilities. Frequent overflows not only lead to regulatory problems but also increase the treatment cost. Leaking systems will result in the erosion of soils through the ing joints leading to the settlement of the ground surface, formation of sinkholes and damage to surrounding pavements and structures. Literature review indicated that Standard ASTM pipe-joint tests varied with the type and size of pipe. In order to quantify the infiltration at various types of pipe-joints, a unified testing program was developed to test 30-in. diameter sewer pipe joint up to a hydrostatic pressure of 7 psi. A testing protocol was developed and approved by a steering committee with representation from the EPA, pipe associations, cities and consulting engineers. The testing protocol outlined the procedures to determine the age rates at pipe joints under shear loading and angular deflection. A testing facility was designed and constructed in the CIGMAT Laboratory at the University of Houston. Pipe joints were tested in duplicate. Based on the test results, there was no age at the 30-in. clay pipe-joint when the joint was tested with and without shear loading and angular deflection. During the straight test (unloaded joint) the joint was subjected to hydrostatic pressure incrementally to a maximum hydrostatic pressure of 7 psi with a total testing time of 30 minutes and there was no age. During the shear test, the joint was subjected to shear force incrementally to a maximum shear force of 4600 lb. The total testing time for each joint was 6.5 hours and the joint was subjected to a maximum hydrostatic pressure of 7 psi at every increment of shear load and there was no age. During the angular test, the joint was subjected to angular rotation in steps to a maximum rotation of 2 o at the joint. The total testing time 1

was 4.5 hours and the joint was subjected to a maximum hydrostatic pressure of 7 psi and the shear load at the joint varied from 4,600 to 8,000 lbs. during the angular test. There was no age. 2. INTRODUCTION Infiltration due to ing pipes, manholes, laterals and other components of a wastewater system will add to the problem of overflow and substantially load the treatment facilities. Frequent overflows not only lead to regulatory problems but also increase the treatment cost [Water Environmental Federation, 1999]. Leaking systems will result in the erosion of soils through the ing joints leading to the settlement of the ground surface, formation of sinkholes and damage to surrounding pavements and structures. Erosion of soil materials around the pipes and manholes can lead to formation of void and settlement of pipes accelerating the damage. Eroding soils entering the wastewater system through the ing joints can cause problems within the wastewater system. Several ASTM standards were reviewed and are summarized in Table A1 in Appendix A [ASTM, 2000]. The test methods cover pipe sizes from 3 to 144 inches. Both air and water have been recommended for use in infiltration/exfiltration tests. Of the test methods reviewed, 85% were exfiltration and 28% were infiltration tests. Test methods for plastic, fiberglass, concrete and clay pipes have also recommended misalignment (angular) and shear force tests at the joints. The testing pressure varied from 3.5 to 40 psi. Acceptable rates varied based on type of pipe and application (Table A1). Literature review indicated that each type of pipe is tested differently in determining the infiltration rate at the pipe joint. Hence it was necessary to develop a unified testing method to better quantify the infiltration at various pipe joints under more realistic joint-loading conditions. Since several factors in the field can affect the performance of pipe joint, it is important to identify the important factors through controlled experiments where important variables are studied one at a time. Based on the review of the literature and ASTM testing standards, a testing protocol for determining the infiltration at the pipe-joint must be developed. 2

Based on the preliminary testing at the University of Houston, a comprehensive testing protocol (Appendix B) was developed and submitted to the steering committee for review and approval. The steering committee members were representing the USEPA, cities, consulting engineers, general contractors, professional associations and pipe industries. Once the testing plan was reviewed and approved by the steering committee, pipe-joints were tested under this test plan. 3. OBJECTIVES The overall objective was to determine, through controlled laboratory tests, the infiltration -rates for different types of 30-in. diameter sewer pipe-joints under various loading conditions. The specific objectives were as follows: 1. Develop a testing protocol to determine the infiltration at the pipe-joint under the following conditions: a. Straight joint (Method A) b. Angular deflection (Method B) c. Shear load (Method C) 2. Develop a testing facility to perform the tests under external hydrostatic pressure. 3. Perform tests according to the testing protocol on pipe joints assembled by the pipe companies/representative. 4. TESTING PROGRAM Two instrumented test stands were designed and constructed at the University of Houston. Each test stand was capable of accommodating two three-foot lengths of 30- inches or greater diameter pipe joined together for testing. Provisions were made to 3

constrain the pipe from moving laterally. The loading points were instrumented with 20,000 pound load cells to measure the applied and reaction loads (Figs. 1 and 2). Test stand provisions will also allow the pipe-joint to be tested under deflection and shear load in accordance with the test protocol. The pipe-joint was first tested under no load followed by the shear test and angular test. Since water age can occur under several joint conditions, three model tests were proposed to closely represent the field situations. In all the cases, after loading, infiltration was tested with a hydrostatic pressure up to 7 psi. Tests were performed in duplicates resulting in six model tests for each pipe joint. The data sheet on the joint characteristics (from pipe manufacturer/ supplier) is in Appendix C. 5. RESULTS AND DISCUSSIONS Two clay pipe joints were tested (ASTM Specification: ASTM C 425) and the properties of the pipe and joint are in Appendix C. The joints were tested under aligned (straight and shear load tests) and misaligned positions (angular test) (Fig. 1 (a), (b) and (c)). The bladders were built to fit the pipe joints using a combination of rubber and plastic sheets (Fig. 2). The joints were pressurized under each mode of loading starting at 3 psi hydrostatic pressure. The tests on clay pipe-joints were performed during the time period of Dec. 17, 2001 to Dec. 20, 2001. 5.1 Test No. 1 (Clay Pipe Joint No.1) (a) METHOD A: Straight Pipe Joint Test (Fig. 1 (a)) The results of the test are summarized in Table 1. was observed at the joint during the total test period of 30 minutes with a maximum hydrostatic pressure of 7 psi for 10 minutes. (b) METHOD B: Angular Deflection Test (Fig. 1 (b)) 4

In the angular deflection test, the angles 0.50, 1.00, 1.50 and 2.00 degrees at the joint were tested. The testing time under each angle was 30 minutes with a maximum hydrostatic pressure of 7 psi for 10 minutes. The results of the test are summarized in Table 1. was observed at the joint during the total test period of 4.5 hrs. The maximum separation at the invert of the joint was about 1.2 at the end of the test. This didn t lead to any during the period of the test. The relationship between the angle of rotation at the joint angle and the shear load at the joint is shown in Fig. 3. With the increase in the angle rotation, the shear load decreased from 8,000 to 6,000 lbs at the joint. (c) METHOD C: Shear Load Test (Fig. 1 (c)) The joint was tested under shear loading according to Method C (Appendix B). The load cell locations are shown in Fig. 1(c). The load was applied through Load Cell No. 1 on the pipe and was increased in steps of 500, 1000, 2000, 3000, 4000, 5000, 6000, 7000, 8000, 10,000 and 12,000 lbs. The testing time under each load was 30 minutes with maximum hydrostatic pressure of 7 psi for 10 minutes. The test results are summarized in Table 2. The Shear load at the pipe joint vs. Applied load at Load Cell No. 1 is shown in Fig. 4. was observed at the joint at the maximum shear load of 4588 lbs and during the total test period of 6.5 hrs. Test No. 1 Summary The composite bladder performed as designed. Total testing time for Methods A, B, and C were 0.5 hour, 4.5 hours and 6.5 hours respectively. was observed at the tested joint for all the testing conditions. The maximum applied shear load at the joint was 4588 lb (over 150 lb/in diameter) and there was no water.. 5

Pipe Joint Bladder Clay Pipe (a) Method A: Straight Pipe Joint Test Load cell 3 Bladder Clay Pipe Pipe Joint Load cell 2 (b) Method B: Angular Deflection Test Load Bladder Load cell 1 1 2 Wood 12 Clay Pipe 1 Load cell 3 Pipe Joint Load cell 2 Side View 2-2 (d) Method C: Shear Load Test 2 Figure 1. Clay Pipe-Joint Test Configurations 6

Method B: Angular Deflection Test Methods A and C: Straight Alignment and Shear Load Tests Figure 2. Views of the Clay Pipe Joint Tests and Loading Frame 7

10000 Shear Load at the Joint, lb 8000 6000 4000 2000 0 0 0.5 1 1.5 2 2.5 Angle, o Figure 3. The Relationship between Angle and Applied Load in Test No. 1 Table 1. Results of Straight and Angular Deflection Tests (Test No. 1) Method Angle Pressure Time Leakage Remarks ( o ) (psi) (min) Total testing A 0 time was 30 minutes. No age. Total testing 0.5 time was 30 minutes. No age. Total testing 1.0 time was 30 minutes. No age. Total testing B time was 30 1.5 minutes. No age. Total testing 2.0 time was 30 minutes. No age. Remarks Up to 2 o 3 to 7 psi Total 5 hrs No Leak 8

6000 Test No. 1 5000 Shear Load at the Joint, lb 4000 3000 2000 1000 0 0 2000 4000 6000 8000 10000 12000 14000 Applied Load, lb Figure 4. Shear Load vs. Applied Load in Test No. 1 Table 2. Results from Shear Load Tests (Test No. 1) Intended Load (lb) 500 1000 2000 3000 Pressure (psi) Time (min) Leakage Actual Load, (lb) Shear at joint, (lb) 555 222 1059 345 2397 1088 3775 1664 Remarks 9

4000 5000 6000 7000 8000 10,000 12,000 Remarks Up to 7 psi Total No 6.5 hrs. 4433 1808 5430 2124 6483 2433 7432 2713 8414 3005 10367 3717 12581 4588 Maximum load 12581 lb. Maximum shear 4588 lb 5.2 Test No. 2. (Clay Pipe Joint No. 2) METHOD A: Straight Pipe Joint Test (Fig. 1 (a)) The results of the test are summarized in Table 3. was observed at the joint during the total test period of 30 minutes with maximum hydrostatic pressure of 7 psi for 10 minutes. 10

METHOD B. (Angular Deflection Test) (Fig. 1 (b)) Initial test was done at 0.5 degree. After this test, there was rotation of the joint which increased the angular deflection to more than 1.6 degrees thereby passing the 1.0 and 1.5 position. The University of Houston staff determined that, since there was no joint age at 1.6 degrees, it would be unnecessary to test the joint at 1.0 and 1.5 degrees, thus reducing the total time for the test. So only 0.50 and 2.0 degree tests were performed in the test. The testing time under each angle was 30 minutes with maximum hydrostatic pressure of 7 psi for 10 minutes.the results of the test are summarized in Table 3. No water was observed at the joint during the total test period of 1.5 hrs. The separations at the invert of the joint were 0.59 and 1.82 at the beginning and the end of the test respectively. This didn t lead to any during the period of the test. It must be noted that some moisture observed on the pipe surface at the base of the bell near the joint, but not originating at the joint itself. The moisture collected on an absorbent tissue was weighted but no detectable amount could be determined. The relationship between the angle and the shear load applied at the joint (load cell 2, Fig. 1 (b)) is shown in Fig. 5. With the increase of the angle, the shear load decreased from 5,200 to 4,600 lbs at the joint. (c) METHOD C: Shear Load/Deflection Test (Fig. 1 (c)) The joint was tested under shear loading as specified in Method C (Appendix C). The load cell locations are shown in Fig. 1 (c). The load was applied at Load Cell No. 1 on the pipe and was increased in steps of 1,000, 2,000, 3,000, 5,000, 7,000, 9,000, 11,000 and 12,000 lbs. in the test. The testing time under each load was 30 minutes with maximum hydrostatic pressure of 7 psi. The maximum shear load at the joint was 4594 lbs. and no water was observed. The test results are summarized in Table 4. The Shear load at the pipe joint vs. Applied load on Load Cell 1 is shown in Fig. 6. was observed at the joint during the total test period of 6.5 hrs.. Test No. 2 Summary The composite bladder performed as designed. Total testing time for Method A, B, and C were 0.5 hour, 1 hours and 6.5 hours respectively. was observed at the tested joint for all testing conditions. The maximum applied shear load at the joint was 4594 lbs.(over 150 lbs/in. diameter) and there was no water. 11

8000 7000 Shear Load at Joint, lb 6000 5000 4000 3000 2000 1000 0 0 0.5 1 1.5 2 2.5 Angle, o Figure 5. The Relationship between Angle and Applied Load in Test No. 2 Table 3. Results from Straight and Angular Deflection Tests (Test No. 2) Method Angle ( o ) A 0 B 0.5 2.0 Pressure (psi) Time (min) Leakage No Leak Remark Up to 2 o 3 to 7 psi Total 1.5 hrs Remarks Total testing time was 30 minutes. No age was observed. Total testing time was 30 minutes. No age was observed. The gap at the bottom of the joint was 0.59. The angle increased to 1.6 degree after the test Total testing time was 30 minutes. No age was observed. The gap at the bottom of the joint was 1.82. The angle increased to 2.6 degree after the test Bladder performed as designed 12

Table 4. Results from the Shear Load Test (Test No. 2) Intended Load (lb) 1000 2000 3000 5000 7000 9000 11000 12,000 Remarks Up to 7 psi Pressure (psi) Time (min) Leakage Total No 6.5 hrs. Actual Load, (lb) Shear at joint, (lb) 1589 570 2651 838 3472 1183 5562 1998 7593 3097 9635 3888 11416 4198 12436 4594 Maximum load 12436 lb. Maximum shear 4594 lb Remarks 13

6000 H 5000 Shear Load at the Joint, lb 4000 3000 2000 1000 0 0 2000 4000 6000 8000 10000 12000 14000 Applied Load, lb Figure 6. Applied Load vs. Shear Load in Test No. 2 6. CONCLUSIONS The testing of the 30-in. daiameter clay pipe-joints was performed in the CIGMAT Laboratory at the University of Houston, Houston, Texas. Based on the two joints tested the following conclusions are advanced. 1. Straight Test: There was no age at the 30-in. clay pipe-joint when the joint was tested without any external loading for a total testing time of 30 minutes. 2. Shear Test: The joint was subjected to a maximum shear force of 4800 lb. (equivalent to 153 lb/in diameter) and there was no age. The total testing time for each joint was 6.5 hours. 3. Angular Test: During the angular test, the joint was subjected to a maximum rotation of 2 o at the joint. The total testing time was 4.5 hours and the shear load at the joint varied from 4,600 to 8,000 lbs. during the angular test. There was no water age. 14

7. REFERENCES [1] Annual Book of ASTM Standards (2000), Section 4 (Construction) and Section 8 (Plastics), ASTM, Philadelphia, PA. [2] Water Environment Federation (1999), Control of Infiltration and Inflow in Private Building Sewer Connections, WEF, Alexandria, VA. 15