research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report

Similar documents
Thermal Response of a Highly Skewed Integral Bridge

DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE

Semi-Integral Abutment Bridges

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and

Effect of Pile Orientation in Skewed Integral Abutment Bridges

Thermal Response of Integral Abutment Bridges With Mechanically Stabilized Earth Walls

Integral bridges and environmental conditions

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

Integral Abutment Bridge Design with Soil Structure Interaction

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY

Modified Sheet Pile Abutment for Low-Volume Road Bridge

Forces in Wingwalls from Thermal Expansion of Skewed Semi-Integral Bridges

Figure 3: Analytic procedure

Integral Abutment Bridges Australian and US Practice

Appendix C Guidelines for Design of Integral Abutments March 3, 2003

Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures

APPENDIX A INTEGRAL ABUTMENTS

Update on Seismic Behavior and Design of

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

Ahmed Mongi, M.S., P.E. Engineering Division

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri

An Integral Abutment Bridge with Precast Concrete Piles

Instrumentation and Monitoring of Precast Bridge Approach Tied to an Integral Abutment Bridge in Bremer County

Design of Dingley Bypass Integral Bridges

THERMAL BEHAVIOR OF IDOT INTEGRAL ABUTMENT BRIDGES AND PROPOSED DESIGN MODIFICATIONS

THERMAL RESPO SE OF I TEGRAL ABUTME T BRIDGES WITH MSE WALLS: UMERICAL A ALYSES A D A PRACTICAL A ALYSIS TOOL

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA

2011 BRIDGE INSPECTION REPORT

Numerical analysis of the embedded abutments of integral bridges

Conditional assessment of Kiri Bridge in Shkoder, Albania

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014

BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE

Development of Preflex Composite Beam-Stub Abutment Integral Bridge System

Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways

OVER US 6 LATERAL BRIDGE SLIDE: I-75

Low-Volume Road Abutment Design Standards

Monitored Displacements of a Unique Geosynthetic-Reinforced Walls Supporting Bridge and Approaching Roadway Structures

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report

EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT

Evaluation of the Foundation and Wingwalls of Skewed Semi-Integral Bridges with Wall. Abutments. A thesis presented to.

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue

Four simply supported steel plate girders (appear to be an old railcar).

Geosynthetic-reinforced soil bridge abutments

STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END

State-Aid Bridge News August 2, 2005

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY

Integral Bridge Design - Derivation of the Spring Constant for Modelling the Soil-Structure Interaction

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY

Bahavior and Analysis of an Integral Abutment Bridge

PENNDOT e-notification

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection

Bank Erosion and Bridge Scour

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY

FHWA/IN/JTRP-2008/11. Final Report. Robert J. Frosch Michael E. Kreger Aaron M. Talbott

ILLINOIS INTEGRAL ABUTMENT BRIDGES: BEHAVIOR UNDER EXTREME THERMAL LOADING AND DESIGN RECOMMENDATIONS KURT PATRICK HOLLOWAY THESIS

MODIFICATION OF IDOT INTEGRAL ABUTMENT DESIGN LIMITATIONS

DESIGN ASSESSMENT OF THE FOUNDERS/MEADOWS GRS ABUTMENT STRUCTURE

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments

Keywords: integral abutment bridge, pile head abutment connection, finite element method.

Integral Abutment Bridges-Development of Soil Model for Soil Structure Interaction in Time History Analysis

The Development of Optimal On- Premise Electronic Message Center (EMC) Lighting Levels and Sign Lighting Measurement Techniques

The Pennsylvania State University. The Graduate School. Department of Civil and Environmental Engineering

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT

Precast Concrete Elements for Accelerated Bridge Construction

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure

Field Monitoring and Evaluation of Curved Girder Bridges with Integral Abutments

300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES

3/18/03 CE Keith P. Brabant, P.E.

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge

Modified Sheet Pile Abutments for Low-Volume Road Bridges

Emergency Bridge Stabilization at Mile Watrous Subdivision

Comparative Study of Behaviour of Integral and Bearing Type Bridge under Temperature Loading

Experimental investigation of axial load on low cycle fatigue performance of steel H piles in integral bridges

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse)

APPENDIX A - THE BEHAVIOR OF INTEGRAL ABUTMENT BRIDGES

Experimental and Analytical Investigation of UHPC Pile-to-Abutment Connections

Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3

PRELIMINARY GEOTECHNICAL DESIGN

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015

INTEGRAL ABUTMENT BRIDGES UNDER THERMAL LOADING: NUMERICAL SIMULATIONS AND PARAMETRIC STUDY

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION

CHAPTER 5 MODELING OF THE BRIDGE

Integral Bridge Design. Integral Bridge Design. in Midas Civil. Midas UK

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS

NCAT Report Comparing Friction Reducers for Use in AMPT Testing. By Adam Taylor, P.E. Nam Tran, Ph.D., P.E., LEED GA

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION

Extending Integral Concepts to Curved Bridge Systems

Field and Analytical Studies of the First Folded Plate Girder Bridge

Design Considerations for Integral Abutment/ Jointless Bridges in the USA

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER

Appendix B. Shallow Foundations Report

Structural health monitoring of the reinforced concrete plug joint system for existing concrete bridges

Field Reconnaissance on the Damage of Transportation Facilities in the 2007 Niigata Chuetsu-oki Earthquake

DULLES CONNCECTOR ROAD SOUND WALL PROJECT FUNDAMENTALS OF TRAFFIC NOISE AND RESULTS. Paul M. Kohler Noise Abatement Program Manager

Experimental Evaluation of Seismic Pounding at Seat- Type Abutments of Horizontally Curved Bridges

Transcription:

Final Report VTRC 06-R35 Virginia Transportation Research Council research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report http:/www.virginiadot.org/vtrc/main/online_reports/pdf/06-r35.pdf EDWARD J. HOPPE, Ph.D., P.E. Senior Research Scientist Virginia Transportation Research Council, 530 Edgemont Road, Charlottesville, VA 22903-2454, www.vtrc.net, (434) 293-1900

Standard Title Page - Report on Federally Funded Project 1. Report No. 2. Government Accession No. 3. Recipient s Catalog No. FHWA/VTRC 06-R35 4. Title and Subtitle 5. Report Date Field Measurements on Skewed Semi-Integral Bridge with Elastic Inclusion: June 2006 Instrumentation Report 6. Performing Organization Code 7. Author(s) Edward J. Hoppe, Ph.D., P.E. 8. Performing Organization Report No. VTRC 06-R35 9. Performing Organization and Address 10. Work Unit No. (TRAIS) Virginia Transportation Research Council 530 Edgemont Road 11. Contract or Grant No. Charlottesville, VA 22903 75447 12. Sponsoring Agencies' Name and Address 13. Type of Report and Period Covered Final: January 2006 May 2006. Virginia Department of Transportation FHWA 1401 E. Broad Street P.O. Box 10249 14. Sponsoring Agency Code Richmond, VA 23219 Richmond, VA 23240 15. Supplementary Notes 16. Abstract This project was designed to enhance the Virginia Department of Transportation s expertise in the design of integral bridges, particularly as it applies to highly skewed structures. Specifically, the project involves extensive monitoring of a semi-integral (integral backwall) bridge with a 45-degree skew. Long-term, continuous monitoring of strains developed in foundation piles, earth pressures exerted on the backwall by the adjacent approach embankment, and concrete buttress reactions preventing the superstructure from rotating in the horizontal plane will be performed. Overall, 120 strain gages, 16 earth pressure cells, and 2 high-capacity load cells, interfaced with electronic dataloggers, will be used in the study. This report provides a record of work carried out from the start of construction in January 2006 to the beginning of May 2006. It specifically describes the instrumentation of the bridge. Future reports will provide an analysis of the results of the field monitoring program. The study is expected to continue for the next 2 years in order to capture the bridge s response over a wide range of climatic conditions. 17 Key Words 18. Distribution Statement Skewed, semi-integral, integral backwall, integral bridge, No restrictions. This document is available to the public through monitoring, elastic inclusion, EPS. NTIS, Springfield, VA 22161. 19. Security Classif. (of this report) 20. Security Classif. (of this page) 21. No. of Pages 22. Price Unclassified Unclassified 14 Form DOT F 1700.7 (8-72) Reproduction of completed page authorized

FINAL REPORT FIELD MEASUREMENTS ON SKEWED SEMI-INTEGRAL BRIDGE WITH ELASTIC INCLUSION: INSTRUMENTATION REPORT Edward J. Hoppe, Ph.D., P.E. Senior Research Scientist Virginia Transportation Research Council (A partnership of the Virginia Department of Transportation and the University of Virginia since 1948) In Cooperation with the U.S. Department of Transportation Federal Highway Administration Charlottesville, Virginia June 2006 VTRC 06-R35

DISCLAIMER The contents of this report reflect the views of the author, who is responsible for the facts and the accuracy of the data presented herein. The contents do not necessarily reflect the official views or policies of the Virginia Department of Transportation, the Commonwealth Transportation Board, or the Federal Highway Administration. This report does not constitute a standard, specification, or regulation. Copyright 2006 by the Commonwealth of Virginia. ii

ABSTRACT This project was designed to enhance the Virginia Department of Transportation s expertise in the design of integral bridges, particularly as it applies to highly skewed structures. Specifically, the project involves extensive monitoring of a semi-integral (integral backwall) bridge with a 45-degree skew. Long-term, continuous monitoring of strains developed in foundation piles, earth pressures exerted on the backwall by the adjacent approach embankment, and concrete buttress reactions preventing the superstructure from rotating in the horizontal plane will be performed. Overall, 120 strain gages, 16 earth pressure cells, and 2 high-capacity load cells, interfaced with electronic dataloggers, will be used in the study. This report provides a record of work carried out from the start of construction in January 2006 to the beginning of May 2006. It specifically describes the instrumentation of the bridge. Future reports will provide an analysis of the results of the field monitoring program. The study is expected to continue for the next 2 years in order to capture the bridge s response over a wide range of climatic conditions. iii

FINAL REPORT FIELD MEASUREMENTS ON SKEWED SEMI-INTEGRAL BRIDGE WITH ELASTIC INCLUSION: INSTRUMENTATION REPORT Edward J. Hoppe, Ph.D., P.E. Senior Research Scientist INTRODUCTION The Virginia Department of Transportation (VDOT) has actively supported the construction of jointless bridges, primarily as an effective means of reducing life cycle maintenance costs. In addition to considering this type of design where feasible, VDOT, in cooperation with the Virginia Transportation Research Council (VTRC), has embarked on a process of revising office standards and producing new design guidelines for fully integral (integral abutment) and semi-integral (integral backwall) bridges. These efforts, aimed at optimizing the integral bridge design process, include field monitoring to evaluate the structure s performance during service and verify design assumptions. Over the past decade, VTRC conducted long-term monitoring projects of semi-integral bridges on Route 257 over Interstate 81 and on Route 60 over the Jackson River. 1,2 Field data collected over a period of several years were used to verify design assumptions and confirm the suitability of using elastic inclusion to reduce stresses and minimize the approach settlement. These projects involved a relatively small number of sensors placed at key structural locations. As the complexity of integral designs undertaken by VDOT increased over the years, so did the need for a more sophisticated field monitoring. This is especially true in cases involving skewed integral bridges, where the actual distribution of stresses acting on a structure in service is not very well documented. PURPOSE AND SCOPE This project was designed to enhance the Virginia Department of Transportation s expertise in the design of integral bridges, particularly as it applies to highly skewed structures. Specifically, the project involves extensive monitoring of a semi-integral (integral backwall) bridge with a 45-degree skew. Long-term, continuous monitoring of strains developed in foundation piles, earth pressures exerted on the backwall by the adjacent approach embankment, and concrete buttress reactions preventing the superstructure from rotating in the horizontal plane will be performed. Overall, 120 strain gages, 16 earth pressure cells, and 2 high-capacity load cells, interfaced with electronic dataloggers, will be used in the study.

This report provides a record of work carried out from the start of construction in January 2006 to the beginning of May 2006. It specifically describes the instrumentation of the bridge. Future reports will provide an analysis of the results of the field monitoring program. The study is expected to continue for the next 2 years in order to capture the bridge s response over a wide range of climatic conditions. METHODOLOGY Description of Bridge The project involves a replacement bridge on Route 18 over Blue Spring Run in Alleghany County, Virginia, as shown in Figures 1 and 2. Significant deterioration of the old bridge, as evidenced by corrosion, delamination, and increased scour susceptibility, was the main reason for this construction. The new semi-integral bridge is 110 ft (33.5 m) long, 42.7 ft (13 m) wide, with one-span steel girders, built at a 45-degree skew. There are no approach slabs constructed at the bridge approaches. The average daily traffic (ADT) is 1,706 vehicles with 2 percent trucks (2004 traffic data). 3 The design incorporates a 15-in-thick (38 cm) layer of elasticized expanded polystyrene (EPS) faced with a separation geotextile, installed at the integral backwall of Abutment A. The EPS serves as an elastic inclusion, effectively accommodating thermally induced movements of the superstructure while reducing the lateral earth pressures and minimizing the approach embankment settlement. Figure 3 shows the cross-section detail of Abutment A, with the elastic inclusion placed at the integral backwall. Figure 1. Old Bridge on Route 18 Over Blue Springs Run 2

Figure 2. Site Location and New Bridge Layout 3

Figure 3. Cross Section of Abutment A Instrumentation Electronic instrumentation installed at the bridge consisted of strain gages, earth pressure cells, and high-capacity load cells. The following tasks are planned: 1. monitoring of strains in foundation piles 2. monitoring of the load (reaction) required to restrain the superstructure from horizontal rotation attributable to a non-collinear force couple acting on the backwalls 3. monitoring of lateral earth pressures exerted on backwalls and wingwalls 4. monitoring of the thickness of the EPS layer at various ambient temperatures 5. monitoring of the shape of the concrete deck surface at various ambient temperatures. 4

The results of precise field surveys are expected to show how the bridge expands and contracts (along the long diagonal or the centerline). RESULTS The bridge replacement project was designed in two stages to allow for uninterrupted traffic flow on Route 18. Figures 4 through 7 show the progress of construction from January to May 2006. Figure 4. Foundation Piles at Abutment B Figure 5. Formwork for Abutment B 5

Figure 6. Placement of Structural Steel Figure 7. View of Completed Deck and Backwall Stage I construction began with pile driving in January 2006. HP10x42 piles were used for foundation support. Figure 8 shows a plan view of the instrumented piles. Each instrumented pile had two levels of Rocktest SM-5A vibrating wire strain gages welded prior to driving, as shown in Figure 9. Sensor layout is shown in Figure 10. The uppermost layer (Level 3) of sensors was added after the pile was installed, with the center of each gage placed at the abutment footing elevation. In all instrumented piles, the surface bound by gages 1 and 2 was oriented to face the structural fill of the adjoining embankment. 6

Figure 8. Layout of Foundation Piles Figure 9. Strain Gage Welded To to Foundation Pile 7

Figure 10. Strain Gage Layout Readings of the foundation pile strain gages were conducted as follows: 1. After the pile installation: initial baseline readings on 02/07/06 2. After the abutment construction: 03/02/06 3. After the steel girder placement: 03/09/06 4. After the concrete deck pour: 04/26/06. Figure 11 shows an example of data, reflecting increased loading, collected from one foundation pile strain gage. Figure 11. Example of Strain Gage Response 8

Figure 12 shows a Geokon Model 4900 vibrating wire load cell embedded into the Abutment B buttress. Its purpose is to measure the magnitude of the lateral load exerted by the adjacent superstructure as a result of thermally induced displacements. The load is transferred from the superstructure through a set of thick stainless steel rub plates that allow for transverse sliding while the load cell registers the axial force. A bearing plate is attached at the back of the load cell to distribute the load inside the abutment buttress. Initial baseline load cell readings were collected on April 26, 2006, with the superstructure in place, but with no backfill placed behind the backwall. Figure 13 shows two Geokon Model 4810 vibrating wire earth pressure cells installed on the integral backwall at Abutment B. There were also two earth pressure cells installed on the integral backwall and one on the wingwall of Abutment A. Initial baseline readings at five installed pressure cells were recorded on May 4, 2006. Figure 12. Load Cell at Abutment B Figure 13. Earth Pressure Cells at Abutment B 9

As of May 5, 2006, the installation of all sensors associated with Stage I of the bridge replacement project was completed. CONCLUSION The instrumentation was successfully installed on the skewed integral bridge on Route 18 over the Blue Springs Run. The monitoring is expected to provide meaningful feedback for optimizing future integral bridge designs. Data from earth pressure cells will be indicative of actual stresses exerted on the backwall by the adjoining embankment. Data from load cells will show how much lateral restraint is required to keep the skewed integral superstructure in place. Data from strain gages will show in-service stresses generated in the foundation piles. RECOMMENDATION 1. VTRC should continue field monitoring, data collection, and data analysis for at least 2 years following the opening of the bridge to traffic in order to capture the bridge s response over a wide range of climatic conditions. BENEFITS AND COSTS ASSESSMENT This study is expected to result in a more economical integral bridge design process, with potentially significant cost savings to VDOT. Field data will provide meaningful feedback to bridge designers, leading to a new generation of minimal maintenance bridges, detailed for inherent durability. ACKNOWLEDGMENTS The author expresses his appreciation to Park Thompson, Keith Weakley, and Eulogio Javier of VDOT s Staunton District Bridge Office for their helpful guidance in this study. Arthur Wagner of VTRC assisted with the sensor installation and field data collection. Linda DeGrasse of VTRC helped with data processing. Randy Combs, Ed Deasy, and Linda Evans of VTRC assisted with the graphics and the editorial process. REFERENCES 1. Hoppe, E.J., and Gomez, J.P. (1996). Field Study of an Integral Backwall Bridge (Report No. VTRC 97-R7). Virginia Transportation Research Council, Charlottesville. 10

2. Hoppe, E.J. (2005). Field Study of Integral Backwall with Elastic Inclusion (Report No. VTRC 05-R28). Virginia Transportation Research Council, Charlottesville. 3. Weakley, K.P., Virginia Department of Transportation. (2006). Personal communication. 11