Conditional assessment of Kiri Bridge in Shkoder, Albania

Similar documents
2011 BRIDGE INSPECTION REPORT

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report

Four simply supported steel plate girders (appear to be an old railcar).

5 DAMAGE TO TRANSPORTATION FACILITIES

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

Integral Abutment Bridge Design with Soil Structure Interaction

Figure 3: Analytic procedure

DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE

Modified Sheet Pile Abutment for Low-Volume Road Bridge

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY

Semi-Integral Abutment Bridges

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT

AN EXPERIMENTAL INVESTIGATION ON BEHAVIOR OF RC PARAPET WALL OF ABUTMENT UNDER COLLISION

Keywords: integral abutment bridge, pile head abutment connection, finite element method.

Integral bridges and environmental conditions

PENNDOT e-notification

300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017

Shifting the Canning Bus Bridge Sideways

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue

CHAPTER 5 MODELING OF THE BRIDGE

OVER US 6 LATERAL BRIDGE SLIDE: I-75

DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA

Low-Volume Road Abutment Design Standards

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and

Effect of Pile Orientation in Skewed Integral Abutment Bridges

EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT

Ahmed Mongi, M.S., P.E. Engineering Division

Numerical analysis of the embedded abutments of integral bridges

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse)

Emergency Bridge Stabilization at Mile Watrous Subdivision

New AASHTO Bridge Inspection Process

Culvert Safety Inspection Report (CSIR)

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA

EFFECTS OF SPATIAL VARIATION OF SEISMIC INPUTS ON BRIDGE LONGITUDINAL RESPONSE

R-Group Finland Oy. RLS Lifting Sockets Technical Manual According to Eurocodes, EU Machinery directive 2006/42/EC and VDI/BV-BS 6205 CE Approved

State-Aid Bridge News August 2, 2005

Integral Abutment Bridges Australian and US Practice

Design of Picton Railway Overbridge for Mine Subsidence

APPENDIX A INTEGRAL ABUTMENTS

Independent Hybrid Corrosion Protection Appraisal

BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE

Critically damaged bridges & concepts for earthquake recovery

Bahavior and Analysis of an Integral Abutment Bridge

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39

Comparative Study of Behaviour of Integral and Bearing Type Bridge under Temperature Loading

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments

STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION

Architect/Contractor/QS/Sub-Contractor/C of W/RE/File ref PiMS Documents Site Visit Report. Item Text Action on

Winona Bridge Visual Quality Review Committee

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015

Integral Abutment Bridges-Development of Soil Model for Soil Structure Interaction in Time History Analysis

Appendix C Guidelines for Design of Integral Abutments March 3, 2003

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge

Rahvusvaheline puitarhitektuuri konverents

Monitored Displacements of a Unique Geosynthetic-Reinforced Walls Supporting Bridge and Approaching Roadway Structures

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri

Update on Seismic Behavior and Design of

The Pennsylvania State University. The Graduate School. Department of Civil and Environmental Engineering

Design of Dingley Bypass Integral Bridges

Integral Bridge Design - Derivation of the Spring Constant for Modelling the Soil-Structure Interaction

2017 UNDERWATER BRIDGE INSPECTION REPORT. TWP 332 over ROOT RIVER. Date of Inspection: Equipment Used: 10/22/2016. Town or Township Highway Agency

Structural Rehabilitation of Buildings

L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION

Integral Bridge Design. Integral Bridge Design. in Midas Civil. Midas UK

PRELIMINARY GEOTECHNICAL DESIGN

Pennsylvania s Experience with LRFD Implementation. By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation

Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways

1 Study the drawings and the installation. 2 Ensure that you have the correct components. 3 Follow the manufacturer s instructions

Geosynthetic-reinforced soil bridge abutments

Appendix B. Shallow Foundations Report

The Long Term Performance Of Skew Integral Bridges

Experimental and Analytical Investigation of UHPC Pile-to-Abutment Connections

Inspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin.

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure

Experimental investigation of axial load on low cycle fatigue performance of steel H piles in integral bridges

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint

Earthquake Resistance of Bridges With Friction Slab Abutments

Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures

COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES.

2007 Niigata Chuetsu-oki Earthquake, Field Reconnaissance Report

Structural health monitoring of the reinforced concrete plug joint system for existing concrete bridges

Technical Report Documentation Page

Retrofit to improve earthquake performance of bridge abutment slopes

Development of Preflex Composite Beam-Stub Abutment Integral Bridge System

Transcription:

Conditional assessment of Kiri Bridge in Shkoder, Albania Gentian Rexhaj 1, Enea Mustafaraj 2 1 2 Department of Civil Engineering, Epoka University, Albania 2 Department of Civil Engineering, Epoka University, Albania ABSTRACT The Kiri bridge is located 1 km in north-west of Shkoder city and it is the only connection for the city of Shkoder and the Vau i Dejes hydropower station. It is a reinforced concrete bridge with 8 spans, 2 sidewalks and steels parapets on both sides. In this paper general evaluation of the bridge s current structural conditions and the ability of the bridge to withstand loads from the vehicular traffic are examined. The methodology used in this study consists of the proper definition of the bridge s structural elements and field inspection of each of them. Deterioration of the structural elements, damage of the paving, parapets and expansion joints are observed at a great extent. The other identified defects are recorded in an inspection form. As a result, the overall conditions were rated 6/10. In this paper some precautions and further measures to be taken are suggested. INTRODUCTION After the declaration of the Albanian state in 1912, there have been built many new roads and bridges. The construction of these structures has been carried out during different time periods and different construction codes such as the Soviet code, Albanian Standard and Code (KTP 23-78) as well as AASHTO, BS Standards and Eurocodes have been used [1]. In the Albanian National Road Network there are found 562 bridges that span a length of 19295 meters across the country, many of them being in service for more than 35 years [12]. This bridge is called Kiri Bridge, is located 1 km in north-west of Shkoder city and connects Shkodra city and Vau i Dejes hydropower station (Figure 1,2). Figure 1. Aerial view of the bridge Figure 2. Entrance of the bridge 1194

It is a reinforced concrete bridge with 8 (eight) spans, 2 sidewalks and steels parapets on both sides, important to notice is in this bridge are passing railway and road vehicles two lines. Each pier has 4 piles with diameter 100 cm (Figure 3, 4). Figure 3. Railway Figure 4. Piers of the bridge The scope of this study is to prepare a general evaluation of the bridge s present ability to withstand loads from light vehicular traffic. INSPECTION PROCEDURE The purposes of the bridge inspection are [3]: a) to ensure public safety and confidence in bridge structural capacity b) to protect public investment and allow efficient allocation of resources c) to effectively schedule maintenance and rehabilitation operations d) to provide a basis for repair, replacement, or other improvements such as retrofit railings e) to ensure that national funding will remain available for bridge rehabilitation and replacement. According to US Bridge Inspection Manual, bridges should be inspected every two years but the frequency may be increased depending on the structural conditions of the considered bridge [3]. Bridge inspection consists of defining the elements (structural parts of the bridge) and total quantities that exist at each bridge. The condition of each element is determined by performing a field inspection and recording quantities of the element that have identified defects that correlate to the severity of the defects. The condition assessment is complete when the appropriate portion of the total quantity is stratified over the defined condition states [4-9] For agencies utilizing bridge management systems, the appropriate element Smart Flags and environment shall be recorded for use in deterioration modelling. INSPECTION RESULTS The bridge is an eight-span bridge, having two concrete abutments on each side of the river and a four group pile foundation, superstructure composed by 80 beams and the deck slab. The deck slab in the area between the beams has variable thickness, being thicker adjacent to the beams and thinner at the central axis parallel to the beam axes. 1195

Figure 5. Description of the elements of the bridge. All beams are supported on the flat bearing steel plates on both ends, joined with the bearing shelf on the left side abutment. The bridge has two lanes. One line has width of 4 m. There are parapets on both sides of the bridge for safety of people. The overall inspection process of Kiri Bridge consists of four stages. The first stage is the identification bridges elements. These elements are divided in superstructure and in substructure: a) Superstructure Inspection. Superstructure Inspection is focused on beams, gears, cable, sidewalks, parapets, wearing course and expansion joints. b) Sub-structure Inspection. Sub-structure Inspection is focused on piles, cap, piers, piers cap, columns, and abutments. During the second stage the quantity of the elements are collected. In the third stage to description of the defects is conducted, and in the fourth stage ranking of the defects noticed during inspection is performed. After the condition assessment of the Kiri Bridge, the following problems were observed: Cracking of the concrete: Accurate inspection was undertaken to detect cracking on the concrete surface of the beams and deck slab. The inspection team looked for cracks all over the superstructure of the bridge. Apart from some cracks at the end parts of the beams and of the slab resulting from additional compression stresses in the concrete elements due to additional forces being induced by earth pressure produced by the landslide, there are no cracks in the superstructure reinforced concrete elements, such as beams and deck slab. 1196

The superstructure seems to be in good condition, with the exception of some minor damages at the ends of the beams caused by overstressing from the contact stresses during the landslide. Spall of concrete The results from the inspection showed that spalling has occurred in some parts of the concrete as a due to slipping of the structure from its supports. As it can be seen from the figures (Figure 6,7), this phenomenon is more emphasized at the ends of the beams, where the beams have slipped over the bearing shelves or over the abutments. No spalling of the structural elements was detected to have been caused by overstressed compressed concrete or by the corrosion expansion. Figure 6. Spall of concrete Figure 7. Spall of concrete. However, there was something that attracted the attention of the inspection team that was worth remarking. The spaces between the main longitudinal tensile steel bars reinforcements did not fulfill the required parameters set according to the standard. [4] This space was way too small, and thus preventing the concrete layer from filling the bottom part of the beams. The concrete cover layer of the main reinforcement bars at the bottom of the beam is damaged in some parts of the beam facilitating the corrosion of steel bars. As it can be seen, the lack of concrete cover layer is not a result of spalling of concrete. Corrosion of reinforcement No corrosion was detected except from those parts of steel reinforcement bars exposed to the environment due to lack of concrete cover layer as a result of inappropriate spacing of the bars. Quality of the concrete Not possessing the original detailed drawings and technical specifications, the analogy has been made with all the other existing bridges for which detailed drawings and technical specifications were found. Based on this analogy, the concrete for the superstructure should have been M-200 for the supports (bearing shelves) and M-150 for the abutments and M-100 for the wing walls. 1197

Non destructive tests were conducted to roughly establish the concrete cubic compression strength of different structural elements of the bridge. The cubic compression strength was measured by non destructive tests made by using KRS-D845 instrument [5]. Based on the results of the tests, there is no doubt about the concrete quality of the superstructure. Despite the fact that the concrete for the superstructure has been cast in place (no prefabricated structure is used), the compression strength of the concrete seems a little bit higher than that usually used for this kind of structure. It exceeds the prescribed value of the project which is M-200, which corresponds to the cubic compression strength equal to 200 Kg/cm 2 after 28 days. This probably is due to the hardening of the concrete during the years. The concrete material in the beams and deck slab is well compacted and some small parts at the bottom of the slab have been plastered with cement mortar to cover the steel reinforcement bars, which probably remained uncovered when the wooden scaffolding had been taken off. Chemical attack Chemical attack on the concrete has been detected on structure. There exists on all air pollutant in the region and the environmental conditions are very good for preserving the concrete quality. Abutment, abutment foundation and wing walls inspection The vertical supporting structural elements of the bridge, i.e. the abutment foundations, the abutments, pile foundation, footing cap and the wing walls of the bridge were checked. After the inspection, the following problems were observed: Cracking of the concrete The inspection team searched for cracks all over the superstructure of the bridge. There were detected different cracks in the upper part of the abutments as well as the presence of some horizontal cracks related to additional normal end shear stresses in the concrete elements caused by horizontal forces applied on the top of the abutments due to friction between superstructure and the support and, later on, applied also on the ballast wall by beam s ends when the ballast wall blocked the displacements of free ends of the superstructure preventing further slipping of them over the bearing shelves. The horizontal forces were result of additional earth pressure produced by the landslide. There are two other major wide cracks on the left abutment (Figure 8,9). Both of them are a consequence of the forces induced to the bearing shelf by the beams during the rotation of the superstructure around its central vertical axis as the result of the direction of the earth pressure caused by the landslide. 1198

Figure 8. Figure 9. The crack openings are relatively wide (less than 1cm) and, apart from the possibility of damage of the concrete during the winter, there may be no further effects on the stability and bearing capacity of the structure. Because the abutment resists a compressive load, the cracks mentioned above will tend to close when they will be resisting bigger loads. Quality of the concrete As for the superstructure, in order to define the concrete grade, analogy has been made with all the other existing bridges for which drawings and technical specifications were found. Based on this analogy, the concrete for the superstructure should have been M-200 for the supports (bearing shelves) and M-150 for the abutments and M-100 for the wing walls, being M for type and 200 corresponding to the cubic compression strength expressed in Kg/cm 2 after 28 days from the day of preparation of the mix. Despite the fact that the concrete for the structure has been cast in place and that coarse material has been used to prepare the mix, the compression strength of the concrete seems a little bit higher than the value prescribed in the project. This is probably due to the hardening of the concrete during the years. Erosion The water-flow mixed with the solid materials produced by the waterway of the bridge has caused the erosion of the concrete at the basement of the abutment and pile as well as the concrete of the abutment itself. Although this kind of damage does not appear to be seriously affecting the stability of the bridge, a long term solution should be found for the new bridge to be built. Superstructure integrity and its bearing capacity The superstructure does not bring serious visible signs of damage. Hence, from a structural point of view, the bearing capacity of the superstructure has remained the same as the one calculated by the designers at the time of the construction of the bridge. This means that the bridge can be crossed by trucks having a total weight of 25 tons and by crawler vehicles weighting not more than 80 tons. 1199

Abutments integrity and their bearing capacity Although the concrete quality is almost decent and, apart the lose material of the basement on left side abutment, as the result of serious damages caused by the erosion of the water flow to the abutment and to its foundation, the integrity of the structure is guaranteed. The bridge can be considered on use if we refer to the standard. The foundation of the right side abutment is in good condition. As a result, it can be said that there are no integrity problems for the superstructure. However, this is not the case for abutments. The left side abutment lacks overall integrity and cannot be considered a bearing structure without appropriate rehabilitating intervention on basement. The left abutment has a major cracks as a result of load on the superstructure and caused by lose of material on basement foundation. Although the cracks are developing under the normal vertical loads (superstructure self weight and traffic loads). Figure 9. Damage of the column Figure 10. Damage of the piles CONCLUSIONS The inspection results have shown that the overall structural conditions of Kiri Bridge are below the average, a rate of 6 (six). In Table 1, the severity conditions of the structural elements are shown: Table 1. Bridge rating elements (1= best condition, 10 = worst condition) No. Element Name Rating 1 Wearing surface 3 2 Expansion joints 7 3 Deck 5 4 Parapets 7 5 Paint 6 6 Bearings 7 7 Abutments 6 8 Abutment foundation 5 1200

9 Reinforced concrete beam 7 The abovementioned problems should be resolved in order to improve the overall structural capacity of Kiri Bridge. REFERENCES [1] Periku, E. (2012) Bridge Assessment in Albania, MSc Thesis, Epoka University. [2] Delegation of the European Commision to Albania (2010) "Albanian Bridge Asset Management System Manual Introduction & Overview", Ref: EuropeAid/127796/C/SER/AL [3] Bridge Inspection Manual (2002) Texas Department of Transportation [4] Bridge Maintenance, Planning, and Repair Handbook - Defines standard maintenance and repair details. [5] AASHTO Movable Bridge Inspection, Evaluation and Maintenance Manual - Provides guidelines for the inspection, preventive maintenance, operation and repair of moveable bridges. This document is available from the American Association of State Highway and Transportation Officials (AASHTO), 444 North Capitol Street, N.W., Suite 249 Washington, D.C. 20001. This document is not available from the Department. [6] Bridge Work Order Handbook Provides instructions for the processing of data collected by Bridge Inspectors. [7] Bridge Inspectors Field Handbook Provides guidance for inspectors in selecting elements and assigning quantities to condition states for selected elements. [8] Recording and Coding Guide for the Structure Inventory and Appraisal of the Nation s Bridges Provides instructions for coding data items required by the Federal Highway Administration. This document is available from the Federal Highway Administration and a link is provided from the State Maintenance Office Infonet site to an electronic version of this document. [9] AASHTO Bridge Element Inspection Manual 1st Edition, 2010. 1201