The short path seepage area is between the dam embankment and the bend in the existing drainage tunnel. This area is highlighted in red on the

Size: px
Start display at page:

Download "The short path seepage area is between the dam embankment and the bend in the existing drainage tunnel. This area is highlighted in red on the"

Transcription

1

2 2

3 The short path seepage area is between the dam embankment and the bend in the existing drainage tunnel. This area is highlighted in red on the picture in the top left hand corner. Water in this pathway seeps through fluvial sediments and rockslide debris and into downstream dam embankment. Recent drilling indicates that silt, sand and gravel materials are continuous from the upstream side to downstream side across the bedrock septum saddle. This is important because these materials are highly erodible.

4 Construction drawings show an area along the right abutment where drain material was not placed indicated by the white circle above. Design documents explain that seepage was not anticipated by engineers to happen in this location. The red and blue dots indicate where the Corps has conducted various types of exploration using auger and roto sonic drilling methods. During our exploration, we took samples and conducted analysis to determine if the engineered materials are suitable to filter water passing through the abutment. 4

5 Hydraulic modeling calculates the top of the underground water table. The area of concern is where a steep water line crosses the downstream abutment area. Since this area is not properly filtered, a steep water gradient could potentially erode and pipe soil. 5

6 6

7 During the January 2009 flood pool of record ( feet), several symptoms of erosion developed along the right abutment. To test for the existence of preferential water seepage paths, the Corps used food grade dyes along the right abutment during the summer conservation pool. The dye locations are shown above in the picture by the red, green, blue and orange dots. The arrows point to where the dyes traveled. The Corps placed activated charcoal packs at key locations in the existing drainage tunnel and at other drain locations in the right abutment. Activated charcoal is a very sensitive way to collect samples and can detect very low concentrations in parts per billion. Sensitive collection methods are necessary since the dyes dissolve into the water table, and they travel through the abutment in very low concentrations. The Corps determined that dyes traveled very quickly through the abutment. In some cases, dye traveled over 400 feet in as little as 20 minutes. 7

8 Preliminary results of testing in 2010 indicate that many preferential seepage paths detected in the 2009 dye test have been significantly changed. A single test conducted with the reservoir at elevation 1,170 was conducted by introducing dyes at various locations along the right abutment. Activated charcoal packs were placed at key drain locations to absorb even trace amounts of dye. Samples were sent to a laboratory and results were compiled by the Corps. Our findings indicate that preferential seepage paths have been reduced as a result of the placement of the 2009 grout curtain. 8

9 A piezometer is a device that measures water level in the ground. The Corps has installed many of these devices in the right abutment and logs the data year round. We conducted a comparison between these water levels before we placed the new filtered drains (the blue lines in the picture above) and the grout curtain (also shown above). The size of the blue dots indicate specific water level differences between 2009 and The larger the dot, the larger the difference between water levels. As shown in the picture, many of the instruments in the critical area show reduced water levels. This is a positive sign that the installed horizontal drains are safely removing water out of the area of concern. 9

10 Willowstick is a company which uses electricity to find the pathways that water follows underground. By placing electrodes upstream and downstream, scientists can measure the intensity of electrical current at survey points along the right abutment. Since both water and electricity follow the path of least resistance, more electrical current at a given survey location would mean that water is flowing under there. The illustration above shows that most water is flowing around the end of the grout curtain. This is a positive sign, since water now has to flow nearly three times as far as it did in the past in order to reach the short path seepage area. The line which apparentlygoes through the grout curtainis is actually flowing underneath the grout curtain, using an isolated lower aquifer that does not pose a significant seepage risk. 10

11 11

12 12

13 Water follows the path of least resistance. The Corps will add filtered drains to the short path seepage area to provide water an easy path to safely flow out of the right abutment. Like a sponge, the right abutment soaks up a great deal of water from the reservoir especially during high pools. By adding a row of filtered drains across water s path, the drains will intercept the water and provide it a way to safely exit from the abutment. If these filtered drains did not exist, water would exit naturally through unfiltered springs. This presents a danger, because the unfiltered exit would potentially allow water to move dirt out of the abutment. If enough dirt underneath the abutment is removed, the abutment could potentially collapse. The Corps is racing ahead to install these filtered drains with pumps in order to remove excess water from the short path seepage area. After the drainage tunnel spur is complete, the pumps would be removed and the drains tied in with the tunnel to allow gravity to do the work of the pumps. 13

14 Adding a tunnel spur and tying in the filtered drains will allow gravity to pull water through the filters and into the tunnel. Water can then flow out the tunnel works and into the Green River. The drains will be installed before the tunnel spur. The Corps believes filtered drains and a tunnel will be effective, as the additional horizontal drains installed in the existing tunnel (completed in 2009) have been proven to work effectively. Design of the tunnel spur is currently at the conceptual level. Design and construction schedules are estimates. Proposed location of the spur is indicated in red on the picture and will generally spanan underground bedrock saddle andtie into two bedrock knobs on either side of the saddle. 14

15 This is a cross section of the short path seepage area. The brown area at the bottom is bedrock. The grainy material above that is the landslide material that water moves through. The Zone 3 Material and Rock Shell are engineered materials that are designed to filter the water before it leaves the downstream face of the abutment. The Corps is concerned that these engineered materials are not adequate to filter water exiting from the abutment during high pools in the reservoir. The blue area represents water that saturates the landslide material and the engineered materials. 15

16 The Corps plans to install filtered drains and pumps into the short path seepage area of the abutment. Like a kid sucking juice through a straw leaving the ice behind, the pumps and filtered drains will draw the water out of the ground, leaving the soil behind. By safely pumping the water out, the water level in the landslide material is reduced. Lower water levels will prevent pressures from building up near the base of the abutment. 16

17 The Corps plans to add a tunnel spur to the existing drainage tunnel in the right abutment. By adding this tunnel, the Corps will tie in the filtered drains and use gravity to pull the water out of the landslide material. Compare this to pumping that we did at first. We can use gravity just like a pump to remove the water, with the benefit that gravity is free and does not need to be maintained like a pump. The tunnel will provide the water safe passage out to the Green River. 17

18 There are other things that need to be fixed at the dam. A new and improved debris boom is necessary to prevent logs and other debris, that washes off of the hills into the reservoir, from reaching the dam spillway. If the spillway got clogged, it could cause the dam to be overtopped in an extreme flood event. The spillway has never been used, because it is reserved for that extreme flood event that would generate a high reservoir pool. In the event of an extreme flood, our engineers believe that large quantities of water flowing over the spillway would cause it to lift up and become unstable. By putting in rock anchor bolts, the spillway concrete would be bolted to the bedrock it lays on and stay in place. Also, the rock currently on the face of the dam near the spillway is weathered and needs to be replaced (see area in red above). Should we need to use the spillway in an extreme flood event, there would be large volumes of water that could erode the face of the dam near the entrance to the spillway. Although the chances of an extreme flood event are very small, these issues are things the Corps needs to fix. 18

19 As stated earlier, the Corps is racing ahead to install filtered drains in the short path seepage area as soon as possible. The tunnel spur is currently being designed and we anticipate starting construction on that project towards the middle of next year. Other projects would begin this winter. Certainly, as is always the case, beginning these projects depends on the availability of funds to support design and construction commitments. 19

20 20

21 This "La Niña" forecast was provided Aug. 5, 2010, by NOAA Climate Prediction Center. Last year was El Niño, and that pattern tends to suppress flooding weather patterns in the Northwest, and sure enough it did. This year is La Niña (strength unclear at this point), and that pattern tends to see more storms and flooding than El Niño; therefore the odds for flooding are higher this upcoming winter, but it is not a guarantee. The picture above is a satellite photo of an atmospheric river or pineapple express where the air flow draws moisture from Hawaii and dumps it over the Pacific Northwest. They are called atmospheric rivers because these weather events are narrow (like a river) and are estimated to carry more water than the Mississippi River. They are like a fire hose as they focus their abundant precipitation over our relatively small watersheds, engorging rivers in as little as 48 hours. This atmospheric river produced the historic Northwest flooding of early February

22 The Corps has people who work at the dam every day. They monitor the dam, make frequent inspections and take instrument readings. They compile reports and send them to scientists and engineers at the Seattle District for regular analysis. If a storm event begins to fill the reservoir, we intend to increase the frequency and intensity of monitoring. If we think we are going to be managing a flood pool, we will place engineers and geologists directly on the dam. That way they can make first hand observations and measurements of how the dam is performing. In terms of how much water we would ultimately store above 1170 feet, COL Anthony Wright, the District EngineerandCommander Commander, will make real time decisions based on the weather forecast, river flows in the lower Green River Valley and information about how the dam is performing while holding back the flood pool. 22

23 We have come a long way in terms of understanding what is wrong with Howard Hanson Dam, and how we are going to fix it. All the work performed last summer and our testing this summer have improved our confidence in the dam. However, there is still around a 1:60 chance of flooding in the lower Green River Valley. La Niña, with her frequent and possible back to back storms, may lead to a decision to rapidly draw down a flood pool. PLEASE keep in mind that even with the dam restored to full capacity, the residents of the Green River Valley live on a flood plain and are always at risk for flooding. We hope to restore Howard Hanson Dam to its full 1:140 capabilityby by mid 2012, but that does not prevent flooding for ALL storms. 23

24 24

25 Completing the Dam Safety Modification Study is very important and is considered a top priority to the Seattle District. We are currently on schedule to deliver a completed Dam Safety Modification Study. The study will identify several measures we think will provide a lasting fix to Howard Hanson Dam. This study is required before any repair can be considered permanent. The study can recommend that temporary measures become permanent, but in order for them to be considered so, the study has to completed and approved. 25

26 26

Hanson Dam s mysteries solved

Hanson Dam s mysteries solved Hanson Dam s mysteries solved Hanson: Earth dams are expected to leak MIKE ARCHBOLD; STAFF WRITER STAFF WRITER LAST UPDATED: APRIL 27TH, 2011 06:34 AM (PDT) It had the makings of a doomsday scenario. Two

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Fly Ash Pond Big Sandy Plant Louisa, Kentucky October, 2016 Prepared for: Kentucky Power Big Sandy Plant Louisa, Kentucky Prepared by: American Electric Power

More information

ATTACHMENT B8 Incident History

ATTACHMENT B8 Incident History Appendix B GIS/Imagery Outputs ATTACHMENT B8 Incident History Appendix B - GIS/Imagery Outputs Appendix B: Attachment B8 Incident History TABLE OF CONTENTS B.B8-1 INTRODUCTION... 1 B.B8-2 FACT SHEETS...

More information

Four simply supported steel plate girders (appear to be an old railcar).

Four simply supported steel plate girders (appear to be an old railcar). BRIDGE INSPECTION BRIDGE NO./NAME N4-005: Akolkolex Crawford FSR (19.0 km) Inspection Date: September 22 nd, 2012 Inspected By: M. Hanson, R. Veitch Year Built: 1982 Number of Spans: 1 Span Lengths: Superstructure

More information

NORTH DAKOTA 2011 FLOOD EVENT

NORTH DAKOTA 2011 FLOOD EVENT NORTH DAKOTA 2011 FLOOD EVENT OUTLINE Missouri River Basin Geography Generic Reservoir Operations Weather and Climate 2011 Basin-wide Hydrology Missouri River Timeline Missouri River Damages Mouse River

More information

The Fontenelle Dam Incident: The Investigation, Likely Causes, and Lessons (Eventually) Learned 8/3/11

The Fontenelle Dam Incident: The Investigation, Likely Causes, and Lessons (Eventually) Learned 8/3/11 The Fontenelle Dam Incident: The Investigation, Likely Causes, and Lessons (Eventually) Learned 8/3/11 Presented to: Association of State Dam Safety Officials, Annual Conference, Washington DC, September

More information

Inspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin.

Inspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin. Inspection Report River Falls Hydroelectric Project FERC Project No. P-10489 Junction Falls Dam River Falls, Wisconsin Prepared for: River Falls Municipal Utilities River Falls, Wisconsin December 2009

More information

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563 Interstate Power and Light Company Burlington Generation Station CCR Surface Impoundment Annual Inspection Report 154.018.012.001 Report issued: December 21, 2016 Hard Hat Services ph: 877-630-7428 hardhatinc.com

More information

Welcome. Recreational Enhancements on the Lehigh River Public Information Workshop 18 February 2010

Welcome. Recreational Enhancements on the Lehigh River Public Information Workshop 18 February 2010 Welcome Recreational Enhancements on the Lehigh River Public Information Workshop 18 February 2010 Cooperating Agencies Delaware River Basin Commission Pennsylvania Fish & Boat Commission Pennsylvania

More information

SEEPAGE ANALYSIS OF TWO CASE HISTORIES OF PIPING INDUCED BY EXCAVATIONS IN COHESIONLESS SOILS

SEEPAGE ANALYSIS OF TWO CASE HISTORIES OF PIPING INDUCED BY EXCAVATIONS IN COHESIONLESS SOILS ICCI2004, The First International Conference on Construction IT, Beijing, CHINA, August 12 th - 14 th SEEPAGE ANALYSIS OF TWO CASE HISTORIES OF PIPING INDUCED BY EXCAVATIONS IN COHESIONLESS SOILS Cai,

More information

on the Lehigh River Public Information Workshop

on the Lehigh River Public Information Workshop Recreational Enhancements on the Lehigh River Public Information Workshop 16 February 2011 Cooperating Agencies US Army Corps of Engineers Philadelphia l District i Delaware River Basin Commission Pennsylvania

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: FEBRUARY 12 THROUGH FEBRUARY

More information

Using the sharp-crested weir formula the outflow was:

Using the sharp-crested weir formula the outflow was: Date: 2009 July 16 11:00 AM 14 Island Lake Dam Inspection Report Persons Present: Bryon Keene, P.Eng. Harry Stinson Brett Dark (14 Island Lake Association) Peter Peart (14 Island Lake Association) The

More information

Bank Erosion and Bridge Scour

Bank Erosion and Bridge Scour JULY 2017 NCHRP PRACTICE-READY SOLUTIONS FOR Bank Erosion and Bridge Scour NCHRP NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM RESEARCH TOPIC HIGHLIGHTS INTRODUCTION Bank Erosion and Bridge Scour: NCHRP

More information

Prepared for: Butte County Department of Water Resource Conservation (BCDWRC) Project No: County of Butte Contract Number: 18050

Prepared for: Butte County Department of Water Resource Conservation (BCDWRC) Project No: County of Butte Contract Number: 18050 10540 White Rock Road, Suite 180 Rancho Cordova, California, 95670 Tel: 916-444-0123 phone Fax: 916-635-8805 fax Prepared for: Butte County Department of Water Resource Conservation (BCDWRC) Project No:

More information

2006 RALSTON AFTERBAY WATER TEMPERATURE INVESTIGATION STUDY REPORT

2006 RALSTON AFTERBAY WATER TEMPERATURE INVESTIGATION STUDY REPORT Placer County Water Agency Middle Fork American River Project (FERC Project No. 2079) 2006 RALSTON AFTERBAY WATER TEMPERATURE INVESTIGATION STUDY REPORT Placer County Water Agency 144 Ferguson Road Auburn,

More information

PRELIMINARY GEOTECHNICAL DESIGN

PRELIMINARY GEOTECHNICAL DESIGN PNCC Manawatu River Pedestrian/ Cycle Bridge PRELIMINARY GEOTECHNICAL DESIGN 1 Introduction Opus has been commissioned by the Palmerston North City Council (PNCC) to prepare a Detailed Business Case (DBC)

More information

Assessing potential cracking zones in embankment dams

Assessing potential cracking zones in embankment dams Southern Cross University epublications@scu 23rd Australasian Conference on the Mechanics of Structures and Materials 2014 Assessing potential cracking zones in embankment dams Ke He University of New

More information

THE VETIVER SYSTEM FOR SLOPE AND ROAD STABILIZATION AND EROSION CONTROL IN THE DEMOCRATIC REPBULIC OF THE CONGO. BY Eng.

THE VETIVER SYSTEM FOR SLOPE AND ROAD STABILIZATION AND EROSION CONTROL IN THE DEMOCRATIC REPBULIC OF THE CONGO. BY Eng. THE VETIVER SYSTEM FOR SLOPE AND ROAD STABILIZATION AND EROSION CONTROL IN THE DEMOCRATIC REPBULIC OF THE CONGO BY Eng. Alain NDONA NZEY DR Congo country-wide data * Land area is equal to 2.345.410 square

More information

\\H\15\ PH9 Inspection Photos

\\H\15\ PH9 Inspection Photos SHOP SLIDE Photo 1. at cracking across the footpath at the end of the Hwy 2 EB to Hwy 684 SB off ramp at the 99 Ave. intersection. Drop in asphalt trail (background) has worsened since 2013 and is now

More information

Welcome. Recreational Enhancements on the Lehigh River Public Information Workshop 31 January 2008

Welcome. Recreational Enhancements on the Lehigh River Public Information Workshop 31 January 2008 Welcome Recreational Enhancements on the Lehigh River Public Information Workshop 31 January 2008 Cooperating Agencies US Army Corps of Engineers Philadelphia District Delaware River Basin Commission Pennsylvania

More information

Bridge Office Trunk Highway Bridge Flood Response Plan

Bridge Office Trunk Highway Bridge Flood Response Plan Bridge Office Trunk Highway Bridge Flood Response Plan Updated 7/18/2012 Purpose Bridges are vulnerable to damage and failure during flooding. Scour may undermine the bridge foundations or remove the protection

More information

Cavitation. Cameron Fritz, John Glover, Maia Griswold

Cavitation. Cameron Fritz, John Glover, Maia Griswold Cavitation Cameron Fritz, John Glover, Maia Griswold CIVE 401, Hydraulic Engineering Dr. P.Y. Julien November 19, 2014 Table of Contents Introduction Page 1 Theory Page 2 Failures Page 5 Prevention Page

More information

Investigating Epidemics in Our Ecosystem

Investigating Epidemics in Our Ecosystem Chapter Global Health Chapter Science Investigation Investigating Epidemics in Our Ecosystem reference materials or access to the Internet Find Out Do this activity to see how quickly harmful agents of

More information

County of Orange. Presented to the Flood Division August 13, 2001 by Nadeem Majaj

County of Orange. Presented to the Flood Division August 13, 2001 by Nadeem Majaj Using HECRAS TO Evaluate Scour At Bridges County of Orange Presented to the Flood Division August 3, 200 by Nadeem Majaj Approximately 575,000 bridges are built over waterways in the US. The most common

More information

Flume Installation Instructions

Flume Installation Instructions Flume Installation Instructions To ensure a successful installation, it is important to keep the following points in mind: 1) There should be no bend, dips, elbows, or flow junction immediately upstream

More information

Wick Drains and Piling for Cai Mep Container Port, Vietnam. Bengt H. Fellenius. Sower's Lecture Atlanta May 8, 2012

Wick Drains and Piling for Cai Mep Container Port, Vietnam. Bengt H. Fellenius. Sower's Lecture Atlanta May 8, 2012 Wick Drains and Piling for Cai Mep Container Port, Vietnam Bengt H. Fellenius Sower's Lecture Atlanta May 8, 2012 1 The Mekong Saigon/HoChiMinhCity The General Area 3 Thi Vai Port Cai Mep Port 4 Artist

More information

Bengt H. Fellenius. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot. Amsterdam.

Bengt H. Fellenius. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot. Amsterdam. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot Bengt H. Fellenius Amsterdam May 27, 216 Fellenius, B.H. and Nguyen, M.H., 213. Wick Drains and Piling for

More information

CHAPTER 11 APPENDIX D

CHAPTER 11 APPENDIX D OFFICE OF STRUCTURES STRUCTURE HYDROLOGY AND HYDRAULICS DIVISION CHAPTER 11 APPENDIX D SCOUR COUNTERMEASURES FOR PIERS AND ABUTMENTS MAY 2015 Maryland SHA Office of Structures, Chapter 11, Appendix D May2015Page

More information

Appendix B. Shallow Foundations Report

Appendix B. Shallow Foundations Report 12/10/2013 GEOTECHNICAL MANUAL Appendix B. Shallow Foundations Report PLEASE NOTE A sample foundations report is included here for reference. It is provided as an example of content, format, and organization

More information

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017 Introduction Substructure Inspection and Rating That portion of the bridge located below the bearings Abutments Piers Rated separately Purpose is to: Receive the loads from the superstructure Transfer

More information

Slope Stabilization in Itaipava Petropolis, RJ, Brazil Using Vetiver Solution A Total Success.

Slope Stabilization in Itaipava Petropolis, RJ, Brazil Using Vetiver Solution A Total Success. Slope Stabilization in Itaipava Petropolis, RJ, Brazil Using Vetiver Solution A Total Success. By Paulo R.Rogerio,PE,Geotechnical Consulting Engineer Pomerode SC Brazil email: prrog@terra.com.br and Joao

More information

Memorandum AECOM tel fax ABN

Memorandum AECOM tel fax ABN AECOM Australia Pty Ltd Level 10, Tower Two 727 Collins Street Melbourne VIC 3008 Australia www.aecom.com +61 3 9653 1234 tel +61 3 9654 7117 fax ABN 20 093 846 925 Memorandum To David Hitchcock Page 1

More information

Gewässer Umwelt Schutz

Gewässer Umwelt Schutz Gewässer Umwelt Schutz GmbH CUW Oil protector Assembly instructions 2 Foreword Always study this assembly instruction manual before Installation and initial operation. This assembly instruction manual

More information

Prepared for Friends of the Corte Madera Creek Watershed. By Ross Taylor and Associates

Prepared for Friends of the Corte Madera Creek Watershed. By Ross Taylor and Associates CATALOG OF STREAM CROSSINGS WITH CULVERTS AND OTHER MANMADE IMPEDIMENTS TO FISH PASSAGE LOCATED ON ANADROMOUS STREAM REACHES WITHIN FAIRFAX CREEK, CORTE MADERA CREEK WATERSHED, MARIN COUNTY, CA. Prepared

More information

B. Stipulated Price (Lump Sum). If Contract is Stipulated Price Contract, payment for Work in this Section is included in total Stipulated Price.

B. Stipulated Price (Lump Sum). If Contract is Stipulated Price Contract, payment for Work in this Section is included in total Stipulated Price. Section 02222 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Abandonment in place of existing sewers, junction structures, manholes, and force mains. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment

More information

WATER LEVEL. Measurements. A publication of the High Plains Underground Water Conservation District

WATER LEVEL. Measurements. A publication of the High Plains Underground Water Conservation District LEVEL WATER Measurements 2017 A publication of the High Plains Underground Water Conservation District In this issue: Jason Coleman, P. E. Results of the 2017 water level measurements are included in this

More information

Frequently Asked Questions

Frequently Asked Questions Frequently Asked Questions How does the SMRT-Y work? The SMRT-Y sensor accurately measures the moisture level in the soil. When the soil is dry, the SMRT-Y allows the irrigation controller to water as

More information

Lessons learned in multi-objective urban detention basin projects

Lessons learned in multi-objective urban detention basin projects Lessons learned in multi-objective urban detention basin projects Raymond Wong, PhD, PE, LEED AP Patrick Sullivan, PE Bill Silva, PE Floodplain Management Association Conference September 6, 2017 Urban

More information

Radon may also be present in well water, and can be released into the air in your home when water is used for showering and other household uses.

Radon may also be present in well water, and can be released into the air in your home when water is used for showering and other household uses. What Is Radon? Radon is a tasteless, odorless, invisible gas that occurs naturally throughout the earth's crust. It is a by-product of the breakdown of uranium in the soil, rock, and water. Over time,

More information

APPENDIX H. Limit Equilibrium Analysis of Dike 1 Abutments Prior to Failure

APPENDIX H. Limit Equilibrium Analysis of Dike 1 Abutments Prior to Failure APPENDIX H Limit Equilibrium Analysis of Dike 1 Abutments August 25, 2016 Appendix H Limit Equilibrium Analysis of Dike 1 Abutments TABLE OF CONTENTS H1 INTRODUCTION... 1 H2 ENGINEERING PROPERTIES OF THE

More information

Endoscopic Retrograde Cholangiopancreatography (ERCP)

Endoscopic Retrograde Cholangiopancreatography (ERCP) Endoscopic Retrograde Cholangiopancreatography (ERCP) Medical Imaging and Treatment of the Bile and Pancreatic Ducts CIE-02718 Understanding ERCP Brochure Update_F.indd 1 7/11/18 9:51 A Minimally Invasive

More information

Table of Contents. Introductory Command Message & Foreword Table of Contents

Table of Contents. Introductory Command Message & Foreword Table of Contents EP 310-1-6a Introduction Section 1 Introduction Section 2 Principles and Guidelines Section 3 Program Plan and Documentation Section 4 Design Standards Section 5 Identification Signs Introductory Command

More information

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN 7-1.0 INTRODUCTION 7-2.0 RIGID PAVEMENT DESIGN 7-2.01 Cross Sections 7-2.02 Ramps and Loops with Storage Area 7-2.03 Major Forks, Branch

More information

Performance of Vetiver Grass in Protecting Embankments on the Bangladesh Coast against Cyclonic Tidal Surge

Performance of Vetiver Grass in Protecting Embankments on the Bangladesh Coast against Cyclonic Tidal Surge 5 th National Conference on Coastal and Estuarine Habitat Restoration Preparing for Climate Change: Science, Practice, and Policy Performance of Vetiver Grass in Protecting Embankments on the Bangladesh

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 4992 CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

PEAK FLOW REDUCTION OPPORTUNITIES IN THE CASCADE CREEK TRIBUTARIES. Final Report. Olmsted County, MN November 2008 Project Number:

PEAK FLOW REDUCTION OPPORTUNITIES IN THE CASCADE CREEK TRIBUTARIES. Final Report. Olmsted County, MN November 2008 Project Number: PEAK FLOW REDUCTION OPPORTUNITIES IN THE CASCADE CREEK TRIBUTARIES Final Report Olmsted County, MN November 28 Project Number: 362-614 COUNTY OF OLMSTED PEAK FLOW REDUCTION OPPORTUNITIES IN THE CASCADE

More information

Adam D. James, P.E., CFM Eric Y. Chow, P.E., CFM. NRCS DAM RISK ASSESSMENTS Sites 6 and 8 Eddy and Chaves Counties, New Mexico

Adam D. James, P.E., CFM Eric Y. Chow, P.E., CFM. NRCS DAM RISK ASSESSMENTS Sites 6 and 8 Eddy and Chaves Counties, New Mexico Adam D. James, P.E., CFM Eric Y. Chow, P.E., CFM NRCS DAM RISK ASSESSMENTS Sites 6 and 8 Eddy and Chaves Counties, New Mexico Cottonwood Walnut Creek watershed, drains east to the Pecos River Purpose to

More information

LAKE NAIVASHA. A Lake in Trouble. A Possible Solution?

LAKE NAIVASHA. A Lake in Trouble. A Possible Solution? LAKE NAIVASHA A Lake in Trouble A Possible Solution? THE PROBLEM Significant and dangerous reduction in the size of the Lake Naivasha water body and serious degradation of water quality caused by: 1. Large

More information

MONTANA FLUME. User s Manual. Montana (Short Parshall) Flume User s Manual

MONTANA FLUME. User s Manual. Montana (Short Parshall) Flume User s Manual MONTANA FLUME User s Manual i Montana (Short Parshall) Flume User s Manual TABLE OF CONTENTS Introduction to the Montana Flume... 1 Function... 1 Design... 1 Standards... 2 Accuracy... 3 Dimensions...

More information

Urban Drainage and Flood Control District. Goldsmith Iliff Pond E-19 Survey

Urban Drainage and Flood Control District. Goldsmith Iliff Pond E-19 Survey Urban Drainage and Flood Control District Goldsmith Gulch @ Iliff Pond E-19 Survey GOLDSMITH GULCH @ ILIFF ALERT ID: 653/654 LID: ILFC2 Prepared by: HDR Engineering, Inc. 303 E 17 th Ave. Suite 700 Denver

More information

Retrofit to improve earthquake performance of bridge abutment slopes

Retrofit to improve earthquake performance of bridge abutment slopes Proceedings of the Ninth Pacific Conference on Earthquake Engineering Building an Earthquake-Resilient Society 14-16 April, 2011, Auckland, New Zealand Retrofit to improve earthquake performance of bridge

More information

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014 Updated: 5/15/14 1 What was driver for deciding to slide vs. roll? Overall weight? 2 1. Why the two different slide methods? 2. How much experience should your contractor have to perform the slide work?

More information

PLANT-DRIVEN IRRIGATION FROM THE GROUND UP.

PLANT-DRIVEN IRRIGATION FROM THE GROUND UP. PLANT-DRIVEN IRRIGATION FROM THE GROUND UP. Root Demand Irrigation (RDI ) is an innovative irrigation approach that allows plants to control the water they receive from the ground up based on the needs

More information

IT S A SECRET! (1 Hour) Addresses NGSS Level of Difficulty: 4 Grade Range: K-2

IT S A SECRET! (1 Hour) Addresses NGSS Level of Difficulty: 4 Grade Range: K-2 IT S A SECRET! (1 Hour) Addresses NGSS Level of Difficulty: 4 Grade Range: K-2 OVERVIEW In this activity, students explore how sound waves travel through various materials. They will build a sound transmission

More information

Restoring a More Natural Flow Regime to the Clinton River Watershed. MWEA 87 th Annual Conference June 26, 2012

Restoring a More Natural Flow Regime to the Clinton River Watershed. MWEA 87 th Annual Conference June 26, 2012 Restoring a More Natural Flow Regime to the Clinton River Watershed MWEA 87 th Annual Conference June 26, 2012 Donald D. Carpenter, Ph.D., PE, LEED AP Lawrence Technological University Agenda Study Goals

More information

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill. Bridge Applications Technology The Reinforced Earth Company (RECo) offers a variety of bridge abutment and bridge crossing solutions, each are based on project specific requirements. Bridge abutments are

More information

Emergency Bridge Stabilization at Mile Watrous Subdivision

Emergency Bridge Stabilization at Mile Watrous Subdivision Emergency Bridge Stabilization at Mile 189.70 Watrous Subdivision Christophe Deniaud, Ph.D., P.Eng. Bridge Engineer, CN 10004-104 Avenue Edmonton, Alberta, Canada T5J 0K2 Tel: (780) 421-6021 Fax: (780)

More information

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK Joseph Navarra, P.E, Maryland State Highway Administration, 410-545-8315, jnavarra@sha.state.md.us ABSTRACT The MDSHA

More information

NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION. Initial Annual RCRA CCR Unit Inspection Report

NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION. Initial Annual RCRA CCR Unit Inspection Report INITIAL ANNUAL INSPECTION REPORT NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION Initial Annual RCRA CCR Unit Inspection Report PRIMARY BASIN NUMBER 2 SURFACE IMPOUNDMENT Submitted

More information

State-Aid Bridge News August 2, 2005

State-Aid Bridge News August 2, 2005 State-Aid Bridge News August 2, 2005 Bridge Hydraulic Information The FHWA has been inquiring about our Scour Program. In particular, there are two areas of concern; 1. Are our Scour Action Plans current

More information

a.the Vetiver Network International b.vietnam Vetiver Network

a.the Vetiver Network International b.vietnam Vetiver Network Presented at the Southern African Association of Geomorphology (SAAG) 2017 Conference, 25-28 July 2017, Swaziland APPLICATION OF VETIVER SYSTEM TECHNOLOGY FOR RIVERBANK AND COASTAL DIKE STABILISATION IN

More information

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Filed: 2018-07-04, EB-2018-0108, Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889

More information

Vol. 18,No Sichuan Water Power. MgO ,,610072) MgO. MgO. MgO. MgO. MgO. MgO. MgO, MgO. MgO

Vol. 18,No Sichuan Water Power. MgO ,,610072) MgO. MgO. MgO. MgO. MgO. MgO. MgO, MgO. MgO 18 2 1 9 9 9 6 Sichuan Water Power Vol. 18 No. 2 1 9 9 9 2 0 6 MgO ( 610072) 10 20 MgO MgO 12 MgO MgO MgO MgO 1 MgO 20 MgO MgO MgO MgO MgO MgO 20 12 MgO MgO MgO 20 MgO MgO MgO 10 : 2 MgO 10 2. 1 1987 1989

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7883 CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

NORTH FORK FEATHER RIVER, CA

NORTH FORK FEATHER RIVER, CA Hydropower Project License Summary NORTH FORK FEATHER RIVER, CA ROCK CREEK CRESTA HYDROELECTRIC PROJECT (P-1962) Kayakers below the Cresta Dam Photo: Hydropower Reform Coalition This summary was produced

More information

Don Pedro Project Project Operations/Water Balance Model Attachment B Model Description and User s Guide, Addendum 1 Base Case Description

Don Pedro Project Project Operations/Water Balance Model Attachment B Model Description and User s Guide, Addendum 1 Base Case Description Don Pedro Project Project Operations/Water Balance Model Attachment B Model Description and User s Guide, Addendum 1 Base Case Description 5-2-213 1. INTRODUCTION The Turlock Irrigation District ( TID

More information

Stormwater Mitigation Worksheet

Stormwater Mitigation Worksheet Planning & Development Dept. Infrastructure Division P.O. Box 11706, or 155 Johnston Street Rock Hill, South Carolina 29731 1706 Phone: 803 329 5515 FAX: 803 329 7228 www.cityofrockhill.com Date Received:

More information

2011 BRIDGE INSPECTION REPORT

2011 BRIDGE INSPECTION REPORT 2011 BRIDGE INSPECTION REPORT BYRD PARK PUMP STATION BRIDGE OVER KANAWHA CANAL April 2011 FINAL December 2011 Looking - from Abutment B to Abutment A Prepared by: WHITMAN, REQUARDT, & ASSOCIATES, LLP 9030

More information

The Intertidal Zone. Vocabulary:

The Intertidal Zone. Vocabulary: The Intertidal Zone This lesson contains four activities with discussion questions related to a video. These parts may be used individually or together, depending on the needs and time constraints of your

More information

EAH 422 ADVANCED WATER RESOURCES ENGINEERING

EAH 422 ADVANCED WATER RESOURCES ENGINEERING EAH 422 ADVANCED WATER RESOURCES ENGINEERING Bridge Hydraulics Prof. Aminuddin Ab. Ghani References The Art And Science Of River Engineering Bridge Failure Pier scour Pier scour Pier scour Bridge Failure

More information

Dry Fire Hydrant Designs. GBW Wall-Mounted Deployable DFH Phoenix, Maryland August 2011

Dry Fire Hydrant Designs. GBW Wall-Mounted Deployable DFH Phoenix, Maryland August 2011 Dry Fire Hydrant Designs GBW Wall-Mounted Deployable DFH Phoenix, Maryland August 2011 The Problem A fixed-mount, dry fire hydrant located on a large stream that is part of the Gunpowder River Watershed

More information

ADMINISTRATIVE DIRECTIVE

ADMINISTRATIVE DIRECTIVE ADMINISTRATIVE DIRECTIVE Title: Emergency Eyewash and Shower Stations Issuing Department: Town Manager s Safety Office Effective Date: June 1, 2014 Approved: Gilbert Davidson, Town Manager Type of Action:

More information

A how to guide. NWHA 2010 February 16,

A how to guide. NWHA 2010 February 16, A how to guide. NWHA 2010 February 16, 2010 1 Public Safety begins with keeping messaging simple. NWHA 2010 February 16, 2010 2 What is a Public Safety Plan? A brief document that exhibits all safety devices:

More information

STATUS REPORT - PINNIPED PREDATION AND DETERRENT ACTIVITIES AT BONNEVILLE DAM, 2009

STATUS REPORT - PINNIPED PREDATION AND DETERRENT ACTIVITIES AT BONNEVILLE DAM, 2009 STATUS REPORT - PINNIPED PREDATION AND DETERRENT ACTIVITIES AT BONNEVILLE DAM, 29 Robert Stansell, Sean Tackley, and Karrie Gibbons - (541) 374-881 Fisheries Field Unit U.S. Army Corps of Engineers Bonneville

More information

Understanding Atrial Fibrillation

Understanding Atrial Fibrillation Understanding Atrial Fibrillation Todd J. Florin, M.D. Table of Contents The Normal Heart...1 What is Atrial Fibrillation...3 Risks of Afib: Stroke...5 Treatment Options...7 Radiofrequency Ablation...9

More information

Francis E. Walter Reservoir Recreation Operations Plan for 2019

Francis E. Walter Reservoir Recreation Operations Plan for 2019 Revised: 24 October 2018 Francis E. Walter Reservoir Recreation Operations Plan for 2019 Note: This plan will remain the same for the next two years with the exception of dates, please reference Table

More information

EXPERIENCES IN THE STABILIZATION OF A LARGE GULLY AT SPRINGS AREA PROPERTY FROM AGUA MINALBA VENEZUELA.

EXPERIENCES IN THE STABILIZATION OF A LARGE GULLY AT SPRINGS AREA PROPERTY FROM AGUA MINALBA VENEZUELA. EXPERIENCES IN THE STABILIZATION OF A LARGE GULLY AT SPRINGS AREA PROPERTY FROM AGUA MINALBA VENEZUELA. R. Luque M. Vetiver Antierosión, C. A: Av. Circunvalación Nº 129 Piñonal Maracay ZP: 2103 Venezuela

More information

Salinas Valley Water Project Annual Flow Monitoring Report

Salinas Valley Water Project Annual Flow Monitoring Report Salinas Valley Water Project Annual Flow Monitoring Report Operational Season 2013 Monterey County Water Resources Agency 893 Blanco Circle Salinas, CA 93901 April 2014 Revised July 2014 TABLE OF CONTENTS

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT STATE BRIDGE NO. 6081 CITY OR COUNTY 053 LOUDOUN TYPE OF BRIDGE REPORT: REGULAR INSPECTION JANUARY 2016 BRIDGE NAME: DIRECTION: FOREST MILLS

More information

BIOLOGY - CLUTCH CH.37 - SOIL.

BIOLOGY - CLUTCH CH.37 - SOIL. !! www.clutchprep.com Plants produce sugars from photosynthesis, but still have many nutritional requirements C, H, and O account for ~95% of a plant s dry weight, and are obtained from CO2 and H2O Vascular

More information

Table 3-1 Summary of Storm Drain Outfalls

Table 3-1 Summary of Storm Drain Outfalls Table 3-1 Summary of Storm Drain Outfalls Outfall Number Description 005 The drainage area associated with Outfall 005 is to the west of the plant adjacent to and north of Warehouse 2/3, and includes a

More information

Real World Variables University Wind Studies Part 1. Randy Montgomery

Real World Variables University Wind Studies Part 1. Randy Montgomery Real World Variables University Wind Studies Part 1 Randy Montgomery Research Purpose Current and proposed legislation is looking at all kinds of irrigation efficiency numbers EPA WaterSense Single Family

More information

anchor point. Essentially, the more the body is parallel to the floor, the more difficult the exercise. The third set of pictures shows two common

anchor point. Essentially, the more the body is parallel to the floor, the more difficult the exercise. The third set of pictures shows two common ST BOWLER SQUAT The bowler squat performed with a suspension trainer is a great little single leg squat/hinge combo! The suspension trainer assists with balance and I believe makes the exercise more effective.

More information

15 Mile Sewer Interceptor. Overview. (All data current as of March 21)

15 Mile Sewer Interceptor. Overview. (All data current as of March 21) 15 Mile Sewer Interceptor (All data current as of March 21) On Dec. 24, 2016, the Macomb Interceptor Drain Drainage District sewer interceptor collapsed along 15 Mile Road, at Eberlein Drive in Fraser,

More information

THERMAL ENERGY STORAGE TANK DOWN UNDER

THERMAL ENERGY STORAGE TANK DOWN UNDER THERMAL ENERGY STORAGE TANK DOWN UNDER OWNER ENGINEER TANK BUILDER Thermal Energy Storage Tank Walnut, CA Los Angeles area Community College serving over 50,000 students Host to the 2020 U.S. Olympic Track

More information

Going with the Flow Update. An update and comparative analysis of five years of Water Sentinels flow data collection of the Upper Verde River

Going with the Flow Update. An update and comparative analysis of five years of Water Sentinels flow data collection of the Upper Verde River Going with the Flow Update An update and comparative analysis of five years of Water Sentinels flow data collection of the Upper Verde River Rachel Shultis Intern for Science-Practice Integration Grand

More information

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 SITE NUMBER AND NAME: NC 52 Pembina River Bridge LEGAL DESCRIPTION: SE 1-50-9-W5M STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 NAD 83 COORDINATES:

More information

Helper Operation. Guide For BC&SJ Helper Ops 6/26/2015. Horace Fithers V1.0

Helper Operation. Guide For BC&SJ Helper Ops 6/26/2015. Horace Fithers V1.0 Guide For BC&SJ Helper Ops 6/26/2015 Horace Fithers V1.0 Contents Helper Service... 2 Determining if a helper is needed... 2 When to determine if a helper is needed... 4 Adding helpers to a train... 4

More information

TP296/298/299/301 Bounce Surround For use with TP Trampolines

TP296/298/299/301 Bounce Surround For use with TP Trampolines TP Bounce Surr Instruction IN8960 02 08 3/2/08 6:47 Page TP296/298/299/30 For use with TP Trampolines INSTRUCTIONS FOR ASSEMBLY MAINTENANCE AND USE Important! These instructions must be followed for safe

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 89188 7 th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER OCTOBER 2, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

TPO Annual Retreat Summary Friday, March 3 rd 9:00 a.m. 11:00 a.m. Daytona International Speedway Bill France Room

TPO Annual Retreat Summary Friday, March 3 rd 9:00 a.m. 11:00 a.m. Daytona International Speedway Bill France Room TPO Annual Retreat Summary Friday, March 3 rd 9:00 a.m. 11:00 a.m. Daytona International Speedway Bill France Room The focus of the annual retreat for 2017 involved Proactive Strategies to Deal with Sea

More information

Dade County, Missouri

Dade County, Missouri Dade County, Missouri Natural Hazard Mitigation Plan FEMA APPROVED FINAL DRAFT June 2014 Dade County, Missouri Natural Hazard Mitigation Plan For Dade County, its Incorporated Communities, School Districts

More information

XP_NOTICE_BT300_OK.qxd 28/11/08 10:59 Page 1 BT 300 BT 300

XP_NOTICE_BT300_OK.qxd 28/11/08 10:59 Page 1 BT 300 BT 300 XP_NOTICE_BT300_OK.qxd 28/11/08 10:59 Page 1 XP_NOTICE_BT300_OK.qxd 28/11/08 10:59 Page 3 B C E A D 4 5 You have chosen a DOMYOS fitness machine and we wish to thank you for the trust you place with us.

More information

Cold In-Place Recycling Forensic Study on U.S. Highway 34 Union County, Iowa

Cold In-Place Recycling Forensic Study on U.S. Highway 34 Union County, Iowa Cold In-Place Recycling Forensic Study on U.S. Highway 34 Union County, Iowa Michael Heitzman Office of Materials Iowa Department of Transportation 800 Lincoln Way Ames, Iowa 50010 Michael.Heitzman@dot.iowa.gov

More information

MINI JUMPER INSTRUCTION MANUAL MSC-3720-H

MINI JUMPER INSTRUCTION MANUAL MSC-3720-H MINI JUMPER INSTRUCTION MANUAL 41734100 MSC-3720-H DO NOT attempt somersaults or flips. Paralysis or death can result if you land on your head or neck! No more than one person on the trampoline at a time.

More information

Getting Results: Measuring Postwildfire. Treatment Effectiveness

Getting Results: Measuring Postwildfire. Treatment Effectiveness Getting Results: Measuring Postwildfire Erosion Control Treatment Effectiveness BAER Burned Area Emergency Response Pete Robichaud, R. Brown, P. Wohlgemuth, J. Wagenbrenner Rocky Mountain and Pacific Southwest

More information

St. Croix River Crossing Bridge Foundation Load Test Project. 1/27/2010 St. Croix River Crossing Bridge - Foundation Load Test Project

St. Croix River Crossing Bridge Foundation Load Test Project. 1/27/2010 St. Croix River Crossing Bridge - Foundation Load Test Project St. Croix River Crossing Bridge Foundation Load Test Project Load Test Sites 4 driven piles Drilled Shaft Site A Site B Load Test Purpose To gather design data for foundation design Allows for more refined

More information

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Jeff Sizemore, P.E. Geotechnical Design Support Engineer SCDOT Ed Tavera, P.E. Principal Geotechnical Engineer Geoengineers

More information