Wick Drains and Piling for Cai Mep Container Port, Vietnam. Bengt H. Fellenius. Sower's Lecture Atlanta May 8, 2012

Similar documents
Bengt H. Fellenius. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot. Amsterdam.

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

PRELIMINARY GEOTECHNICAL DESIGN

EVALUATION OF FIELD PERFORMANCE OF PREFABRICATED VERTICAL DRAINS (PVD) FOR SOIL GROUND IMPROVEMENT IN THE SOUTHERN VIETNAM

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri

NSW Coastal, Ocean and Port Engineering Panel

Numerical analysis of the embedded abutments of integral bridges

Modified Sheet Pile Abutment for Low-Volume Road Bridge

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

Table 3-1 Summary of Storm Drain Outfalls

Use of Ductile Iron Pipe Piles for a New Shared Use Path Bridge over Maribyrnong River in West Melbourne

APPENDIX H. Limit Equilibrium Analysis of Dike 1 Abutments Prior to Failure

RAKED PILES FOR ABUTMENT AND THE BENEFITS OF DRIVEN PRECAST CONCRETE PILES FOR LOW CARBON INFRASTRUCTURE.

ATTACHMENT B8 Incident History

Evaluation of Eurocode 7 Example 2.3 PILE IN CLAY ETC 10. Adriaan van Seters Fugro Ingenieursbureau BV The Netherlands

3/18/03 CE Keith P. Brabant, P.E.

SEEPAGE ANALYSIS OF TWO CASE HISTORIES OF PIPING INDUCED BY EXCAVATIONS IN COHESIONLESS SOILS

First Technology Safety Systems. Design Freeze Status. Flex-PLI-GTR Development

Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge

L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA

Geotechnical Issues Associated With the Design and Construction of the Middle River Bridge

The short path seepage area is between the dam embankment and the bend in the existing drainage tunnel. This area is highlighted in red on the

Permanent deformation of bridge abutment on liquefiable soils

Assessing potential cracking zones in embankment dams

Figure 3: Analytic procedure

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8

Four simply supported steel plate girders (appear to be an old railcar).

The UCD community has made this article openly available. Please share how this access benefits you. Your story matters!

Retrofit to improve earthquake performance of bridge abutment slopes

Appendix B. Shallow Foundations Report

Kentucky Lake Bridge Pipe Pile Load Test Program 45 th Annual STGEC Mobile, AL October 27-30, 2014

Dodge County Drainage Board

DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE

PERFORMANCE OF REINFORCED EARTH BRIDGE ABUTMENT WALLS IN THE CANTERBURY EARTHQUAKES

Swell And Compressibility of Fiber Reinforced Expansive Soils

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA

Flume Installation Instructions

Height Calibration Log Sheet

Performance of Vetiver Grass in Protecting Embankments on the Bangladesh Coast against Cyclonic Tidal Surge

Shifting the Canning Bus Bridge Sideways

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

Appendix C Guidelines for Design of Integral Abutments March 3, 2003

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39

Modified Sheet Pile Abutments for Low-Volume Road Bridges

STRUCTURAL STABILITY ASSESSMENT

Application of pile underpinning technology on shield machine crossing through pile foundations of road bridge

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

NC DOUBLE OPPOSING HEAD DRILL

Novel treatment technique

Stantec Consulting Ltd Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) Fax: (905)

St. Croix River Crossing Bridge Foundation Load Test Project. 1/27/2010 St. Croix River Crossing Bridge - Foundation Load Test Project

Use of Dilute Flowable Backfill for Corrosion Mitigation of Buried Pipe

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

Prefabricated Vertical Drain with Fabric

Geosynthetic-reinforced soil bridge abutments

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments

Experimental investigation of axial load on low cycle fatigue performance of steel H piles in integral bridges

NUMERICAL ANALYSES OF PVD IMPROVED GROUND AT REFERENCE SECTION OF SECOND BANGKOK INTERNATIONAL AIRPORT

APPENDIX A INTEGRAL ABUTMENTS

Architect/Contractor/QS/Sub-Contractor/C of W/RE/File ref PiMS Documents Site Visit Report. Item Text Action on

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes

Environmental Effects on Mitosis Advanced Inquiry Lab Big Idea 3, Investigation 7 Introduction: Background:

Monitored Displacements of a Unique Geosynthetic-Reinforced Walls Supporting Bridge and Approaching Roadway Structures

Integral Abutment Bridges-Development of Soil Model for Soil Structure Interaction in Time History Analysis

Emergency Bridge Stabilization at Mile Watrous Subdivision

NCAT Report Comparing Friction Reducers for Use in AMPT Testing. By Adam Taylor, P.E. Nam Tran, Ph.D., P.E., LEED GA

AN EXPERIMENTAL INVESTIGATION ON BEHAVIOR OF RC PARAPET WALL OF ABUTMENT UNDER COLLISION

Clay Sewer Pipe-Joint Infiltration Leak-Rate Testing

5 DAMAGE TO TRANSPORTATION FACILITIES

B. Stipulated Price (Lump Sum). If Contract is Stipulated Price Contract, payment for Work in this Section is included in total Stipulated Price.

Engineering characterization of Vetiver system for shallow slope stabilization

THE UNIVERSITY OF KANSAS KU RECREATION SERVICES FACILITIES MASTER PLAN

EVALUATION OF INTELLIGENT DUAL-LATERAL WELL IN MULTI-LAYERED RESERVOIRS

R-Group Finland Oy. RLS Lifting Sockets Technical Manual According to Eurocodes, EU Machinery directive 2006/42/EC and VDI/BV-BS 6205 CE Approved

EVALUATION ON THE SHEAR STRENGTHENING EFFECT OF RC COLUMNS WITH CARBON FIBER SHEETS

Earthquake Resistance of Bridges With Friction Slab Abutments

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint

Ashton Avenue Integral Bridge

a.the Vetiver Network International b.vietnam Vetiver Network

Intrinsically Safe Ultrasonic Testers: How important are they?

OWNER S MANUAL and INSTALLATION INSTRUCTIONS

Conditional assessment of Kiri Bridge in Shkoder, Albania

Author(s) Flynn, Kevin N.; McCabe, Bryan A.; Egan, D.

The Epidemic Model 1. Problem 1a: The Basic Model

The Structure upon which the ends of a Bridge rests is referred to as an Abutment

Frequently Asked Questions

EFFECTS OF SPATIAL VARIATION OF SEISMIC INPUTS ON BRIDGE LONGITUDINAL RESPONSE

NDT Technology for QA of Flexible Pavement Construction Northeast Asphalt User/Producer Group Annual Meeting Mystic, Connecticut October 17, 2007

Monitoring of a bridge with integral abutments

THERMAL ENERGY STORAGE TANK DOWN UNDER

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017

Plyometrics. Plyo Hurdles (Set of 4) Product Stock

Experimental Procedure

Case To: Oxford Board of Adjustment From: Benjamin Requet, Senior Planner Date: January 09, 2017

Effect of Pile Orientation in Skewed Integral Abutment Bridges

Transcription:

Wick Drains and Piling for Cai Mep Container Port, Vietnam Bengt H. Fellenius Sower's Lecture Atlanta May 8, 2012 1

The Mekong

Saigon/HoChiMinhCity The General Area 3

Thi Vai Port Cai Mep Port 4

Artist View 5

The site of the new container facility extends over an 800 m by 600 m area along the Thi Vai River CG CFS 6

NORTH-SOUTH Locations of Buildings, Boreholes, and Settlement Points 1,200 1,000 N TCM and CPTU SS BH Piezometers Extensometers 800 600 M-Shop 400 Substation BH-14 C-Gate 200 CFS 0 0 100 200 300 400 500 600 700 800 900 1,000 EAST-WEST 7

DEPTH (m) DEPTH (m) DEPTH (m) Soil Profile WATER CONTENT (%) + 3.5 m 0 20 40 60 80 100 GW & GL 0 w P w n w L 0 GRAIN SIZE DISTRIBUTION 0 20 40 60 80 100 CONE CONE STRESS, q t t (MPa) 0.0 1.0 2.0 0 CPTU-26 5 w n BH-14 5 5 10 10 CLAY SILT 10 15 15 15 20 20 20 25 25 25 30 30 30 35 35 35 40 40 SAND 40 w n BH-76 45 w n BH-14 CLAY 45 SILT GRAVEL 45 50 50 50 8

DEPTH (m) DEPTH (m) DEPTH (m) DEPTH (m) CPTU Sounding Results 0 Cone Stress, q t (MPa) 0 2 4 0 Sleeve Friction, f s (KPa) 0 20 40 60 80 100 0 Pore Pressure (KPa) 0 500 1,000 1,500 0 Friction Ratio, f R (%) 0 1 2 3 4 5 5 5 5 5 10 10 10 10 15 15 15 15 20 20 20 20 25 25 25 25 30 30 30 30 35 35 35 35 9

Void Ratio (- -) DEPTH (m) Results from a large series of consolidation tests show the soil to be very compressible, normally consolidated Typical example of results 2.40 2.20 2.00 1.80 1.60 1.40 1.20 1.00 DEPTH: 9 m e 0 = 1.92 C c = 1.40 m r = 55 m = 5 CR = 0.48 10 100 1,000 Stress (KPa) 0 5 10 15 20 25 30 35 Modulus Number, m 0 2 4 6 8 10 From CPTU Sounding From consolidometer Test 10

Risk for flooding in the area is real and the inundation can be severe, as illustrated by the flooding of the Fall of 2011. The above shows an areal photo of a Honda factory parking lot in Bangkok (October 2011). The highest water level expected at the site is Elev. +4.0 m, which level is about 0.5 m above the ground surface. Therefore, the ground elevation will be raised by about 2.0 m to Elev. +5.5 m in order to avoid flooding and to create a suitable foundation surface. 11

Because of the thick very compressible clay and silt layer, the 2+ m thick fill placed to raise the land will cause significant settlement, which would continue for a very long time. To shorten that time, vertical drains (wick drains) were installed to 37 m depth across the site (in some places into the sand, in other places a bit of the clay was left between the drain tip and the sand). Moreover, a temporary surcharge was added raising the surface to Elev. +8 m through Elev. +10 m, i.e., an additional 2.5 m to 4.5 m of fill height. 12

SETTLEMENT FILL HEIGHT Principle of the wick drain and surcharge soil improvement scheme Amount of fill placed Surcharge removed when 80% 90% consolidation is achieved FILL Paving and roadways For case of surcharge not removed For case of surcharge removed ORIGINAL GROUND SURFACE Initial compression and consolidation settlement SETTLEMENT ORIGINAL GROUND SURFACE 80 % to 90 % of total consolidation settlement For case of surcharge removed For case of surcharge not removed TIME 13

The wick drain used for the project is a 100 mm wide and 3 mm thick and consists of a corrugated, 0.15 mm thick, plastic core wrapped with a synthetic filter. 14

Fill height and ground surface settlement until one month before start of driving piles for the building foundations 15

Fill height and pore pressures measured June 24, 2009, through September 17, 2010 (Days -527 and -77) at the CFS building The tip elevations are per original installed depth. The settlement of the piezometer tips is not included. 16

DEPTH (m) FILL ELEVATION Distribution with depth of the pore pressures at the CFS building PORE PRESSURES JUNE 24, 2009 THROUGH SEP 17, 2010 (KPa) + 5.0 m 0 5 0 50 100 150 200 250 300 350 400 U 0 June 24, and Sep 18, '09 just before adding surcharge (Days -504 and -447). Sep 17, '09 last reading (Day -77). Dec 1, '09 maximum reading (Day -365). 10 15 20 25 30 35 40 17

Settlement (mm) 09-01-01 Ground surface settlements DAYS 10-12-01 Start of pile driving for the CFS and CG buildings 0-800 -700-600 -500-400 -300-200 -100 0 500 1,000 SS-108 1,500 2,000 SS-38 SS-39 SS-30 Surcharge removal SS-29 2,500 SS-32 SS-104 SS-28 3,000 3,500 4,000 Container Freight Station, CFS and Container Gate, CG 18

View on October 4, 2011, taken from the south-east end of CFS building showing some of the about 1,680 piles driven for the CFS. 19

The building foundations were placed on precast, ordinary reinforced, concrete piles with a square 400 mm cross section made up by 10-m segments spliced in the field by welding steel end-plates together. For Buildings CFS and CG, the piles were driven to 28 m and 18 m depth, respectively. The intended working loads were 347 KN for the CFS building and 265 KN for the other buildings. One pile at each building was subjected to a static loading test. The test piles were not instrumented, and the test schedule included unloading/reloading cycles and varying load hold durations. Therefore, the test results have very limited use for the design. The static loading tests (CFS and CG) were carried out in September 2010, nine months after pile driving Load-movement curves from static loading tests at CFS and CG buildings 20

21

22

Settlement (mm) The below figure shows the settlements measured by the SS-plates at or near the buildings until November 15, 2011. The zero date is December 1, 2010, the day of the start of the pile driving for the CGS building. Driving was completed on January 24 at the CG building. DAYS 0-800 -700-600 -500-400 -300-200 -100 0 100 200 300 400 500 500 Surcharge removal Pile driving 1,000 SS-108 SS-30 1,500 2,000 SS-39 2,500 SS-108 3,000 SS-28 SS-29 SS-38 SS-32 3,500 4,000 Container Freight Station, CFS and Container Gate, CG SS-104 23

Settlement (mm) ELEVATION (mm) 10,000 9,000 AS-PLACED FILL HEIGHT 8,000 7,000 6,000 SS-29 SS-28 ELEV. +5.5 m 5,000 MAXIMUM WATER LEVEL 4,000 3,000 ORIGINAL GROUND SURFACE MEAN WATER LEVEL 2,000-800 -700-600 -500-400 -300-200 -100 0 100 200 300 400 500 600 DAYS PILE DRIVING Start placing fill End placing surcharge Removing surcharge Pile driving DAYS 0-800 -700-600 -500-400 -300-200 -100 0 100 200 300 400 500 600 500 1,000 1,500 2,000 2,500 Red heavy lines are SS-28 and SS-29 All values are normalized to the 2,900 mm average settlement at Day 0 3,000 400 mm 3,500 AT CFS and CG 4,000 24

NORTH-SOUTH Settlement (mm) Pile head settlements and benchmark settlements at the building locations 400 350 300 250 200 CONTAINER FREIGHT STATION, CFS AND CONTAINER GATE SS-22 SS-23 SS-24 SS-29 SS-108 SS-30 C-Gate SS-227 SS-37 SS-36 SS-235 SS-236 DAYS -800-700 -600-500 -400-300 -200-100 0 100 200 300 400 500 0 Surcharge Pile 500 1,000 removal SS-108 SS-30 driving 1,500 150 100 50 SS-102 SS-228 SS-28 SS-230 CFS Pz-09 Ext-09 SS-33 SS-34 SS-233 SS-234 2,000 2,500 3,000 SS-39 SS-28 CFS Average of Piles added to SS29 C-Gate Average of Piles added to SS108 SS-29 SS-108 SS-38 SS-32 0 500 550 600 650 700 750 800 850 900 EAST-WEST 3,500 4,000 Container Freight Station, CFS and Container Gate, CG SS-104 Container Freight Station (CFS) and Container Gate (CG) 25

Settlement (mm) Settlements measured for SS-plates and piles at the CFS and CG buildings until November 15, 2011 2,500 DAYS -100-50 0 50 100 150 200 250 300 350 400 450 500 2,600 2,700 CG Average values of pile head settlement added to SS-108 2,800 SS-108 2,900 3,000 CFS Average values of pile head settlement added to SS-29 SS-29 26

DEPTH (m) Settlement distribution measured in an extensometer station (multi-anchor points) outside the CFS building during 18 months: from July 17, 2009 (one to three months after start of placing fill) through January 14, 2011, one month after piles were driven near the location of the extensometer station. + 5.0 m 0.0 0.5 1.0 1.5 2.0 2.5 3.0 0 First Fill Surface 5 SETTLEMENT (m) Relative settlement between anchor points during last five months of monitoring 10 15 June 29, 2010, after the temporary surcharge had been removed R 4 mm/m 20 R 6 mm/m R 12 mm/m 25 R 30 mm/m July 17, 2009 January 14, 2011 30 35 40 Zero Reading of was taken on July 17, 2009. The settlement plates located within the CFS footprint then showed that 0.6 m settlement had already occurred (since February 20, 2009). Total plate settlement on January 14, 2011, was 3.08 m. The curves show readings spaced about one month apart. 27

STRESS (KPa) From measured fill height and settlement to input to analysis 140 120 100 80 60 40 20 0 Stress from as-placed fill (approximated) Stress from fill adjusted for settlement and buoyancy 0 5 10 15 20 25 30 35 40 MONTHS Removal of Surcharge Stress from fill elevation Stress reduction due to settlement and buoyancy 28

UniSettle4 input and results [www.info@unisoftltd.com] 29

UniSettle4 input and results [www.info@unisoftltd.com] Input alternatives 30

SETTLEMENT (mm) 0 MONTHS 0 6 12 18 24 30 36 42 500 Immediate Compression Secondary Compression 1,000 1,500 2,000 2,500 Full fill height reached Measured settlement Settlement calculated with the drains assumed functioning along the full depth 3,000 3,500 4,000 Surcharge removed Piles driven Settlement calculated with the drains assumed not to function below 20 m depth 31

28 m CFS Pile 40 m CFS Pile Settlement of the CFS Building for 28 m Pile SETTLEMENT CLAY Neutral Plane SAND Neutral Plane DEPTH 32

View on October 4, 2011, taken from the south end of CFS building showing some of the about 750 piles driven for the CFS building. In the background, lengthened piles are being driven for the CG building. 33

Photos from the driving of piles with extension 39

40

CONCLUSIONS The most probable cause to the continued consolidation below about 20 m depth is that large soil stresses have squashed the wick drains preventing the drains from functioning properly. The consequence is that the overall area and the piles will continue to settle even if no new loads are placed. But there will be new loads, so... The problem with the piled foundations can be (and was hopefully) resolved by lengthening the piles to bring the neutral plane (the depth to the settlement equilibrium) into the non-settling sand below the clay. It is not realistic to install new and better drains or arrange, say, for vacuum treatment to get the consolidation to occur quickly. The site will have to live with continuing to add fill to compensate for excessive settlement, which will in turn add consolidation, and to suffer the maintenance actions that regularly will be required for non-piled foundations. The monitoring scheme was designed to confirm that the wick drain method worked. When the measurements showed that the method did not work, the method became very much inadequate, and it could not be of any assistance for selecting a solution to the problem. Every monitoring programme should have redundancy and be designed to resolve issues should the design show to be unsuccessful. How to resolve the question "what if we're wrong?" should always be kept in mind and in the planning of a monitoring programme. 41

The Lotus Vietnam's National Flower Thank you for your attention 42