UE 335 Marginal Cost of Service

Size: px
Start display at page:

Download "UE 335 Marginal Cost of Service"

Transcription

1 UE 335 / PGE / 1200 Macfarlane Goodspeed BEFORE THE PUBLIC UTILITY COMMISSION OF THE STATE OF OREGON UE 335 Marginal Cost of Service PORTLAND GENERAL ELECTRIC COMPANY Direct Testimony and Exhibits of Robert Macfarlane Jacob Goodspeed February 15, 2018

2 Table of Contents UE 335 / PGE / 1200 Macfarlane Goodspeed / i I. Introduction and Summary... 1 II. Generation Marginal Cost Study... 2 III. Transmission Marginal Cost Study... 5 IV. Distribution Marginal Cost Study... 7 V. Customer Service Marginal Cost Study VI. Area and Streetlights VII. Qualifications List of Exhibits UE General Rate Case Direct Testimony

3 I. Introduction and Summary UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. Please state your names and positions. A. My name is Robert Macfarlane. I am Interim Manager, Pricing and Tariffs for Portland General Electric Company (PGE). I am responsible, along with Mr. Goodspeed, for the development of the marginal cost studies. My name is Jacob Goodspeed. I am a Senior Regulatory Analyst in Pricing and Tariffs for PGE. I am also responsible for the development of the marginal cost studies. Our qualifications are included at the end of this testimony. Q. What is the purpose of your testimony? A. Our testimony describes the methodologies and results of PGE s generation, transmission, distribution, customer service, and street lighting marginal cost of service studies. PGE Exhibit 1201 provides a summary of these marginal costs by component. The summary lists costs by PGE rate schedule for generation capacity and energy, transmission, subtransmission, substation, feeder backbone and tapline, transformers, service laterals, meters, and customer service costs. Rate schedule changes are discussed in PGE Exhibit Q. What is the purpose of the distribution and customer marginal cost studies? A. The purpose is to calculate the incremental or marginal unit cost of service for various categories (e.g., distribution substations, feeders, billing). These unit costs, expressed as costs per customer, costs per kilowatt (kw) of demand, or costs per kilowatt hour (kwh) are then used to allocate the functional revenue requirements as described in PGE Exhibit UE 335 General Rate Case Direct Testimony

4 II. Generation Marginal Cost Study UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. What methodology do you propose in this docket? A. We propose a long-run generation methodology that explicitly takes into account the cost of marginal generation capacity, long-run marginal energy costs, and renewable energy requirements. Q. Please describe the steps used to develop the long-run generation allocation methodology. A. The generation marginal cost analysis involves the following inputs and steps: 1. Determine both a long-run marginal energy cost and a long-run marginal capacity cost by first defining the marginal long-run generation resource as a combined cycle combustion turbine (CCCT) used to provide both energy and capacity. 2. From this analysis, separately estimate the capacity and energy components as follows: a. Estimate the marginal cost of future capacity as the fixed cost of an Fclass simple cycle combustion turbine (SCCT). b. Use these SCCT fixed costs as the portion of the CCCT fixed cost that is assigned to capacity with the remaining CCCT fixed costs assigned to energy. c. Add 17% reserve requirements to the SCCT capacity costs consistent with PGE s 2016 Integrated Resource Plan (IRP). 3. Finally, express the capacity and energy values in real levelized terms. UE 335 General Rate Case Direct Testimony

5 UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. Has the methodology used to develop the long-run generation allocation changed since PGE s 2018 General Rate Case filed as Docket No. UE 319? A. No. Q. What are the sources of the overnight capital costs for the resources used in the model? A. PGE s 2016 IRP is the source of the overnight capital costs 1 used in the analysis. Q. Please describe how you determined the proportion of marginal energy costs attributable to the CCCT and the generic wind farm. A. We weighted the marginal energy cost by the Renewable Portfolio Standard (RPS) target percentages for each year. For example, if the RPS target is 20% in a given year, the weighting is 20% wind and 80% thermal. The weightings reflect the revised RPS targets included in Senate Bill Q. What is the source of your long-term gas price forecast? A. We used the Wood Mackenzie long-term gas price forecast dated November 2017 for the Sumas and AECO hubs, blended with near-term forward curves. We equally weighted the projected burner tip prices from these two hubs. Q. Did you include the projected costs of carbon dioxide compliance in your analysis? A. No. On both the national and state level, no carbon tax exists. Any potential future carbon tax is uncertain. The exclusion of carbon tax from this analysis is consistent with the treatment of carbon tax for purposes of PGE s avoided cost calculations used in Tariff Schedule Cost of the project as if no interest were included during its construction th Oregon Legislative Assembly, 2016 Regular Session UE 335 General Rate Case Direct Testimony

6 UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. Did you include production tax credits in your analysis? A. Yes. A production tax credit value of 60% was used, based on a resource that commences construction in Q. What is the fully allocated cost of the wind farm? A. The cost of the generic wind plant exclusive of wheeling is estimated at $42.05 per megawatt hour (MWh) in real levelized 2019 dollars. Q. How did you estimate each rate schedule s long-run marginal cost of energy? A. We multiply each schedule s monthly on-peak and off-peak load forecast by the corresponding monthly on-peak and off-peak long-term energy value. Q. How do you shape the annual long-run marginal cost of energy into monthly on-peak and off-peak values? A. We shape the annual long-run marginal energy cost into monthly on-peak and off-peak values based on the monthly on-peak and off-peak Mid-Columbia forward prices used in PGE s net variable power cost model (i.e., the Multi-area Optimization Network Energy Transaction model, also known as MONET 3 ). 3 See PGE Exhibit 300 for a description of MONET. UE 335 General Rate Case Direct Testimony

7 III. Transmission Marginal Cost Study UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. Have you performed a transmission unit marginal costs analysis for this docket? A. Yes. The methodology is the same as that used in UE 319. Based on the transmission project, contained in PGE Exhibit 1202, we calculate a unit marginal cost of $11.98/kW. 4 Q. Is PGE a transmission-dependent utility? A. Yes. PGE is a transmission-dependent utility that purchases about 3,700 megawatts (MW) of transmission from Bonneville Power Administration (BPA) to integrate its generation and purchased power. PGE operates a limited transmission system comprised of approximately 268 pole miles of 500 kilovolts (kv) lines and 270 pole miles of 230 kv lines, some of which is functionalized to generation. At the 230 kv level, the system ties into seven BPA bulk power substations around the Portland area. PGE also has ties into three BPA bulk power substations in the Salem area. The primary function of the 230 kv system that is functionalized to transmission is to provide an interface to the main grid for load service. Q. What drives additions to PGE s existing transmission system? A. PGE s transmission planners evaluate whether additions to PGE s existing transmission system are needed to meet North American Electric Reliability Corporation (NERC) and Western Electric Coordinating Council (WECC) reliability standards for serving customers on the basis of 1-in-3 peak load conditions during the summer and winter 20 seasons for both the near term and the long-term. 5 The winter period is defined as 4 The transmission marginal cost value is shown in the provided transmission marginal cost study. 5 Ibid, page 6. UE 335 General Rate Case Direct Testimony

8 UE 335 / PGE / 1200 Macfarlane Goodspeed / November 1 st through March 31 st, and the summer is defined as June 1 st through October 31 st, therefore ten months in all. Because the transmission planners use ten months of peak loads when evaluating reliability, we extend the peak load criteria slightly to twelve months when calculating unit marginal costs. A twelve month criteria, or twelve coincident peak (12CP) is also consistent with how the Federal Energy Regulatory Commission (FERC) determines PGE s Open Access Transmission Tariff prices. UE 335 General Rate Case Direct Testimony

9 IV. Distribution Marginal Cost Study UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. Which marginal distribution costs do you calculate? A. We calculate marginal distribution costs separately for subtransmission, substations, distribution feeders (backbone facilities and local facilities), line transformers (including services), and meters. Q. How do you calculate the marginal unit costs of subtransmission and substations? A. We calculate the subtransmission unit costs using the subtransmission marginal investment cost from UE 319 escalated for inflation. We calculate substation marginal costs using a recent engineering estimate of the cost to construct a substation. We then divide the cost by the substation transformer capacity in kw, and annualize the cost per kw. Customers served at subtransmission voltage are excluded from this calculation because they supply their own substation. Columns (B) and (C) in PGE Exhibit 1201, page 3, summarize subtransmission and substation costs. Q. How do you calculate the marginal unit feeder costs? A. We estimate distribution feeder unit costs in the following manner: 1. Perform an analysis that places customers by class on the distribution feeder from which they are currently served. 2. Eliminate any distribution feeders from which we cannot obtain customer information, and which do not conform to typical standards. Examples of these non-typical feeders are feeders serving customers at 4 kv, and feeders that serve downtown core areas. UE 335 General Rate Case Direct Testimony

10 UE 335 / PGE / 1200 Macfarlane Goodspeed / Perform an inventory of the wire types and sizes for each feeder. Standardize these wire types and sizes to current specifications and then calculate the cost of rebuilding these feeders in today s dollars. 4. Segregate the wire types and sizes into mainline feeders and taplines. Mainline feeders are typically capable of carrying larger loads and are generally closer to the substations from which they originate. Taplines are typically capable of carrying smaller loads and can be remote from substations. 5. For each feeder, allocate the mainline cost responsibility of each customer class based on the customer class s proportionate contribution to noncoincident peak (NCP). Calculate a unit cost per kw by totaling the feeder cost responsibilities and dividing by the sum of each class s NCP. 6. For each feeder, allocate the tapline cost responsibility of each customer class based on its proportionate design demand (estimated peak at the line transformer). Calculate a unit cost per kw for both poly- and single- phase customers by totaling the feeder cost responsibilities and dividing by the sum of each schedule s design demand. 7. Annualize the mainline and tapline unit costs by applying an economic carrying charge. 8. Separately estimate the unit costs of customers with peak loads greater than 4 MW who are typically on dedicated distribution feeders. Calculate these marginal unit costs (per customer) as the average distance between the UE 335 General Rate Case Direct Testimony

11 UE 335 / PGE / 1200 Macfarlane Goodspeed / substation and the customer-owned facilities. Finally, apply the annual carrying charge to annualize the cost per customer. 9. Separately estimate the per-customer costs of customers served at subtransmission voltage. This is done by first calculating the average distance from the point at which subtransmission voltage customers connect into the subtransmission system from their substation. Then we multiply this average distance by the current cost per wire mile and annualize the costs. Columns (D), (E), and (F) on page 3 of PGE Exhibit 1201 summarize feeder mainline and tapline costs. Q. Why do you propose to calculate the marginal costs of feeders on the basis of class size rather than by rate schedule? A. We propose this because past marginal feeder costs analyses have resulted in extremely high unit marginal costs for the irrigation Schedules 47 and 49 due to their preponderant location on remote feeders within PGE s service territory. This cost result for the irrigation schedules seems to be due to geographical distinction rather than due to economies of scale. Because PGE does not price by geographical area, we propose the class size distinction when calculating unit marginal feeder costs. For all other marginal cost categories, we separately measure the unit marginal costs of the irrigation schedules. Q. Please describe any other considerations in calculating unit feeder costs. A. Currently, many municipalities require undergrounding of taplines within subdivisions and commercial areas. Therefore, we used the current cost of underground facilities exclusively in our marginal feeder tapline cost calculations. UE 335 General Rate Case Direct Testimony

12 UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. How do you calculate marginal transformer and service costs? A. We calculate each schedule s marginal transformer and service costs by estimating the cost of providing the average customer within specific load sizes with a service lateral and a line transformer (secondary delivery voltage only). For smaller customers such as those on Schedules 7 and 32, we estimate the average number of customers on a transformer in order to appropriately calculate the per customer share of transformer costs. Column (G) on page 3 of PGE Exhibit 1201 summarizes transformer and service costs. Because primary and subtransmission voltage customers supply their own transformer and service laterals, the marginal cost for these customers is zero. Q. Please describe how you calculate the marginal costs of meters. A. We calculate marginal meter costs as the weighted installed cost of an Advanced Metering Infrastructure (AMI) meter for each rate schedule or load size, and then apply an annual carrying charge. Column (H) on page 3 of PGE Exhibit 1201 summarizes meter costs. Q. How do you allocate distribution operations and maintenance (O&M) to each distribution category and ultimately to each rate schedule? A. We allocate test-period distribution O&M by distribution category to the rate schedules in proportion to each schedule s respective usage and per unit marginal capital cost. All of the distribution costs by functional category, on page 3 of PGE Exhibit 1201, are inclusive of test-period distribution O&M. UE 335 General Rate Case Direct Testimony

13 UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. The UE 319 Partial Stipulation required PGE to evaluate the marginal capital costs of primary and secondary Distribution Facilities and the maintenance costs contained in FERC Account Nos. 583, 584, 593, and 594 and estimate the amounts attributable to secondary voltage service conductors, secondary voltage conductors, and primary voltage conductors. Has PGE met this requirement? A. Yes. In consultation with Service and Design Project Managers, who in turn spoke with field personnel, we estimated the percentage of time field personnel spend on maintaining secondary service conductors. After estimating the approximate $6.1 million costs of maintaining secondary service conductors by the appropriate Accounting Work Order (AWO), we deduct the estimated secondary service conductor maintenance cost amounts from the total of the FERC maintenance amounts. Then, for the appropriate cost categories, we allocate the amount of expense attributable to primary voltage and secondary voltage conductors by the objective measure of relative circuit wire miles. This decomposition of the FERC maintenance accounts is contained in the feeder O&M work papers accompanying this filing. In addition to the allocation of maintenance costs described above, we reassigned approximately $60,000 in transformer costs from overhead and underground line maintenance to the transformer maintenance account. Column (F) on page 3 of PGE Exhibit 1201 summarizes secondary distribution facilities costs. Q. Please explain how this impacts the maintenance cost of secondary conductors. A. PGE allocates its projected test period distribution feeder maintenance costs on the basis of each schedule s marginal costs; hence, attributing primary voltage and UE 335 General Rate Case Direct Testimony

14 UE 335 / PGE / 1200 Macfarlane Goodspeed / secondary voltage conductor maintenance costs separately will result in changes in how test period distribution feeder maintenance costs are allocated to the rate schedules. Primary voltage conductor maintenance costs are allocated to mainline feeders and local facilities. Secondary voltage conductor maintenance costs are allocated to local facilities based on the estimated percentage of secondary voltage conductors serving each rate schedule. This results in higher allocated test period maintenance costs to customers using secondary facilities. UE 335 General Rate Case Direct Testimony

15 V. Customer Service Marginal Cost Study UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. What is the purpose of the customer service marginal cost study? A. The purpose is to calculate the incremental cost of customer service for each rate schedule. PGE incurs costs in managing its relationship with customers, including handling customer communications, measuring usage, maintaining records, and billing. As such, customer service costs increase as the number of customers PGE serves increases. Column (I) on page 3 of PGE Exhibit 1201 summarizes marginal customer costs. Q. Does PGE use the forecasted test year expenses in the customer marginal cost study? A. Yes. PGE uses forecasted costs for the 2018 test period and 2017 actual costs to develop the 2019 test year Customer Service Marginal Cost Study. These costs are found in FERC Account Nos. 902, 903, 905, 908, and 909. The 2019 forecasted costs are also referred to as budget amounts in this testimony. Q. Is the study s methodology the same as in PGE s last rate case UE 319? A. Yes, the methodology is the same. As in UE 319, the costs are allocated by PGE accounts directly on the basis of cost causation. A few accounts are allocated based on a sub-allocation of the other account costs. After the costs are spread across rate schedules, the final result is marginal costs for each rate schedule by each of the three functionalized categories: metering, billing, and other services. UE 335 General Rate Case Direct Testimony

16 UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. Please provide an example of how you calculate metering marginal costs. A. The 2019 forecasted amount for FERC Account No. 902, Field Collection Department, is allocated based on manual meter reads and a weighted percentage of customers (less unmetered lighting and signals). Q. Please provide examples of how you calculate billing marginal costs. A. Examples include: The costs for Retail Receivables and Field Collections are allocated based on percentage of adjusted write-offs by rate schedule. Customer Information System billing costs are allocated by the number of customers, except streetlights and traffic signals. The costs for Printing and Automated Mail Services are allocated based on the number of paper bills delivered. Network Data Operation costs are allocated based on the number of customers with meters, which excludes unmetered lighting and traffic signals. Q. Please provide examples of how you calculate other customer service marginal costs. A. Examples include: The budget amount associated with the Customer Contact Operations is allocated by the number of customers on rate schedules using up to 200 kw. The budget amount for the Direct Access Operations Department is allocated by the number of customers participating in the direct access program. UE 335 General Rate Case Direct Testimony

17 UE 335 / PGE / 1200 Macfarlane Goodspeed / The budget amount for the Special Attention Operations Department is allocated based on the number of residential customers. The Solar Payment Option and Net Metering Operations budget amounts are allocated by the number of customers participating in the programs. UE 335 General Rate Case Direct Testimony

18 VI. Area and Streetlights UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. Please describe how you price Area Lights and Streetlights. A. We price the investment portion (i.e., poles and luminaires) of providing lighting service using a real levelized annual revenue requirement. Lighting schedule prices will be updated to reflect the Cost of Capital adopted by the Commission in this proceeding. Q. Please describe how you calculate the amount of outdoor lighting maintenance. A. Similar to UE 319, we propose to base the test period lighting maintenance amount on the incurred maintenance amounts during PGE s most recent complete 5-year relamping cycle ( ), before conversion to Light-Emitting Diode (LED) area and streetlights commenced. More specifically, we express the historical maintenance amounts on a per-light basis, and then escalate this per-light maintenance figure for inflation. A further reduction is made for LED street and area lights since (1) their maintenance is significantly less than other lights, and (2) the years used in the most recent 5-year re-lamping cycle do not include LEDs. Following this, we allocate maintenance to each type of luminaire based on the marginal cost of maintenance study. Q. Do you provide a summary exhibit of the proposed pole and luminaire prices? A. Yes. This summary is provided in PGE Exhibit UE 335 General Rate Case Direct Testimony

19 VII. Qualifications UE 335 / PGE / 1200 Macfarlane Goodspeed / Q. Mr. Goodspeed, please state your educational background and qualifications. A. I received a Bachelor of Arts degree in Public Policy from Washington State University and a Master of Business Administration degree from the University of New Orleans. I accepted my current role at PGE in 2016, and have previously worked in Senior Pricing Analyst and Pricing Lead roles for Entergy Services, Inc., providing pricing and rate design support to Entergy Louisiana LLC., Entergy Texas Inc., Entergy New Orleans Inc., and Entergy Arkansas Inc. I have also served as a financial analyst in Entergy s nuclear organization. Q. Mr. Macfarlane, please state your educational background and experience. A. I received a Bachelor of Arts business degree from Portland State University with a focus in Finance. I have been Interim Manager, Pricing and Tariffs since January of My prior title was Regulatory Consultant. Since joining PGE in 2008, I have worked as an analyst in the Rates and Regulatory Affairs Department. My duties at PGE have included pricing, revenue requirement, Public Utility Regulatory Policies Act avoided costs, and regulatory issues. From 2004 to 2008, I was a consultant with Bates Private Capital in Lake Oswego, OR, where I developed, prepared, and reviewed financial analyses used in securities litigation. Q. Does this conclude your testimony? A. Yes. UE 335 General Rate Case Direct Testimony

20 VIII. List of Exhibits UE 335 / PGE / 1200 Macfarlane Goodspeed / 18 PGE Exhibit Description 1201 Marginal Cost Study 1202 PGE s Draft Near Term Local Transmission Plan UE 335 General Rate Case Direct Testimony

21 UE 335 / PGE / 1201 Macfarlane Goodspeed / Page 1 PORTLAND GENERAL ELECTRIC 2019 MARGINAL ENERGY COSTS Marginal Busbar Energy Schedule Energy (MWh) Cost Schedule 7 8,017,734 $303,025,693 Schedule 15 16,701 $567,660 Schedule 32 1,700,609 $63,345,918 Schedule 38 32,692 $1,260,508 Schedule 47 23,002 $874,342 Schedule 49 69,419 $2,638,126 Schedule 83 2,946,960 $110,562,096 Schedule 85 2,944,147 $109,544,583 Schedule ,085 $19,873,332 Schedule 90-P 1,850,474 $67,405,013 Schedule 91/95 57,146 $1,942,392 Schedule 92 2,667 $96,756 TOTALS 18,202,636 $681,136,419

22 UE 335 / PGE / 1201 Macfarlane Goodspeed / Page 2 PORTLAND GENERAL ELECTRIC 2019 MARGINAL ENERGY AND CAPACITY COSTS Thermal Thermal Wind Weighted Capacity Marginal Marginal Capacity Marginal SCCT Energy Energy Costs Energy Year $/kw-year $/MWh $/MWh RPS $/kw-year $/MWh % % % % % % % % % % % % % % % % % % % % Real Levelized $ $34.08 $42.05 $ $36.31 NPV $1,360 $436 $538 $1,360 $464 Nominal Levelized $ $39.73 $49.02 $ $42.33 Real Levelized $ $34.08 $42.05 $ $36.31 Composite Income Tax Rate 27.15% Property Tax Rate 1.45% Inflation Rate 2.00% Capitalization: Preferred 0.00% 0.00% 0.00% Common 50.00% 9.50% 4.75% All Equity 50.00% 4.75% Debt 50.00% 4.97% 2.49% Cost of Capital 7.24% After-Tax Nominal Cost of Capital 6.56% After-Tax Real Cost of Capital 4.47%

23 UE 335 / PGE / 1201 Macfarlane Goodspeed / Page 3 PORTLAND GENERAL ELECTRIC SUMMARY OF TRANSMISSION, DISTRIBUTION AND CUSTOMER MARGINAL COST STUDIES FEEDER FEEDER SECONDARY TRANSFORMER TRANSMISSION SUBTRANSMISSION SUBSTATION MAINLINE TAPLINE TAPLINE & SERVICE METER CUSTOMER COSTS COSTS COSTS COSTS COSTS COSTS COSTS COSTS COSTS SCHEDULE ($/kw) ($/kw) ($/kw) ($/kw) ($/kw) ($kw) ($/Customer) ($/Customer) ($/Customer) (A) (B) (C) (D) (E) (F) (G) (H) (I) Schedule 7 Residential Single-phase $11.98 $12.15 $12.24 $20.41 $15.71 $4.39 $83.97 $19.43 $63.37 Three-phase $11.98 $12.15 $12.24 $20.41 $15.71 $4.39 $ $58.07 $63.37 Schedule 15 Residential $11.98 $12.15 $12.24 $21.38 $18.06 $2.72 $2.89 N/A $11.23 Schedule 15 Commercial $11.98 $12.15 $12.24 $21.38 $18.06 $2.72 $2.89 N/A $13.01 Schedule 32 General Service Single-phase $11.98 $12.15 $12.24 $24.70 $23.90 $3.34 $ $17.23 $80.60 Three-phase $11.98 $12.15 $12.24 $24.70 $11.35 $1.59 $ $72.71 $80.60 Schedule 38 TOU Single-phase $11.98 $12.15 $12.24 $24.54 $24.34 $2.04 $ $58.07 $ Three-phase $11.98 $12.15 $12.24 $24.54 $12.08 $1.01 $ $ $ Schedule 47 Irrigation Single-phase $11.98 $12.15 $12.24 $24.70 $23.90 $10.77 $57.73 $79.11 Three-phase $11.98 $12.15 $12.24 $24.70 $11.35 $21.43 $86.54 $79.11 Schedule 49 Irrigation Single-phase $11.98 $12.15 $12.24 $24.54 $24.34 $ $58.07 $ Three-phase $11.98 $12.15 $12.24 $24.54 $12.08 $ $71.36 $ Schedule 83 Secondary General Service Single-phase $11.98 $12.15 $12.24 $24.54 $24.34 $2.04 $ $57.73 $ Three-phase $11.98 $12.15 $12.24 $24.54 $12.08 $1.01 $1, $ $ Schedule 85 Secondary General Service $11.98 $12.15 $12.24 $19.54 $7.12 $2, $ $1, Schedule 85 Primary General Service $11.98 $12.15 $12.24 $19.54 $7.12 $0.00 $1, $1, Schedule 89 Secondary $11.98 $12.15 $12.24 $76,614 N/A $14, $ $9, ($/Customer) Schedule 89 Primary $11.98 $12.15 $12.24 $76,614 N/A $0.00 $1, $9, ($/Customer) Schedule 89 Subtransmission $11.98 $12.15 N/A $77,041 N/A N/A $19, $9, ($/Customer) Schedule 90 Primary $11.98 $12.15 $12.24 $365,087 NA $0.00 $1, $33, Schedules 91 & 95 Streetlighting $11.98 $12.15 $12.24 $21.38 $18.06 $5.05 $2.89 N/A $ Schedules 92 Traffic Signals $11.98 $12.15 $12.24 $21.38 $10.30 $0.14 $9.19 N/A $986.10

24 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 1 Portland General Electric Company s Longer Term Local Transmission Plan For the Planning Cycle December 28, 2017

25 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 2 Contents 1. Introduction Local Planning Regional and Interregional Coordination Planning Process and Timeline... 3 Figure 1: PGE OATT Attachment K Eight Quarter Planning Cycle... 4 Figure 2: Quarterly Customer Meetings Transmission System Plan Inputs and Components PGE s Transmission System... 5 Figure 3: Map of PGE s Service Territory... 5 Figure 4: PGE-Owned Transmission System Circuits... 6 Figure 5: PGE Circuit Miles Owned (By Voltage Level) Load Forecast... 6 Figure 6: Summer/Winter Loading Conditions and Corresponding Daily-Averaged Temperatures... 7 Figure 7: Portland General Electric s Historic & Projected Seasonal Peak Load Forecasted Resources Economic Studies Stakeholder Submissions Methodology... 8 Figure 8: Powerflow Base Cases Used in 2017 Assessment Steady State Studies Transient Stability Studies Figure 9: WECC Disturbance-Performance Table of Allowable Effects on Other Systems Results Steady State Results Longer Term Evaluation Longer Term Transient Stability Appendix A: 10 Year Project List Lower Columbia Resiliency Project North Hillsboro Capacity Project Orenco-Sunset 115kV Reconductor Project Northern Substation 115kV Conversion Project... 17

26 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 3 1. Introduction This 2017 Longer Term Local Transmission Plan reflects Quarters 5 through 8 of the local transmission planning process as described in PGE s Open Access Transmission Tariff (OATT) Attachment K. The plan includes all transmission system facility improvements identified through this planning process. A power flow reliability assessment of the plan was performed which demonstrated that the planned facility additions will meet NERC and WECC reliability standards. PGE s OATT is located on its Open Access Same-time Information System (OASIS) at Additional information regarding Transmission Planning is located in the Transmission Planning folder on PGE s OASIS. Unless otherwise specified, capitalized terms used herein are defined in PGE s OATT Local Planning This Local Transmission Plan (LTP) has been prepared within the two-year process as defined in PGE s OATT Attachment K. The LTP identifies the Transmission System facility additions required to reliably interconnect forecasted generation resources and serve the forecasted Network Customers load, Native Load Customers load, and Point-to-Point Transmission Customers requirements, including both grandfathered, non-oatt agreements and rollover rights, over a ten (10) year planning horizon. Additionally, the LTP typically incorporates the results of any stakeholder-requested economic congestion studies results that were performed. However, none were requested or incorporated during this particular cycle. Projects identified in the Longer Term Local Transmission Plan s six (6) to ten (10) year planning horizon are not committed projects and are subject to modification and/or withdrawal. Projects described herein are not part of PGE s Expansion Plan as described in Section of Attachment O to PGE s OATT Regional and Interregional Coordination PGE coordinates its planning processes with other transmission providers through membership in the Northern Tier Transmission Group (NTTG) and the Western Electric Coordinating Council (WECC). PGE uses the NTTG process for regional planning, coordination with adjacent regional groups and other planning entities for interregional planning, and development of proposals to WECC. Additional information is located in PGE s OATT Attachment K, in our Transmission Planning Business Practice on OASIS, and on the NTTG s website at 2. Planning Process and Timeline This plan is for the planning cycle. PGE s OATT Attachment K describes an eight (8) quarter study and planning cycle. The planning cycle schedule is shown below in Figure 1. PGE Longer Term Local Transmission Plan

27 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 4 Figure 1: PGE OATT Attachment K Eight Quarter Planning Cycle Quarter Tasks 1 Select Near Term base cases and gather load data Near Term Even Years 2 Post Near Term methodology on OASIS, select one Economic Study for evaluation 3 Select Longer Term base cases, post draft Near Term Plan on OASIS, hold public meeting to solicit stakeholder comment 4 Incorporate stakeholder comments and post final Near Term plan on OASIS 5 Gather load data and accept Economic Study requests Longer Term Odd Years 6 Select one Economic Study for evaluation 7 Post draft Longer Term plan on OASIS, hold public meeting to solicit stakeholder comment 8 Post final Longer Term plan on OASIS, submit final Longer Term Plan to stakeholders and owners of neighboring systems PGE updates its Transmission Customers about activities and/or progress made under the Attachment K planning process, during regularly scheduled customer meetings. Meeting announcements, agendas, and notes are posted in the Customer Meetings folder on PGE s OASIS. Figure 2 shows the meetings held in 2017 and the meetings scheduled for Figure 2: Quarterly Customer Meetings Planning Cycle Quarter Meeting Date 5 March 7, June 6, September 12, December 5, March 13, June 12, September 11, December 11, 2018 *Meeting dates in italics are upcoming and subject to change. PGE Longer Term Local Transmission Plan

28 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 5 3. Transmission System Plan Inputs and Components 3.1. PGE s Transmission System Portland General Electric s (PGE) service territory covers more than 4,000 square miles and provides service to over 825,000 customers. PGE s service territory is confined within Multnomah, Washington, Clackamas, Yamhill, Marion, and Polk counties in northwest Oregon, as shown in Figure 3. Figure 3: Map of PGE s Service Territory i"..' EASTERN Coonties..,,...- Cdum.. - ~IHlh.- < SOUTHERN CENTRAL EASTERN SOUTHERN - WESTERN PGE s Transmission System is designed to reliably distribute power throughout the Portland & Salem regions for the purpose of serving native load. In addition to the load-service transmission facilities, PGE also maintains ownership of networked Transmission System circuits (See Figure 4) used to integrate transmission and generation resources on the Bulk Electric System. PGE Longer Term Local Transmission Plan

29 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 6 Figure 4: PGE-Owned Transmission System Circuits Transmission Circuit Circuit Miles Transmission Path Grizzly-Malin 500kV miles COI 1 Grizzly-Round Butte 500kV 15.6 miles Colstrip-Townsend #1 500kV 37.3 miles (15% ownership) Colstrip-Townsend #2 500kV 36.9 miles (15% ownership) Bethel-Round Butte 230kV 99.2 miles WOCS 2 St Marys-Trojan 230kV 41.4 miles SOA 3 Rivergate-Trojan 230kV 35.1 miles SOA In total, PGE owns 1,590 circuit miles of sub-transmission/transmission at voltages ranging from 57kV to 500kV. (See Figure 5) Figure 5: PGE Circuit Miles Owned (By Voltage Level) Voltage Level Pole Miles Circuit Miles 500 kv kv kv kv Load Forecast For load forecasting purposes, PGE s transmission system is evaluated for a 1-in-3 peak load condition during the summer and winter seasons for Near Term (years 1 through 5) and Longer Term (years 6 through 10) studies. The 1-in-3 peak system load is calculated based on weather conditions that PGE can anticipate experiencing once every three years. The summer (June 1 st through October 31 st ) and winter (November 1 st through March 31 st ) load seasons are considered the most critical study seasons due to heavier peak loads and high power transfers over PGE s T&D System to its customers. PGE defines the seasons to align with the Peak Reliability Seasonal System Operating Limits Coordination Process, Appendix V. 1 California-Oregon Intertie 2 West of Cascades South 3 South of Allston PGE Longer Term Local Transmission Plan

30 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 7 Figure 6: Summer/Winter Loading Conditions and Corresponding Daily-Averaged Temperatures Summer 1-in-2 79ºF 1-in-3 81ºF 1-in-5 83ºF 1-in-10 85ºF 1-in-20 87ºF Winter 1-in-2 28ºF 1-in-3 24ºF 1-in-5 21ºF 1-in-10 18ºF 1-in-20 15ºF Figure 7: Portland General Electric s Historic & Projected Seasonal Peak Load (Projection is for a 1-in-3 Loading Condition) Portland General Electric Historic & Projected Seasonal Peak Load (Projection is for a 1..jn-J Loading Condition) 4,200 ~ , l [,,...J ~ 3, ~ ---~ --~ ~ ;.. cu ll. 3, ; --Summar - - Winter 3, < Year As depicted in Figure 7, PGE s all-time peak load occurred on December 21, 1998, with the Net System Load 4 reaching 4073 MW. PGE s all time summer peak occurred on July 29, 2009 with the Net System Load reaching 3949 MW. 4 The Net System Load is the total load served by PGEM, including losses. This includes PGE load in all control areas, plus ESS load, minus net borderlines. PGE Longer Term Local Transmission Plan

31 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page Forecasted Resources The forecasted resources are comprised of generators, identified by network customers as designated network resources, that are integrated into the wider regional forecasts of expected resources committed to meet seasonal peak loads Economic Studies Eligible customers or stakeholders may submit economic congestion study requests during either Quarter 1 or Quarter 5 of the planning cycle. However, PGE did not receive any study requests during the planning cycle. 3.5 Stakeholder Submissions Any stakeholder may submit data to be evaluated as part of the preparation of the draft Longer Term Local Transmission Plan and/or the development of sensitivity analyses, including alternative solutions to the identified needs set out in prior Local Transmission Plans, Public Policy Considerations and Requirements, and transmission needs driven by Public Policy Considerations and Requirements. However, PGE did not receive any such data submissions during the planning cycle. 4. Methodology PGE s transmission system is designed to reliably supply projected customer demands and projected Firm Transmission Services over the range of forecasted system demands. Studies are performed annually to evaluate where transmission upgrades may be needed to meet performance requirements. PGE maintains system models within its planning area for performing the studies required to complete the System Assessment. These models use data that is provided in WECC Base Cases in accordance with the MOD and MOD reliability standards. Electrical facilities modeled in the cases have established normal and emergency ratings, as defined in PGE s Facility Ratings Methodology document. A facility rating is determined based on the most limiting component in a given transmission path, in accordance with the FAC reliability standard. Reactive power resources are modeled as made available in the WECC base cases. For PGE, reactive power resources include shunt capacitor banks available on the 115kV transmission system (primarily auto mode - time-clock; two auto mode - voltage control) and on the 57kV transmission system (auto mode - voltage control). Studies are evaluated for the Near Term Planning Horizon (years 1 through 5) and the Longer Term Planning Horizon (years 6 through 10) to ensure adequate capacity is available on PGE s transmission system. The load model used in the studies is obtained from PGE s corporate forecast, reflecting a 1-in- 3 demand level for peak summer and peak winter conditions. Known outages of generation or transmission facilities with durations of at least six months are appropriately represented in the system models. Transmission equipment is assumed to be out of service in the Base Case system models if there is no spare equipment or mitigation strategy for the loss of the equipment. In the Near Term, studies are performed for the following: PGE Longer Term Local Transmission Plan

32 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 9 System Peak Load for either Year One or Year Two System Peak Load for Year Five System Off-Peak Load for one of the five years Sensitivity studies are performed for each of these cases by varying the study parameters to stress the system within a range of credible conditions that demonstrate a measurable change in performance. PGE alters the real and reactive forecasted load and the transfers on the paths into the Portland area on all sensitivity studies. For peak system sensitivity cases, the 1-in-10 load forecast is used. Studies are evaluated at peak summer and peak winter load conditions for one of the years in the Longer Term Planning Horizon. Figure 8: Powerflow Base Cases Used in 2017 Assessment SUMMER Study Year Origin WECC Base Case PGE Case Name PGE System Load (MW) Year One/Two Case HS2 19 HS PLANNING 3665 Year Five Case HS1 22 HS PLANNING 3762 Year One/Two Sensitivity HS2 19 HS SENSITIVITY 3789 Year Five Sensitivity HS1 22 HS SENSITIVITY 3889 Long Term Case HS1 27 HS PLANNING WINTER SPRING Year One/Two Case HW HW PLANNING 3694 Year Five Case HW HW PLANNING 3792 Year One/Two Sensitivity HW HW SENSITIVITY 3879 Year Five Sensitivity HW HW SENSITIVITY 3981 Long Term Case HW HW PLANNING 3921 Near Term Off Peak Case LSP2-S 19 LSP PLANNING 2427 Near Term Off Peak Sensitivity LSP2-S 19 LSP SENSITIVITY 2427 The Bulk Electric System is evaluated for steady state and transient stability performance for planning events described in Table 1 of the NERC TPL reliability standard. When system simulations indicate an inability of the systems to respond as prescribed in the NERC TPL standard, PGE identifies projects and/or Corrective Action Plans which are needed to achieve the required system performance throughout the Planning Horizon Steady State Studies PGE performs steady-state studies for the Near-Term and Long-Term Transmission Planning Horizons. The studies consider all contingency scenarios identified in Table 1 of the NERC TPL reliability standard to determine if the Transmission System meets performance requirements. These studies also assess the impact of Extreme Events on the system expected to produce severe system impacts. The contingency analyses simulate the removal of all elements that the Protection System and other automatic controls are expected to disconnect for each contingency without Operator intervention. The analyses include the impact of the subsequent tripping of generators due to voltage limitations and tripping of transmission elements where relay loadability limits are exceeded. Automatic controls simulated include phase-shifting transformers, load tap changing transformers, and switched capacitors and reactors. PGE Longer Term Local Transmission Plan

33 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 10 Cascading is not allowed to occur for any contingency analysis. If the analysis of an Extreme Event concludes there is Cascading, an evaluation of possible actions designed to reduce the likelihood or mitigate the consequences and adverse impacts of the event(s) is completed. Capacity addition projects are developed when simulations indicate the system s inability to meet the steady-state performance requirements for P1 events. For P2-P7 events, PGE identifies distribution substations where manual post-contingency load-shedding may be required to ensure that the Transmission System remains within the defined operating limits Transient Stability Studies PGE evaluates the voltage and transient stability performance of the Transmission System for contingencies to PGE and adjacent utility equipment at 500kV and 230kV. The studies evaluate single line-to-ground and 3ϕ faults to these facilities, including generators, bus sections, breaker failure, and loss of a double-circuit transmission line. Extreme events are studied for 3ϕ faults with Delayed Fault Clearing. For all 500kV and 230kV breaker positions, PGE implements high-speed protection through two independent relay systems utilizing separate current transformers for each set of relays. For a fault directly affecting these facilities, normal clearing is achieved when the protection system operates as designed and faults are cleared within four to six cycles. PGE implements breaker-failure protection schemes for its 500kV and 230kV facilities; and the majority of 115kV facilities. Delayed clearing occurs when a breaker fails to operate and the breaker-failure scheme clears the fault. Facilities without delayed clearing are modeled as such in the contingency definition. The transient stability results are evaluated against the performance requirements outlined in the NERC TPL reliability standard and against the WECC Disturbance-Performance Table of Allowable Effects on Other Systems (Table I). The simulation durations are run to 20 seconds. PGE Longer Term Local Transmission Plan

34 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 11 Figure 9: WECC Disturbance-Performance Table of Allowable Effects on Other Systems 5 WECC and NERC Categories Outage Frequency Associated with the Performance Category Transient Voltage Dip Standard Minimum Transient Frequency Standard Post Transient Voltage Deviation Standard A (P0) Not Applicable Nothing in addition to NERC B (P1) 0.33 Not to exceed 25% at load buses or 30% at non-load buses. Not to exceed 20% for more than 20 cycles at load buses. Not below 59.6 Hz for 6 cycles or more at a load bus. Not to exceed 5% at any bus. C (P2-P7) Not to exceed 30% at any bus. Not to exceed 20% for more than 40 cycles at load buses. Not below 59.0 Hz for 6 cycles or more at a load bus. Not to exceed 10% at any bus. D (Extreme) < Nothing in addition to NERC Contingency analyses simulate the removal of all elements that the Protection System and other automatic controls expected to disconnect for each contingency without Operator intervention. The analyses include the impact of the subsequent: - Successful high speed (less than one second) reclosing and unsuccessful high speed reclosing into a Fault where high speed reclosing is utilized - Tripping of generators due to voltage limitations - Tripping of Transmission lines and transformers where transient swings cause Protection System operation based on generic or actual relay models - Automatic controls simulated include generator exciter control and power system stabilizers, static var compensators, power flow controllers, and DC Transmission controllers. Cascading is not allowed to occur for any contingency analysis. If the analysis of an Extreme Event concludes there is Cascading, an evaluation of possible actions designed to reduce the likelihood or mitigate the consequences and adverse impacts of the event(s) is completed. 5 The WECC TPL-001-WECC-CRT Regional Criterion is currently undergoing a revision to adapt the new categories (P0-P7) in the NERC TPL reliability standard. PGE Longer Term Local Transmission Plan

35 UE 335 / PGE / 1202 Macfarlane - Goodspeed / Page 12 Corrective Action Plans are developed if the stability studies indicate that the system cannot meet the TPL and WECC performance requirements. - P1: No generating unit pulls out of synchronism - P2-P7: When a generator pulls out of synchronism, the resulting apparent impedance swings do not result in the tripping of any Transmission system elements other than the generating unit and its directly connected facilities - P1-P7: Power oscillations exhibit acceptable damping 5. Results 5.1. Steady State Results Longer Term Evaluation There are no contingency loading or voltage concerns on PGE s system in the Longer Term Planning Horizon for NERC TPL Categories P1, P2, P3, P4, and P5. NERC TPL Category P6 and P7 contingency overloads and voltage concerns are addressed with load shedding, as permitted, on PGE s local distribution system. None of the contingencies evaluated will result in cascading from PGE s Control Area to another Control Area Longer Term Transient Stability The Longer Term transient stability studies indicate that PGE s Transmission System exhibits adequate transient stability throughout the 500kV and 230kV transmission systems. The minimum transient frequency response recorded did not dip below 59.6 Hz for any of the contingency events studied on PGE s Transmission System. Underfrequency Load Shedding ( UFLS ) relays are not affected because the set point for UFLS relays is 59.3 Hz. The transient voltage dip did not exceed 25% at any load bus or 30% at any non-load bus for any of the contingency events studied on PGE s Transmission System Projects Currently Included in the Longer Term Plan There are 3 projects currently planned for implementation in the Longer Term Planning Horizon. Projects described in this Longer Term Plan are subject to modification and/or withdrawal. Potential projects are described in detail in Appendix A. PGE Longer Term Local Transmission Plan

UE / PGE / 100 TOOMAN TINKER SCHUE BEFORE THE PUBLIC UTILITY COMMISSION OF THE STATE OF OREGON Power Costs PORTLAND GENERAL ELECTRIC COMPANY Direct Testimony and Exhibits of L. Alex Tooman- Jay Tinker

More information

Attention Filing Center:

Attention Filing Center: Portland General Electric Company Legal Department 121 SW Salmon Street Portland, Oregon 97204 503-464-7822 Facsimile 503-464-2200 Loretta I. Mabinton Associate General Counsel March 27, 2018 Via Electronic

More information

Open Season Questions and Answers. Posted: November 26, 2013

Open Season Questions and Answers. Posted: November 26, 2013 Portland General Electric Transmission & Reliability Services Open Season Questions and Answers Posted: November 26, 2013 1. What Transmission and Ancillary Services would apply to the transmission awarded

More information

Regional Transmission Resources

Regional Transmission Resources I 2017 PSE Integrated Resource Plan Regional Transmission Resources This appendix reviews current regional transmission issues and efforts to address those issues. Contents 1. OVERVIEW I-2 2. THE PACIFIC

More information

October 25, UM 1856 PGE's Plan to Advancing its Energy Storage Modeling Capability

October 25, UM 1856 PGE's Plan to Advancing its Energy Storage Modeling Capability Portland General Electric 121 SW Salmon Street Portland, Ore. 97204 PortlandGeneral.com October 25, 2018 Public Utility Commission of Oregon Attn: Filing Center 201 High Street, S.E. P.O. Box 1088 Salem,

More information

This Available Transfer Capability Implementation Document (ATCID) contains the required information as specified in NERC MOD-001-1a, R3.

This Available Transfer Capability Implementation Document (ATCID) contains the required information as specified in NERC MOD-001-1a, R3. Puget Sound Energy Transmission Available Transfer Capability Implementation Document Version Posted: February 14, 2014 Version Effective: February 14, 2014 Revision No.: 0.4 Section 1 Purpose: This Available

More information

EIM Tariff Changes Round 2

EIM Tariff Changes Round 2 EIM Tariff Changes Round 2 #1 #2 Southern Intertie (Attachment O) LAP Pricing for Losses on Southern Interie (Schedule 12A) Powerex Powerex In its responses to stakeholders comments on the first round

More information

Net Variable Power Cost

Net Variable Power Cost Niman Peschka Hager BEFORE THE PUBLIC UTILITY COMMISSION OF THE STATE OF OREGON UE Net Variable Power Cost PORTLAND GENERAL ELECTRIC COMPANY Direct Testimony and Exhibits of Michael Niman Terry Peschka

More information

Annual Electric Balancing Authority Area and Planning Area Report

Annual Electric Balancing Authority Area and Planning Area Report Part I - Schedule 1. Identification and Certification Form Approved OMB Numbers: 1902-0140 (Expires 05/31/2016) 1. Respondent Identification: Code: Name: 3. Respondent Mailing Address: Chris Robinson P.O.

More information

Planning for Demand Response in PGE s IRP

Planning for Demand Response in PGE s IRP Planning for Demand Response in PGE s IRP Pacific Northwest Demand Response Project Meeting February 14, 2013 2012 Portland General Electric. All rights reserved. PGE Load Resource Balance: Energy 2 1

More information

Table of Contents. UM 1912 / PGE 600 Goodspeed - Jordan / 1. UM 1912 Resource Value of Solar Reply Testimony

Table of Contents. UM 1912 / PGE 600 Goodspeed - Jordan / 1. UM 1912 Resource Value of Solar Reply Testimony UM / PGE 00 Goodspeed - Jordan / Table of Contents I Introduction and Summary... II Response to OPUC Commission s Staff Comments... III Response to Renewable Northwest s Comments... IV. OSEIA s Comments

More information

ENO IRP Public Technical Conference 2015 IRP Process & Company Overview

ENO IRP Public Technical Conference 2015 IRP Process & Company Overview ENO IRP Public Technical Conference 2015 IRP Process & Company Overview Milestone 1 2015 ENO IRP June 27, 2014 1 Conference Objectives Explain integrated resource planning Highlight process for public

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Portland General Electric Company ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Portland General Electric Company ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Portland General Electric Company ) Docket No. ER17-1075-000 MOTION TO INTERVENE AND COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM

More information

PGE Energy Imbalance Market (PGE EIM BP)

PGE Energy Imbalance Market (PGE EIM BP) Business Practice: PGE Energy Imbalance Market (PGE EIM BP) Posted: September 30, 2017 Effective: October 1, 2017 Revision No.: 0 Table of Contents 1. Introduction... 3 2. Communication with the PGE EIM

More information

Citizens Utility Board of Oregon

Citizens Utility Board of Oregon Citizens Utility Board of Oregon 0 SW Broadway, Suite 00 Portland, OR 0 (0) - (0) - cub@oregoncub.org www.oregoncub.org July, 0 Public Utility Commission Attn: Filing Center PO Box 0 Salem, OR 0-0 Re:

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UE230 DISPOSITION: REQUEST ALLOWED WITH CONDITIONS

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UE230 DISPOSITION: REQUEST ALLOWED WITH CONDITIONS ORDER NO. ENTERED JUl 0 5 2011 BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UE230 In the Matter of PORTLAND GENERAL ELECTRIC Advice No. 11-07 Schedule 145 Boardman Adjustment Update. ORDER DISPOSITION:

More information

SUBMITTED VIA E-TARIFF FILING. March 1, 2017

SUBMITTED VIA E-TARIFF FILING. March 1, 2017 1050 Thomas Jefferson Street, NW Seventh Floor Washington, DC 20007 (202) 298-1800 Phone (202) 338-2416 Fax Gary D. Bachman (202) 298-1880 gdb@vnf.com SUBMITTED VIA E-TARIFF FILING March 1, 2017 The Honorable

More information

Operational Flexibility

Operational Flexibility H 2017 PSE Integrated Resource Plan Operational Flexibility This appendix summarizes the operational flexibility study performed for PSE by E3 Consulting for the 2017 IRP. Contents 1. OVERVIEW H-2 2. SYSTEM

More information

Supporting Reference for Indentification of Interconnection Reliability Operating Limits

Supporting Reference for Indentification of Interconnection Reliability Operating Limits Purpose Planning Authorities (PAs), Transmission Planners (TPs), and Reliability Authorities (RAs) identify System Operating Limits (SOLs) via various planning and operating studies and real-time experience.

More information

ROLE OF PROTECTION SYSTEMS IN CATASTROPHIC FAILURES IN POWER SYSTEMS. A. G. Phadke

ROLE OF PROTECTION SYSTEMS IN CATASTROPHIC FAILURES IN POWER SYSTEMS. A. G. Phadke ROLE OF PROTECTION SYSTEMS IN CATASTROPHIC FAILURES IN POWER SYSTEMS A. G. Phadke Presentation outline: Some past blackouts in North America Why do blackouts occur? Defensive strategies Impact of evolving

More information

PUBLIC SERVICE COMMISSION OF THE DISTRICT OF COLUMBIA 1325 G STREET N.W., SUITE 800 WASHINGTON, D.C ORDER

PUBLIC SERVICE COMMISSION OF THE DISTRICT OF COLUMBIA 1325 G STREET N.W., SUITE 800 WASHINGTON, D.C ORDER PUBLIC SERVICE COMMISSION OF THE DISTRICT OF COLUMBIA 1325 G STREET N.W., SUITE 800 WASHINGTON, D.C. 20005 ORDER June 24, 2016 FORMAL CASE NO. 1017, IN THE MATTER OF THE DEVELOPMENT AND DESIGNATION OF

More information

NSP 2016 WIND RFP QUESTIONS (UPDATED OCTOBER 21, 2016)

NSP 2016 WIND RFP QUESTIONS (UPDATED OCTOBER 21, 2016) NSP 2016 WIND RFP QUESTIONS (UPDATED OCTOBER 21, 2016) CONTENTS RFP Question 24 Clarification Posted October 21 2016... 2 RFP Questions Posted October 17 2016 (Questions 16 through 27)... 3 RFP Questions

More information

Pacific Southwest Blackout on September 8, 2011 at 15:27

Pacific Southwest Blackout on September 8, 2011 at 15:27 PES GM 2013, Vancouver, Canada July 24, 2013 1 Pacific Southwest Blackout on September 8, 2011 at 15:27 Canada, July 24 th, 2013 Dr. Milorad Papic mpapic@idahopower.com 2 Outline 1. Generic Scenario for

More information

In the Matter of Portland General Electric Company 2016 Integrated Resource Plan Docket LC 66

In the Matter of Portland General Electric Company 2016 Integrated Resource Plan Docket LC 66 Troutman Sanders LLP 100 SW Main St., Suite 1000 Portland, Oregon 97204 troutman.com Chris D. Zentz chris.zentz@troutman.com December 1, 2017 VIA ELECTRONIC FILING Oregon Public Utility Commission Attention:

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON ORDER NO. t8 ENTERED FEB 0 2 2018 BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON LC66 In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, ORDER 2016 Integrated Resource Plan. DISPOSITION: 2016 IRP REVISED

More information

Cannabis Regulations Response and Update on Cannabis Legalization

Cannabis Regulations Response and Update on Cannabis Legalization Page 1 of 5 EXECUTIVE SUMMARY On 2018 October 17, Bill C-45, The Cannabis Act, came into force legalizing non-medical cannabis in Canada. Non-medical cannabis is now legal in limited forms, including dried

More information

l'j atlantic citlj ~ elect,ic

l'j atlantic citlj ~ elect,ic Philip J. Passanante Assistant General Counsel 92DC42 PO Box 6066 Newark, DE 19714-6066 302.429.3105 - Telephone 302.429.3801 - Facsimile philip.passanante@pepcoholdings.com l'j atlantic citlj ~ elect,ic

More information

UE 335 Revenue Requirement

UE 335 Revenue Requirement UE / PGE / 00 Tooman Espinoza BEFORE THE PUBLIC UTILITY COMMISSION OF THE STATE OF OREGON UE Revenue Requirement PORTLAND GENERAL ELECTRIC COMPANY Direct Testimony and Exhibits of Alex Tooman, Ph.D. Marco

More information

Western Area Power Administration, Conditional Firm Transmission Service Business Practice

Western Area Power Administration, Conditional Firm Transmission Service Business Practice Western Area Power Administration Conditional Firm Transmission Service Business Practice Background: In Order No. 890, dated February 16, 2007, the Federal Energy Regulatory Commission ( FERC or Commission

More information

CITY OF VALLEJO HIDDENBROOKE IMPROVEMENT DISTRICT NO IMPROVEMENT LEVY ADMINISTRATION REPORT FISCAL YEAR

CITY OF VALLEJO HIDDENBROOKE IMPROVEMENT DISTRICT NO IMPROVEMENT LEVY ADMINISTRATION REPORT FISCAL YEAR CITY OF VALLEJO HIDDENBROOKE IMPROVEMENT DISTRICT NO. 1998-1 IMPROVEMENT LEVY ADMINISTRATION REPORT FISCAL YEAR 2010-11 December 17, 2010 Hiddenbrooke Improvement District No. 1998-1 Improvement Levy Administration

More information

Is Energize Eastside needed?

Is Energize Eastside needed? Is Energize Eastside needed? Questioning PSEs Motive and Proof By: J. Richard Lauckhart Energy Consultant, Davis, Ca lauckjr@hotmail.com Former VP at Puget 1 Why am I involved? I now live in California

More information

UE 283 General Rate Case Filing For Prices Effective January 1, 2015

UE 283 General Rate Case Filing For Prices Effective January 1, 2015 BEFORE THE PUBLIC UTILITY COMMISSION OF THE STATE OF OREGON UE General Rate Case Filing For Prices Effective January, 0 PORTLAND GENERAL ELECTRIC COMPANY DIRECT TESTIMONY AND EXHIBITS February, 0 BEFORE

More information

RE: Docket No. UM 1953 In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Investigation into Proposed Green Tariff.

RE: Docket No. UM 1953 In the Matter of PORTLAND GENERAL ELECTRIC COMPANY, Investigation into Proposed Green Tariff. Public Utility Commission 0 High St SE Suite 00 Salem, OR 0- Mailing Address: PO Box 0 Salem, OR 0-0 0-- July, 0 Via Electronic Filing OREGON PUBLIC UTILITY COMMISSION ATTENTION: FILING CENTER PO BOX 0

More information

UE 335 Net Variable Power Costs

UE 335 Net Variable Power Costs UE / PGE / 00 Niman Kim Batzler BEFORE THE PUBLIC UTILITY COMMISSION OF THE STATE OF OREGON UE Net Variable Power Costs PORTLAND GENERAL ELECTRIC COMPANY Direct Testimony and Exhibits of Mike Niman Cathy

More information

MARIN CLEAN ENERGY ADDENDUM NO. 5 TO THE REVISED COMMUNITY CHOICE AGGREGATION IMPLEMENTATION PLAN AND STATEMENT OF INTENT

MARIN CLEAN ENERGY ADDENDUM NO. 5 TO THE REVISED COMMUNITY CHOICE AGGREGATION IMPLEMENTATION PLAN AND STATEMENT OF INTENT MARIN CLEAN ENERGY ADDENDUM NO. 5 TO THE REVISED COMMUNITY CHOICE AGGREGATION IMPLEMENTATION PLAN AND STATEMENT OF INTENT TO ADDRESS MCE EXPANSION TO CONTRA COSTA COUNTY; THE CITIES OF CONCORD, MARTINEZ,

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON ORDER NO. 00-391 ENTERED JUL 20 2000 This is an electronic copy. Attachments may not appear. BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UE 112 In the Matter of Portland General Electric Company s Advice

More information

Attachment B Utilities and Transportation Commission Comments on Puget Sound Energy s Colstrip Study Docket UE

Attachment B Utilities and Transportation Commission Comments on Puget Sound Energy s Colstrip Study Docket UE Attachment B Utilities and Transportation Commission Comments on Puget Sound Energy s Colstrip Study Docket UE-120767 I. Introduction In the Commission s Acknowledgement letter of PSE s 2011 Integrated

More information

Methods for Establishing IROLs

Methods for Establishing IROLs Methods for Establishing IROLs Informational Webinar NERC Methods for Establishing IROLs Task Force (MEITF) January 25, 2019 Logistics This is an informational webinar to describe the efforts of the NERC

More information

May 12, In the Matter of Portland General Electric Co Integrated Resource Plan Docket No. LC 66

May 12, In the Matter of Portland General Electric Co Integrated Resource Plan Docket No. LC 66 STEPHEN C. HALL 503.290.2336 telephone stephen.hall@troutmansanders.com TROUTMAN SANDERS LLP Attorneys at Law 100 SW Main St., Suite 1000 Portland, Oregon 97204 503.290.2400 telephone troutmansanders.com

More information

Portland General Electric Request for Information (RFI): Providers of Utility Operable Energy Storage Systems

Portland General Electric Request for Information (RFI): Providers of Utility Operable Energy Storage Systems Portland General Electric Request for Information (RFI): Providers of Utility Operable Energy Storage Systems Table of Contents 1 Background Information... 2 1.1 About Portland General Electric... 2 1.2

More information

Wakefield to Woburn Underground Power Cable Project. Town of Wakefield Board of Selectman Meeting November 13, 2017

Wakefield to Woburn Underground Power Cable Project. Town of Wakefield Board of Selectman Meeting November 13, 2017 Wakefield to Woburn Underground Power Cable Project Town of Wakefield Board of Selectman Meeting November 13, 2017 Project Update, DPW Agreement and Franchise Petition ¾ Provide project update to the Town

More information

PG&E Automated Demand Response (ADR) Incentives

PG&E Automated Demand Response (ADR) Incentives PG&E Automated Demand Response (ADR) Incentives for Ag Irrigation Pumps "PG&E" refers to Pacific Gas and Electric Company, a subsidiary of PG&E Corporation. 2018 Pacific Gas and Electric Company. All rights

More information

Woburn to Wakefield 345-kV Line Project and Mystic to Woburn 115-kV Line Project

Woburn to Wakefield 345-kV Line Project and Mystic to Woburn 115-kV Line Project Woburn to Wakefield 345-kV Line Project and Mystic to Woburn 115-kV Line Project Town of Winchester Board of Selectmen Presentation April 6, 2015 Facilitating Our Partnership Open, regular communication

More information

Addressing a New Interconnection Reliability Operating Limit

Addressing a New Interconnection Reliability Operating Limit Addressing a New Interconnection Reliability Operating Limit Phil O Donnell Manager, Operations and Planning Audits What is an Interconnection Reliability Operating Limit (IROL)? 2 NERC definition Development

More information

NERC Voltage Ride-through Follow-up Activities

NERC Voltage Ride-through Follow-up Activities NERC Voltage Ride-through Follow-up Activities Robert W. Cummings Senior Director of Engineering and Reliability Initiatives MRO Reliability Conference May 24, 2017 Early JUNE Publish Inverter Task Force

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1832

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1832 BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1832 Served electronically at Salem, Oregon, 4/28/17, to: Respondent's Attorney Denise Saunders Portland General Electric Company 121 SW Salmon Street

More information

Endesa 1Q 2017 Results 09/05/2017

Endesa 1Q 2017 Results 09/05/2017 Endesa 1Q 2017 Results 09/05/2017 1. Highlights and key financial figures 2. Endesa s performance in 1Q 2017 market context 3. Financial results 4. Final remarks 2 1. Highlights and key financial figures

More information

BEFORE THE COUNCIL OF THE CITY OF NEW ORLEANS

BEFORE THE COUNCIL OF THE CITY OF NEW ORLEANS BEFORE THE COUNCIL OF THE CITY OF NEW ORLEANS IN RE: APPLICATION OF ENTERGY NEW ) ORLEANS, INC. FOR APPROVAL TO ) CONSTRUCT NEW ORLEANS POWER ) DOCKET NO. UD--0 STATION AND REQUEST FOR COST RECOVERY )

More information

Discussion of Technical Issues Required to Implement a Frequency Response Standard

Discussion of Technical Issues Required to Implement a Frequency Response Standard Reference 1 Discussion of Technical Issues Required to Implement a Frequency Response Standard Howard F. Illian Abstract NERC is investigating the implementation of a Frequency Response Standard on the

More information

Joint Office of Gas Transporters 0209: URolling AQ

Joint Office of Gas Transporters 0209: URolling AQ Development Workgroup Report Rolling AQ Modification Reference Number 0209 Version 1.0 This Development Work Group Report has been prepared by Group Members and follows the format required by the UNC Modification

More information

Request for Proposals

Request for Proposals Request for Proposals for Program Design and Implementation Services for Demand Side Capacity Reductions from Targeted Commercial Industrial Customers January 3, 2012 2011 Demand Response RFP Table of

More information

DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT NOVEMBER 2006

DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT NOVEMBER 2006 DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT NOVEMBER 2006 CON REVIEW FSF-MME-0906-025 ACQUISITION OF AN MRI UNIT CAPITAL EXPENDITURE: $2,711,682 LOCATION: HATTIESBURG, FORREST COUNTY, MS I. PROJECT

More information

Standard FAC Establish and Communicate System Operating Limits

Standard FAC Establish and Communicate System Operating Limits A. Introduction 1. Title: Establish and Communicate System Operating Limits 2. Number: FAC-014-2 3. Purpose: To ensure that System Operating Limits (SOLs) used in the reliable planning and operation of

More information

What Behaviors Do Behavior Programs Change

What Behaviors Do Behavior Programs Change What Behaviors Do Behavior Programs Change Yingjuan (Molly) Du, Dave Hanna, Jean Shelton and Amy Buege, Itron, Inc. ABSTRACT Utilities behavioral programs, such as audits and web-based tools, are designed

More information

STATE OF NORTH DAKOTA PUBLIC SERVICE COMMISSION FINDINGS OF FACT, CONCLUSIONS OF LAW AND ORDER. June 27, Appearances

STATE OF NORTH DAKOTA PUBLIC SERVICE COMMISSION FINDINGS OF FACT, CONCLUSIONS OF LAW AND ORDER. June 27, Appearances STATE OF NORTH DAKOTA PUBLIC SERVICE COMMISSION Northern States Power Company Natural Gas Rate Increase Application FINDINGS OF FACT, CONCLUSIONS OF LAW AND ORDER June 27, 2001 Appearances Commissioners:

More information

For An Act To Be Entitled. Subtitle

For An Act To Be Entitled. Subtitle 0 0 State of Arkansas INTERIM STUDY PROPOSAL 0-0th General Assembly A Bill DRAFT JMB/JMB Second Extraordinary Session, 0 SENATE BILL By: Senator J. Hutchinson Filed with: Arkansas Legislative Council pursuant

More information

Blackout risk, cascading failure and complex systems dynamics

Blackout risk, cascading failure and complex systems dynamics Blackout risk, cascading failure and complex systems dynamics Ian Dobson University of Wisconsin, Madison Benjamin A. Carreras Oak Ridge National Laboratory David E. Newman University of Alaska, Fairbanks

More information

MAY 17, 2016 CITY COUNCIL STUDY SESSION POLICY DISCUSSION ON MEDICAL CANNABIS CULTIVATION FACILITIES

MAY 17, 2016 CITY COUNCIL STUDY SESSION POLICY DISCUSSION ON MEDICAL CANNABIS CULTIVATION FACILITIES MAY 17, 2016 CITY COUNCIL STUDY SESSION POLICY DISCUSSION ON MEDICAL CANNABIS CULTIVATION FACILITIES Staff Presentation 1. Overview of Ordinance 1083 and 1084 and discussion on allowing medical cannabis

More information

ASCO Power Control Systems Overview

ASCO Power Control Systems Overview ASCO Power Control Systems Overview POWER CONTROL CHALLENGES Today more than ever, continuous electrical power is essential for providing mission-critical services. Whether it s a hospital providing critical

More information

Proposed Amendment of 10A NCAC 26E.0603 Requirements for Transmission of Data

Proposed Amendment of 10A NCAC 26E.0603 Requirements for Transmission of Data Proposed Amendment of 10A NCAC 26E.0603 Requirements for Transmission of Data Agency: Contact: DHHS/ Mental Health, Developmental Disabilities, and Substance Abuse Services Amanda Reeder, Rule-Making Coordinator

More information

TD005 Revision 7 Maintaining Accurate Distribution System Documentation

TD005 Revision 7 Maintaining Accurate Distribution System Documentation TD PROCEDURE TD005 Revision 7 Maintaining Accurate Distribution System Documentation Issue Date: Effective Date: Owner Departments: System Operations, GIS Mapping Subject Matter Experts: Christopher D.

More information

ACE DIVERSITY INTERCHANGE

ACE DIVERSITY INTERCHANGE ACE DIVERSITY INTERCHANGE O P E R A T I O N A L E F F I C I E N C Y A C H I E V E D T H R O U G H C O O R D I N A T I O N A M O N G B A L A N C I N G A U T H O R I T I E S WHAT IS IT? ADI stands for Area

More information

Rationales for FAC August 2018

Rationales for FAC August 2018 Rationales for FAC-014-3 August 2018 Requirement R1 Each Reliability Coordinator shall establish Interconnection Reliability Operating Limits (IROLs) for its Reliability Coordinator Area in accordance

More information

December 19, Click on the Regulatory Information link at the bottom right of the page;

December 19, Click on the Regulatory Information link at the bottom right of the page; Robin Meidhof Senior Attorney Robin.Meidhof@sce.com Edward Randolph Director of the Energy Division California Public Utilities Commission 505 Van Ness Avenue San Francisco, CA 94102 December 19, 2018

More information

I. Introduction. A. My name is Scott Russell. I am a Specialist with the Structuring and Origination

I. Introduction. A. My name is Scott Russell. I am a Specialist with the Structuring and Origination Russell Tooman / I. Introduction Q. Please state your names and positions with PGE. My name is Scott Russell. I am a Specialist with the Structuring and Origination Department at PGE. My name is Alex Tooman.

More information

Section Processing

Section Processing Section 10000 Processing Table of Contents 10100 Introduction 10200 Participation 10300 Submit Requests in Pounds, Not Cases 10400 Approved Processors 10500 TDA Processing Contracts 10600 Value Pass-Through

More information

Telekom Austria Group Results for the 1st Quarter May 27, 2003

Telekom Austria Group Results for the 1st Quarter May 27, 2003 Telekom Austria Group Results for the 1st Quarter 2003 May 27, 2003 1 Cautionary Statement This presentation contains certain forward-looking statements. Actual results may differ materially from those

More information

UPPER MIDWEST MARKETING AREA ANALYSIS OF COMPONENT LEVELS AND SOMATIC CELL COUNT IN INDIVIDUAL HERD MILK AT THE FARM LEVEL 2015

UPPER MIDWEST MARKETING AREA ANALYSIS OF COMPONENT LEVELS AND SOMATIC CELL COUNT IN INDIVIDUAL HERD MILK AT THE FARM LEVEL 2015 UPPER MIDWEST MARKETING AREA ANALYSIS OF COMPONENT LEVELS AND SOMATIC CELL COUNT IN INDIVIDUAL HERD MILK AT THE FARM LEVEL 2015 Staff Paper 16-01 Prepared by: Corey Freije August 2016 Federal Milk Market

More information

Comparative Analysis of Western EIM and NWPP MC Intra-Hour Energy Market Options

Comparative Analysis of Western EIM and NWPP MC Intra-Hour Energy Market Options Comparative Analysis of Western EIM and NWPP MC Intra-Hour Energy Market Options Table of Contents I Executive Summary... 1 1 Introduction... 2 1.1 Background... 4 2 Overview of Western EIM and NWPP MC

More information

Agency Information Collection Activities; Submission for Office of Management and Budget

Agency Information Collection Activities; Submission for Office of Management and Budget This document is scheduled to be published in the Federal Register on 01/28/2016 and available online at http://federalregister.gov/a/2016-01690, and on FDsys.gov 4164-01-P DEPARTMENT OF HEALTH AND HUMAN

More information

OREGON SAGE GROUSE FRAMEWORK

OREGON SAGE GROUSE FRAMEWORK OREGON SAGE GROUSE FRAMEWORK Protecting sage grouse habitat from human disturbance 1. Existing Conditions Oregon has effectively protected Greater Sage Grouse core habitat from most human disturbance.

More information

ST. JUDE MEDICAL / THORATEC TRANSACTION HIGHLIGHTS July 22, 2015

ST. JUDE MEDICAL / THORATEC TRANSACTION HIGHLIGHTS July 22, 2015 ST. JUDE MEDICAL / THORATEC TRANSACTION HIGHLIGHTS July 22, 2015 1 FORWARD LOOKING STATEMENT This presentation contains forward-looking statements within the meaning of the Private Securities Litigation

More information

ACE Diversity Interchange White Paper

ACE Diversity Interchange White Paper ACE Diversity Interchange White Paper Authored by: The NERC ACE Diversity Interchange Task Force March 2012 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table

More information

INVESTOR PRESENTATION

INVESTOR PRESENTATION INVESTOR PRESENTATION JUNE 2016 OTCQB:CANN ABOUT General Cannabis Corporation (GCC) is the all-in-one resource for the highest quality service providers available to the regulated Cannabis Industry. We

More information

Acquisition of Novartis Influenza Vaccines Business. 27 th October 2014

Acquisition of Novartis Influenza Vaccines Business. 27 th October 2014 1 Acquisition of Novartis Influenza Vaccines Business 27 th October 2014 2 Legal Notice Forward looking statements The materials in this presentation speak only as of the date of these materials, and include

More information

Media Briefing. Damage to Majuba power station coal storage silo. 03 November Tshediso Matona Chief Executive

Media Briefing. Damage to Majuba power station coal storage silo. 03 November Tshediso Matona Chief Executive Media Briefing Damage to Majuba power station coal storage silo 03 November 2014 Tshediso Matona Chief Executive Introduction Majuba power station incident The system outlook and plan Conclusion 2 Introduction

More information

A Day in the Life of a Transactive Grid

A Day in the Life of a Transactive Grid A Day in the Life of a Transactive Grid GridWise Architecture Council Presented to: Council of State Governments Webinar December 3, 2014 Mark Knight and Tom Sloan GWAC Members Ron Melton GWAC Administrator

More information

RESIDENTIAL SERVICE PROTECTION FUND

RESIDENTIAL SERVICE PROTECTION FUND RESIDENTIAL SERVICE PROTECTION FUND 759.685 Surcharge assessed on retail telecommunications subscribers; rules. (1)(a) In order to fund the programs provided in sections 2 to 6, chapter 290, Oregon Laws

More information

August 2014 Public Communications Summary

August 2014 Public Communications Summary August 2014 Public Communications Summary 9/23/14 The following is a summary of feedback received by Puget Sound Energy (PSE) between Aug. 1 and Aug. 31, 2014 regarding the Energize Eastside project. During

More information

ETON IRRIGATOR ADVISORY COMMITTEE

ETON IRRIGATOR ADVISORY COMMITTEE ETON IRRIGATOR ADVISORY COMMITTEE 11 th March 2011 Queensland Competition Authority GPO Box 2257 BRISBANE QLD 4001 Dear Sirs RE: SunWater Network Service Plans Eton Bulk Water Supply Scheme and Eton Distribution

More information

Cannabis Legalization Proposed Bylaws

Cannabis Legalization Proposed Bylaws 2018 April 03 Page 1 of 7 EXECUTIVE SUMMARY On 2017 April 13, the Government of Canada introduced Bill C-45, An Act respecting cannabis and to amend the Controlled Drugs and Substances Act, the Criminal

More information

Cerus P-Series General Specifications Section 15172

Cerus P-Series General Specifications Section 15172 Cerus P-Series s Section 15172 Variable Frequency Drives PART 1-GENERAL 1.01 SECTION INCLUDES A. Variable Frequency Drive(VFD) 1.02 RELATED SECTIONS A. Section 16195 1.03 REFERENCES A. NEMA250 B. EN 50178

More information

The Disruption in the European Power Grid on 4 November 2006

The Disruption in the European Power Grid on 4 November 2006 The Disruption in the European Power Grid on 4 November 2006 A Why-Because Analysis Bernd Sieker Causalis Limited May 2007 Bernd Sieker (Causalis Limited) The Disruption in the European Power Gridon 4

More information

BEFORE THE FEDERAL COMMUNICATIONS COMMISSION WASHINGTON, DC 20554

BEFORE THE FEDERAL COMMUNICATIONS COMMISSION WASHINGTON, DC 20554 BEFORE THE FEDERAL COMMUNICATIONS COMMISSION WASHINGTON, DC 20554 In the Matter of ) ) Telecommunications Relay Services and ) CG Docket No. 03-123 Speech-to-Speech Services for Individuals ) With Hearing

More information

City of Calistoga Staff Report

City of Calistoga Staff Report City of Calistoga Staff Report 9 TO: FROM: DATE: August 1, 2017 SUBJECT: Honorable Mayor and City Council Lynn Goldberg, Planning and Building Director Potential Initiation of Municipal Code Amendments

More information

Determining the Vulnerabilities of the Power Transmission System

Determining the Vulnerabilities of the Power Transmission System Determining the Vulnerabilities of the Power Transmission System B. A. Carreras D. E. Newman I. Dobson Depart. Fisica Universidad Carlos III Madrid, Spain Physics Dept. University of Alaska Fairbanks AK

More information

Standards of Conduct for Transmission Providers

Standards of Conduct for Transmission Providers Standards of Conduct for Transmission Providers Posted and Effective as of December 30, 2016 Puget Sound Energy ( PSE ) is a public utility that owns, operates, and controls facilities used for the transmission

More information

Enabling Cannabis Retail Stores and Facilities Land Use Bylaw

Enabling Cannabis Retail Stores and Facilities Land Use Bylaw 2018 February 21 Page 1 of 12 EXECUTIVE SUMMARY This report proposes new rules to regulate the retail sale of cannabis in the Land Use Bylaw (LUB). The goal is to provide broad opportunities for cannabis

More information

Stafff Paper Prepared by: Corey Freije. December 2018

Stafff Paper Prepared by: Corey Freije. December 2018 UPPER MIDWEST MARKETING AREA ANALYSIS OF COMPONENT LEVELS AND SOMATIC CELLL COUNT IN INDIVIDUAL HERD MILK AT THE FARM LEVEL 2017 Stafff Paper 18-022 Prepared by: Corey Freije December 2018 Federal Milk

More information

Acceptable Use Policy - Phone

Acceptable Use Policy - Phone These terms are current as of August 5, 2017 and are subject to change from time to time. Please visit shaw.ca for the most current Terms of Use. Acceptable Use Policy - Phone Introduction Thank you for

More information

Stallings, Kristy. Kristy,

Stallings, Kristy. Kristy, Stallings, Kristy From: Sent: To: Cc: Subject: Attachments: Keith Copaken Wednesday, February 08, 2012 9:18 AM Stallings, Kristy 'Snyder, John L.'; 'Jeff DeGasperi'; MSchlup TDD Exec Summary for FAED Submittal

More information

Development Bank of Southern Africa Amendment Bill [B ]

Development Bank of Southern Africa Amendment Bill [B ] Development Bank of Southern Africa Amendment Bill [B 2-2014] Briefing of Select Committee on Finance National Council of Provinces 21 October 2014 Presenters : Mr Ben Mokheseng Deputy Director: Asset

More information

STAFF REPORT City of Lancaster NB 2

STAFF REPORT City of Lancaster NB 2 STAFF REPORT City of Lancaster NB 2 12/13/16 MVB Date: December 13, 2016 To: From: Subject: Mayor Parris and City Council Members Mark V. Bozigian, City Manager Allison E. Burns, City Attorney Ordinance

More information

Integrated Impact Assessment Report for Service Specifications

Integrated Impact Assessment Report for Service Specifications Integrated Impact Assessment Report for Service Specifications Service Specification Reference Service Specification Accountable Commissioner B14/S/a Urological cancers Specialised kidney, bladder and

More information

ORDINANCE NO

ORDINANCE NO ORDINANCE NO. 02011-06 AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF YUMA, ARIZONA, AMENDING CHAPTER 154 OF THE YUMA CITY CODE, AS AMENDED, RELATING TO ZONING REGULATIONS, PROVIDING FOR CHANGES TO THE

More information

A Day in the Life of a Transactive Grid

A Day in the Life of a Transactive Grid A Day in the Life of a Transactive Grid GridWise Architecture Council Presented to: National Council of State Legislators Webinar March 5, 2015 Mark Knight and Tom Sloan GWAC Members Ron Melton GWAC Administrator

More information

Cannabis Legalization Festivals and Events

Cannabis Legalization Festivals and Events 2017 June 06 Page 1 of 5 EXECUTIVE SUMMARY As part of the comprehensive set of bylaw amendments which were presented to Council on 2018 April 05, Administration recommended providing an exemption from

More information

Impact of Power System Blackouts M. M. Adibi, IEEE Life Fellow, Nelson Martins, IEEE Fellow

Impact of Power System Blackouts M. M. Adibi, IEEE Life Fellow, Nelson Martins, IEEE Fellow 1 2015 IEEE Power & Energy Society General Meeting Impact of Power System Blackouts M. M. Adibi, IEEE Life Fellow, Nelson Martins, IEEE Fellow Panel Session at the IEEE PES GM 2015 Cascading Failures:

More information

GOVERNING BODY MEETING in Public 22 February 2017 Agenda Item 3.4

GOVERNING BODY MEETING in Public 22 February 2017 Agenda Item 3.4 GOVERNING BODY MEETING in Public 22 February 2017 Paper Title Purpose of paper Redesign of Services for Frail Older People in Eastern Cheshire To seek approval from Governing Body for the redesign of services

More information

Co-location Arrangements for Interconnecting Canadian Carriers

Co-location Arrangements for Interconnecting Canadian Carriers COMPETITOR ACCESS TARI 2nd Revised Page 95 Cancels 1st Revised Page 95 Co-location Arrangements for Interconnecting Canadian Carriers 1. Service Description Co-location is an arrangement whereby Interconnecting

More information