1 Public Disclosure Authorized Public Disclosure Authorized losure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Benin Second Multisectoral HIV/AIDS Control Project (P096056) Operation Name: Second Multisectoral HIV/AIDS Control Project (P096056) Project Stage: Implementation Seq.No: 9 Status: ARCHIVED Last Modified : 06-Apr-2011 Country: Benin Approval FY: 2007 Product Line: IBRD/IDA Region: AFRICA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Projet Multisectoriel de Lutte contre le VIH/SIDA Key s Board Approval 05-Apr-2007 Original Closing Planned Mid Term Review 18-Jan-2010 Last Archived ISR 03-Nov-2010 Effectiveness 09-Jan-2008 Revised Closing Actual Mid Term Review 18-Jan-2010 Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objectives of the proposed project are derived from the country's strategic plan for fighting HIV/AIDS and its effects, and for preventing the further spread of HIV/AIDS by means of a multisectoral program approach. They are essentially similar to those under the predecessor project. Thus, complementing the activities financed by other sources, the purpose is to help Benin Government implement its new National Strategic Framework for boosting its national response to HIV/AIDS by contributing to increase and improve the coverage and utilization of prevention services, treatment and care for specific high-risk and vulnerable groups. More specifically, the project will contribute to: (a) strengthening access to and increasing utilization of prevention services for vulnerable groups (women, youth, etc.) and the high-risk groups such as the commercial sex workers and staffs of some key ministries; (b) improve access and utilization of treatment and care services for HIV/AIDS infected and affected persons, notably those living with HIV/AIDS (PLWHA), and orphans and vulnerable children (OVC); and (c) consolidate the coordination, management, and the monitoring and evaluation of the national response to HIV/AIDS for its sustainability. Has the Project Development Objective been changed since Board Approval of the Project? Yes Component(s) No Component Name Component Cost A. Social Mobilization and Prevention Services B. Access to Treatment, Care services C. Coordination, Management, and Monitoring and Evaluation 7.70 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Page 1 of 9

2 Implementation Status Overview The project has been restructured as requested by the government: the credit's proceeds have been reallocated; baseline and end-of-project targets values have been adjusted to take into account new available data and achievements as of the January 2010 mid-term review. The project is making good progress towards the achievement of its development objective in spite of the recurrent strikes of the health sector staff throughout the country to claim for better working conditions and financial reward. The setting up of the national HIV/AIDS monitoring and evaluation system is completed and now has to be made fully operationalas of February 11, 2011, the physical execution rate of the Project stands at nearly 80%, while 66% of the IDA Credit has been disbursed.. Results Project Development Objective Indicators Health personnel receiving training Dec-2009 Core Indicator Number *Project level result. Persons trained in HIV service delivery. Source :Ministry of Health and NAC Annual Reports 2009 *Project level result. Persons trained in HIV service delivery. Source: Ministry of Health and NAC Annual Reports Source: Ministry of Health and NAC Annual Reports Source: Ministry of Health and NAC Annual Reports Pregnant women living with HIV who received antiretrovirals to reduce the risk of MTCT Core Indicator Number Report Page 2 of 9

3 Persons aged 15 and older who received counseling and testing for HIV and received their test result Report *Project level result Cumulative number as of end December End-of-project target of far exceeded. Source: Health SectorAnnual Sex workers who report using a condom with their most recent client Custom Indicator Percentage measured by the Second Generation STI/AIDS Surveillance Survey which is undertaken biannually. This figure comes from the most recent survey, undertaken in This data was released in July Data for 2010 will be released in October Report Page 3 of 9

4 Young women and men aged who both correctly identify ways of preventing the sexual transmission of HIV and who reject misconce ption about HIV transmission in the last 12 months Custom Indicator Percentage measured by the Second Generation STI/AIDS Surveillance Survey which is undertaken biannually. This figure comes from the most recent survey, undertaken in This data was released in July AIDS Surveillance Survey *Program level result Data for 2010 will be available in October Percentage and number of people with advanced HIV infection reveiving antretroviral combination therapy Intermediate Results Indicators cannot be estimated Source:Health Sector Annual Country Report Page 4 of 9

5 Orphaned and vulnerable children aged 0-17 whose households received free basic external support in caring for the child 09-Jan Source: Grantee routine monitoring records and report Adults and children with HIV receiving antiretroviral combination therapy Core Indicator Number cannot be estimated cannot be estimated. These are the latest figures currently available. Source: Health Sector Report and UNGASS Country Source: Grantee routine monitoring records and report Report Page 5 of 9

6 Adults Sub- Core Indicator Number Breakdown cannot be estimated cannot be estimated. These are the latest figures currently available Children Sub- Core Indicator Number Breakdown 77 cannot be estimated. Source: Health Sector report Source: Health Sector Report and UNGASS Country cannot be estimated. These are the latest figures currently available. Source: Health Sector Report and UNGASS Country 200 Source: Health Sector Report and UNGASS Country Report Page 6 of 9

7 Condoms distributed 06-Nov End-of-project target exceeded by end December Source: Condoms distribution Reports by PSI and Grantees PLWHA receiving psychological support 06-Nov Source: Grantee routine monitoring records and reports Source: Condoms distribution Reports by PSI and Grantees Persons reached with community outreach and support and IBCC/BCC programs Source: Periodic reports from subbeneficiaries Source: Grantee routine monitoring records and reports Source: Periodic reports from subbeneficiaries Page 7 of 9

8 Subprojects financed targeting vulnerable populations, high-risk groups and geographic hot spots 06-Nov Source: Financial and program reports Implementing agencies submitting timely quarterly monitoring and financial reports to SP/CNLS in the last 12 months Custom Indicator Percentage Oct-2009 Source: Periodic reports from Grantees Source: Financial and program report Annual joint review and workplan exercises conducted 06-Nov Source: Joint Review Report and and NAC Annual Source: Periodic reports from Grantees HIV-infected pregnant women receiving a complete course of antiretrovirals to reduce the risk of MTCT Custom Indicator Percentage Source: Joint Review Report and and NAC Annual Report Source Health Sector Annual Report Page 8 of 9

9 Data on Financial Performance (as of 17-Feb-2011) Financial Agreement(s) Key s Project Loan No. Status Approval Signing Effectiveness Closing P IDA Effective 05-Apr May Jan-2008 Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P IDA Effective XDR Disbursement Graph Key Decisions Regarding Implementation Project implementation is progressing satisfactorily. The government plans to submit a request for reallocation of the IDA credit's proceeds and an extension of the closing date to complete critical activities in the field of care and treatment for HIV/AIDS affected persons. Restructuring History Level two Approved on 21-Dec-2010 Related Projects There are no related projects. Page 9 of 9

Implementation Status & Results Mali Mali - Multi-sectoral HIV/AIDS Project (P082957)

Implementation Status & Results Mali Mali - Multi-sectoral HIV/AIDS Project (P082957) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Mali Mali - Multi-sectoral HIV/AIDS Project (P082957) Operation Name: Mali - Multi-sectoral HIV/AIDS

More information

Implementation Status & Results Burkina Faso Health Sector Support & Multisectoral AIDS Project (P093987)

Implementation Status & Results Burkina Faso Health Sector Support & Multisectoral AIDS Project (P093987) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Burkina Faso Health Sector Support & Multisectoral AIDS Project (P093987) Operation Name: Health

More information

Implementation Status & Results India India: Third National HIV/AIDS Control Project (P078538)

Implementation Status & Results India India: Third National HIV/AIDS Control Project (P078538) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results India India: Third National HIV/AIDS Control Project (P078538) Operation Name: India: Third National

More information

Implementation Status & Results Guinea Health Sector Support Project (P065126)

Implementation Status & Results Guinea Health Sector Support Project (P065126) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Guinea Health Sector Support Project (P065126) Operation

More information

Implementation Status & Results Burkina Faso Reproductive Health Project in Burkina Faso (P119917)

Implementation Status & Results Burkina Faso Reproductive Health Project in Burkina Faso (P119917) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Burkina Faso Reproductive Health Project in Burkina

More information

Implementation Status & Results Brazil AIDS-SUS (National AIDS Program - National Health Service) (P113540)

Implementation Status & Results Brazil AIDS-SUS (National AIDS Program - National Health Service) (P113540) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil AIDS-SUS (National AIDS Program - National Health Service) (P113540) Operation Name: AIDS-SUS

More information

Implementation Status & Results Vietnam HIV/AIDS Prevention (P082604)

Implementation Status & Results Vietnam HIV/AIDS Prevention (P082604) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Vietnam HIV/AIDS Prevention (P082604) Operation Name: HIV/AIDS Prevention (P082604) Project Stage: Implementation

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Nigeria Health, Nutrition & Population Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 7 ARCHIVED on 22-Dec-2015 ISR21893 Implementing Agencies: Public

More information

Implementation Status & Results Nepal Avian Influenza Control Project (P100342)

Implementation Status & Results Nepal Avian Influenza Control Project (P100342) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Nepal Avian Influenza Control Project (P100342) Operation Name: Avian Influenza Control Project

More information

Satisfactory Satisfactory Moderate

Satisfactory Satisfactory Moderate Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia ID-TF NATIONAL PROGRAM FOR COMMUNITY EMPOWERMENT IN RURAL AREAS HEALTHY AND BRIGHT GENERATION

More information

The World Bank Ghana - Maternal, Child Health and Nutrition Project (P145792)

The World Bank Ghana - Maternal, Child Health and Nutrition Project (P145792) Public Disclosure Authorized AFRICA Ghana Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 7 ARCHIVED on 25-Sep-2017 ISR29449 Implementing Agencies:

More information

Implementation Status & Results Indonesia ID-TF ADDITIONAL FINANCING OF PNPM RURAL III FOR GENERASI (COMM.CCT) SCALING-UP PROGRAM (P122032)

Implementation Status & Results Indonesia ID-TF ADDITIONAL FINANCING OF PNPM RURAL III FOR GENERASI (COMM.CCT) SCALING-UP PROGRAM (P122032) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia ID-TF ADDITIONAL FINANCING OF PNPM RURAL III FOR GENERASI (COMM.CCT) SCALING-UP PROGRAM

More information

Implementation Status & Results Afghanistan National Solidarity Program III (P117103)

Implementation Status & Results Afghanistan National Solidarity Program III (P117103) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Afghanistan National Solidarity Program III (P117103)

More information

The World Bank AIDS-SUS (National AIDS Program - National Health Service) (P113540)

The World Bank AIDS-SUS (National AIDS Program - National Health Service) (P113540) LATIN AMERICA AND CARIBBEAN Brazil Health, Nutrition & Population Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 11 ARCHIVED on 24-Dec-2015 ISR21939 Implementing Agencies: Departamento

More information

Document of. The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-42900) ON A CREDIT IN THE AMOUNT OF SDR 23.5 MILLION

Document of. The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-42900) ON A CREDIT IN THE AMOUNT OF SDR 23.5 MILLION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR2189 IMPLEMENTATION COMPLETION AND RESULTS REPORT

More information

HIV/AIDS INDICATORS. AIDS Indicator Survey 8 Basic Documentation Introduction to the AIS

HIV/AIDS INDICATORS. AIDS Indicator Survey 8 Basic Documentation Introduction to the AIS HIV/AIDS INDICATORS During the last decade there has been an increased effort to track the progress in the area of HIV/AIDS. A of international agencies and organizations have developed indicators designed

More information

Challenges and Opportunities for Responding to HIV/AIDS in LDCs. Mazuwa Banda Department of HIV/AIDS World Health Organization

Challenges and Opportunities for Responding to HIV/AIDS in LDCs. Mazuwa Banda Department of HIV/AIDS World Health Organization Challenges and Opportunities for Responding to HIV/AIDS in LDCs Mazuwa Banda Department of HIV/AIDS World Health Organization Outline of Presentation Global HIV/AIDS epidemic HIV/AIDS and LDCs Challenges

More information

IBRDDDA DATA SHEET TEMPLATE FOR PROJECT PAPER

IBRDDDA DATA SHEET TEMPLATE FOR PROJECT PAPER Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date: October 13, 2009 Country: Trinidad and Tobago Project Name: HIV/AIDS Prevention

More information

IMPACT AND OUTCOME INDICATORS IN THE NATIONAL HIV MONITORING AND EVALUATION FRAMEWORK

IMPACT AND OUTCOME INDICATORS IN THE NATIONAL HIV MONITORING AND EVALUATION FRAMEWORK IMPACT AND OUTCOME S IN THE NATIONAL HIV MONITORING AND EVALUATION FRAMEWORK 2008-2012 1. HIV Prevention IMPACT S 1. Percentage of young women and men aged 15 24 who are HIV infected (UNGASS (22), MKUKUTA)

More information

UNGASS Declaration of Commitment on HIV/AIDS: Core Indicators revision

UNGASS Declaration of Commitment on HIV/AIDS: Core Indicators revision UNGASS Declaration of Commitment on HIV/AIDS: Core Indicators revision Updated version following MERG recommendations Context In light of country reports, regional workshops and comments received by a

More information

Health (60%);Other social services (20%);Central government administration (20%) Project ID

Health (60%);Other social services (20%);Central government administration (20%) Project ID Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB3401 Additional Financing for the Chad Second Population and HIV/AIDS Project Region AFRICA Sector Health (60%);Other social

More information

NATIONAL REPORT ON UNGASS

NATIONAL REPORT ON UNGASS CONSEIL NATIONAL DE LUTTE CONTRE LE SIDA (NATIONAL COUNCIL FOR THE FIGHT AGAINST AIDS) -=-=-=-=-=-=-=-=- PERMANENT EXECUTIVE SECRETARIAT -=-=-=-=- REPUBLIC OF CONGO Unité*Travail*Progrès (Unity*Work*Progress)

More information

Integrated Safeguards Data Sheet (Initial)

Integrated Safeguards Data Sheet (Initial) THE WORLD BANK GROUP InfoShop Date Prepared/Updated: 10/25/2002 Section I - Basic Information Integrated Safeguards Data Sheet (Initial) 25025 A. Basic Project Data Country: MOLDOVA Project ID: P074122

More information

Annex A: Impact, Outcome and Coverage Indicators (including Glossary of Terms)

Annex A: Impact, Outcome and Coverage Indicators (including Glossary of Terms) IMPACT INDICATORS (INDICATORS PER GOAL) HIV/AIDS TUBERCULOSIS MALARIA Reduced HIV prevalence among sexually active population Reduced HIV prevalence in specific groups (sex workers, clients of sex workers,

More information

GHANA Assessment of the Epidemiological Situation and Demographics

GHANA Assessment of the Epidemiological Situation and Demographics Estimated percentage of adults living with HIV/AIDS, end of 2002 These estimates include all people with HIV infection, whether or not they have developed symptoms of AIDS, alive at the end of 2002: 3.4

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H0800) ON A ADAPTABLE PROGRAM LOAN IN THE AMOUNT OF US$102 MILLION TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H0800) ON A ADAPTABLE PROGRAM LOAN IN THE AMOUNT OF US$102 MILLION TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Human Development AFCC2 Africa Region Document of The World Bank IMPLEMENTATION COMPLETION

More information

HIV/AIDS in China. -A A Potential epidemic? Kong-Lai Zhang, MD Professor, Department of Epidemiology, Peking Union Medical College Beijing, CHINA

HIV/AIDS in China. -A A Potential epidemic? Kong-Lai Zhang, MD Professor, Department of Epidemiology, Peking Union Medical College Beijing, CHINA HIV/AIDS in China -A A Potential epidemic? Kong-Lai Zhang, MD Professor, Department of Epidemiology, Peking Union Medical College Beijing, CHINA September 12, 2008 1 HIV epidemic in Asia General Population

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Sector Project ID Borrower(s) Implementing Agency PROJECT INFORMATION

More information

GOVERNMENT OF SIERRA LEONE NATIONAL HIV/AIDS POLICY

GOVERNMENT OF SIERRA LEONE NATIONAL HIV/AIDS POLICY National HIV/AIDS Policy GOVERNMENT OF SIERRA LEONE NATIONAL HIV/AIDS POLICY NATIONAL HIV/AIDS POLICY FOR SIERRA LEONE 1. ACRONYMS CBOs - Community Based Organisations CAC/DAC/RAC - Chiefdom AIDS Committee/District

More information

World Health Organization. A Sustainable Health Sector

World Health Organization. A Sustainable Health Sector World Health Organization A Sustainable Health Sector Response to HIV Global Health Sector Strategy for HIV/AIDS 2011-2015 (DRAFT OUTLINE FOR CONSULTATION) Version 2.1 15 July 2010 15 July 2010 1 GLOBAL

More information

Ex Post-Evaluation Brief BURUNDI: Health Sectoral Programme II

Ex Post-Evaluation Brief BURUNDI: Health Sectoral Programme II Ex Post-Evaluation Brief BURUNDI: Health Sectoral Programme II Sector 12230 Basic health infrastructure Health sector programme, Phase II - Programme/Client BMZ No. 1995 65 748* incl. accompanying measure,

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT

More information

Performance Management Plan Indicator Worksheet #1

Performance Management Plan Indicator Worksheet #1 Performance Management Plan Indicator Worksheet #1 Adapted from Investing in People: Indicators and Definitions (USAID) 1. Name and number of Strategic Objective: Reduced mother-to-child transmission of

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Jun ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Jun ,000,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020903 Public Disclosure Authorized Public Disclosure Authorized Project ID P116167 Country Niger Project

More information

Steady Ready Go! teady Ready Go. Every day, young people aged years become infected with. Preventing HIV/AIDS in young people

Steady Ready Go! teady Ready Go. Every day, young people aged years become infected with. Preventing HIV/AIDS in young people teady Ready Go y Ready Preventing HIV/AIDS in young people Go Steady Ready Go! Evidence from developing countries on what works A summary of the WHO Technical Report Series No 938 Every day, 5 000 young

More information

The President s Emergency Plan for AIDS Relief: Indicators, Reporting Requirements, and Guidelines for Focus Countries. Revised for FY2006 Reporting

The President s Emergency Plan for AIDS Relief: Indicators, Reporting Requirements, and Guidelines for Focus Countries. Revised for FY2006 Reporting The President s Emergency Plan for AIDS Relief: Indicators, Reporting Requirements, and Guidelines for Focus Countries Revised for FY2006 Reporting July 29, 2005 Contents INTRODUCTION...3 Emergency Plan

More information

Linkages between Sexual and Reproductive Health and HIV

Linkages between Sexual and Reproductive Health and HIV Linkages between Sexual and Reproductive Health and HIV Manjula Lusti-Narasimhan Department of Reproductive Health and Research World Health Organization The HIV pandemic 25 years 1981 2006 Rationale for

More information

MICROFINANCE PLUS HEALTH PROGRAMMES SUPPORTING THE FIGHT AGAINST HIV/AIDS

MICROFINANCE PLUS HEALTH PROGRAMMES SUPPORTING THE FIGHT AGAINST HIV/AIDS MICROFINANCE PLUS HEALTH PROGRAMMES SUPPORTING THE FIGHT AGAINST HIV/AIDS 1 I. Context: Poverty and HIV/Aids HIV/AIDS represents a real shock which affects the different forms social, physical and financial

More information

TUBERCULOSIS AND HIV/AIDS: A STRATEGY FOR THE CONTROL OF A DUAL EPIDEMIC IN THE WHO AFRICAN REGION. Report of the Regional Director.

TUBERCULOSIS AND HIV/AIDS: A STRATEGY FOR THE CONTROL OF A DUAL EPIDEMIC IN THE WHO AFRICAN REGION. Report of the Regional Director. 30 August 2007 REGIONAL COMMITTEE FOR AFRICA ORIGINAL: ENGLISH Fifty-seventh session Brazzaville, Republic of Congo, 27 31 August Provisional agenda item 7.8 TUBERCULOSIS AND HIV/AIDS: A STRATEGY FOR THE

More information

MYANMAR SEX WORK & HIV MYANMAR SEX WORK & HIV

MYANMAR SEX WORK & HIV MYANMAR SEX WORK & HIV e SEX WORK & HIV SEX WORK & HIV Myanmar, formerly known as Burma, has a population of 50 million people [1]. The estimated nation wide population of sex workers in 2007 was between 40,000 and 80,000 and

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF-14306,TF-57980,TF Dec ,777,110.69

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF-14306,TF-57980,TF Dec ,777,110.69 Public Disclosure Authorized 1. Project Data Report Number : ICRR0020213 Public Disclosure Authorized Project ID P104523 Project Name Horn of Africa HIV/AIDS ACGF Country Practice Area(Lead) Additional

More information

UNGASS Indicators and possible adoption of NDPHS indicators. Tallinn /P.Leinikki

UNGASS Indicators and possible adoption of NDPHS indicators. Tallinn /P.Leinikki UNGASS Indicators and possible adoption of NDPHS indicators National Indicators 1. Committment and Action: 1. Domestic and international AIDS spending by categories and financing sources 2. National Composite

More information

Mid-term Review of the UNGASS Declaration of. Commitment on HIV/AIDS. Ireland 2006

Mid-term Review of the UNGASS Declaration of. Commitment on HIV/AIDS. Ireland 2006 Mid-term Review of the UNGASS Declaration of Commitment on HIV/AIDS Ireland 2006 Irish Role in Global Response Just as the HIV/AIDS epidemic is a global threat, addressing the challenge of the epidemic

More information

Effects of the Global Fund on the health system

Effects of the Global Fund on the health system Ukraine: Effects of the Global Fund on the health system Tetyana Semigina 27 Abstract Ukraine has one of the most rapidly growing HIV/AIDS epidemics in Europe, with estimated numbers of people living with

More information

Report No. PID11503 ST. KITTS AND NEVIS-KN: HIV/AIDS... PREVENTION AND CONTROL PROJECT. Latin America and Caribbean Region. Sector Health (100%)

Report No. PID11503 ST. KITTS AND NEVIS-KN: HIV/AIDS... PREVENTION AND CONTROL PROJECT. Latin America and Caribbean Region. Sector Health (100%) Report No. PID11503 Project Name ST. KITTS AND NEVIS-KN: HIV/AIDS... PREVENTION AND CONTROL PROJECT Region Latin America and Caribbean Region Sector Health (100%) Project ID P076798 Borrower(s) ST. KITTS

More information

Peace Corps Global HIV/AIDS Strategy (FY )

Peace Corps Global HIV/AIDS Strategy (FY ) The Peace corps :: global hiv/aids str ategy :: fisc al years 2009 2014 1 of 5 Peace Corps Global HIV/AIDS Strategy (FY 2009 2014) 2007 facts BacKGroUnd 33 million people are living with hiv. More than

More information

United Nations Development Programme (UNDP) Sudan. Grant Closure Plan HIV Round 5 Global Fund Grant Grant Number: SUD-506-G08-H. Sudan.

United Nations Development Programme (UNDP) Sudan. Grant Closure Plan HIV Round 5 Global Fund Grant Grant Number: SUD-506-G08-H. Sudan. United Nations Development Programme (UNDP) Sudan Grant Closure Plan HIV Round 5 Global Fund Grant Grant Number: SUD-506-G08-H Sudan June 2012 Grant Closure Plan, Global Fund Round 5 HIV/AIDS Grant, UNDP

More information

Children and AIDS Fourth Stocktaking Report 2009

Children and AIDS Fourth Stocktaking Report 2009 Children and AIDS Fourth Stocktaking Report 2009 The The Fourth Fourth Stocktaking Stocktaking Report, Report, produced produced by by UNICEF, UNICEF, in in partnership partnership with with UNAIDS, UNAIDS,

More information

Okinawa, Toyako, and Beyond: Progress on Health and Development

Okinawa, Toyako, and Beyond: Progress on Health and Development Okinawa, Toyako, and Beyond: Progress on Health and Development Prof. Michel D. Kazatchkine Executive Director The Global Fund to Fight AIDS, Tuberculosis and Malaria United Nations University, Tokyo,

More information

Global Fund Round 9 Grant HIV and HSS UNDP-Belize. 14 June, 2011

Global Fund Round 9 Grant HIV and HSS UNDP-Belize. 14 June, 2011 1 Global Fund Round 9 Grant HIV and HSS UNDP-Belize 14 June, 2011 Accelerating the Pace: Reaching Marginalized and Vulnerable Populations with Critical Services 2 Factsheet: Project approved in Round 9

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Sector Project ID Borrower(s) Implementing Agency Environment Category

More information

ESTIMATING THE RESOURCE REQUIREMENTS FOR THE CAMBODIA NATIONAL STRATEGIC PLAN FOR A COMPREHENSIVE AND MULTISECTORAL RESPONSE TO HIV/AIDS

ESTIMATING THE RESOURCE REQUIREMENTS FOR THE CAMBODIA NATIONAL STRATEGIC PLAN FOR A COMPREHENSIVE AND MULTISECTORAL RESPONSE TO HIV/AIDS ESTIMATING THE RESOURCE REQUIREMENTS FOR THE CAMBODIA NATIONAL STRATEGIC PLAN FOR A COMPREHENSIVE AND MULTISECTORAL RESPONSE TO HIV/AIDS 2006-2010 April 2006 TECHNICAL REPORT ESTIMATING RESOURCE REQUIREMENTS

More information

DOWNLOAD PDF MONITORING AND EVALUATION OF THE CIVIL SOCIETY CONTRIBUTION TO TACKLING HIV/AIDS IN NAMIBIA, 2006

DOWNLOAD PDF MONITORING AND EVALUATION OF THE CIVIL SOCIETY CONTRIBUTION TO TACKLING HIV/AIDS IN NAMIBIA, 2006 Chapter 1 : Joint United Nations Programme on HIV/AIDS - Wikipedia Title(s): Monitoring and evaluation of the civil society contribution to tackling HIV/AIDS in Namibia, current levels of activity among

More information

Monitoring and Evaluation

Monitoring and Evaluation Monitoring and Evaluation Toolkit HIV, Tuberculosis and Malaria and Health Systems Strengthening Part 2: Tools for monitoring programs for HIV, tuberculosis, malaria and health systems strengthening HIV

More information

Executive Board of the United Nations Development Programme, the United Nations Population Fund and the United Nations Office for Project Services

Executive Board of the United Nations Development Programme, the United Nations Population Fund and the United Nations Office for Project Services United Nations DP/FPA/CPD/BRA/5 Executive Board of the United Nations Development Programme, the United Nations Population Fund the United Nations Office for Project Services Distr.: General 26 September

More information

SCALING UP TOWARDS UNIVERSAL ACCESS

SCALING UP TOWARDS UNIVERSAL ACCESS SCALING UP TOWARDS UNIVERSAL ACCESS Considerations for countries to set their own national targets for HIV prevention, treatment, and care April 2006 Acknowledgements: The UNAIDS Secretariat would like

More information

Technical Guidance for Global Fund HIV Proposals

Technical Guidance for Global Fund HIV Proposals Technical Guidance for Global Fund HIV Proposals FINAL DRAFT DOCUMENT The document will remain in a final draft form for Round 9 and will be finalized for the Round 10 Resource Toolkit. If you would like

More information

Botswana Advocacy paper on Resource Mobilisation for HIV and AIDS

Botswana Advocacy paper on Resource Mobilisation for HIV and AIDS Republic of Botswana Botswana Advocacy paper on Resource Mobilisation for HIV and AIDS Page 1 June 2012 1.0 Background HIV and AIDS remains one of the critical human development challenges in Botswana.

More information

To provide you with the basic concepts of HIV prevention using HIV rapid tests combined with counselling.

To provide you with the basic concepts of HIV prevention using HIV rapid tests combined with counselling. Module 2 Integration of HIV Rapid Testing in HIV Prevention and Treatment Programs Purpose Pre-requisite Modules Learning Objectives To provide you with the basic concepts of HIV prevention using HIV rapid

More information

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL CREDIT

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Human Development 1 Eastern Africa 2 Africa Region Document of The World Bank FOR OFFICIAL

More information

Cote d Ivoire Country Report FY15

Cote d Ivoire Country Report FY15 USAID ASSIST Project Cote d Ivoire Country Report FY15 Cooperative Agreement Number: AID-OAA-A-12-00101 Performance Period: October 1, 2014 September 30, 2015 DECEMBER 2015 This annual country report was

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-36291) ON A CREDIT IN THE AMOUNT OF SDR 10.7 MILLION (US$ 14.0 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-36291) ON A CREDIT IN THE AMOUNT OF SDR 10.7 MILLION (US$ 14.0 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-36290 IDA-36291)

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H0660) ON A GRANT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H0660) ON A GRANT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H0660) ON

More information

ART for prevention the task ahead

ART for prevention the task ahead ART for prevention the task ahead Dr Teguest Guerma WHO/HQS WHO's role and vision Status of the epidemic Overview Progress and challenges in treatment and prevention scale up ART for prevention Questions

More information

FINANCING FRAMEWORK: RESOURCE REQUIREMENT for the KENYA NATIONAL AIDS STRATEGIC PLAN (KNASP)

FINANCING FRAMEWORK: RESOURCE REQUIREMENT for the KENYA NATIONAL AIDS STRATEGIC PLAN (KNASP) H A R A M B E E Republic of Kenya FINANCING FRAMEWORK: RESOURCE REQUIREMENT for the KENYA NATIONAL AIDS STRATEGIC PLAN (KNASP) 2005-2010 POLICY Preparation and printing of this document was made possible

More information

HIV in Zambia MINISTRY OF HEALTH. Dr Albert Mwango, BScHB, MBChB, MPH National Antiretroviral Program Coordinator,

HIV in Zambia MINISTRY OF HEALTH. Dr Albert Mwango, BScHB, MBChB, MPH National Antiretroviral Program Coordinator, HIV in Zambia Dr Albert Mwango, BScHB, MBChB, MPH National Antiretroviral Program Coordinator, MINISTRY OF HEALTH 8th INTEREST WORKSHOP Intercontinental Hotel, Lusaka May 5 th -9 th, 2013 Background Clinical

More information

Sexual and Reproductive Health and HIV. Dr. Rita Kabra Training course in Sexual and Reproductive Health Research Geneva 2012

Sexual and Reproductive Health and HIV. Dr. Rita Kabra Training course in Sexual and Reproductive Health Research Geneva 2012 Sexual and Reproductive Health and HIV Dr. Rita Kabra Training course in Sexual and Reproductive Health Research Geneva 2012 Global estimates of HIV-(2009) People living with HIV 33.3 million [31.4 35.3

More information

Project Name Barbados-HIV/AIDS Prevention and Control Project ID

Project Name Barbados-HIV/AIDS Prevention and Control Project ID Report No. PID10562 Project Name Barbados-HIV/AIDS Prevention and Control (@)... Project Region Sector Project ID Latin America and the Caribbean (LCR) Other Population; Health & Nutrition BBPE75220 Borrower

More information

Executive Board of the United Nations Development Programme, the United Nations Population Fund and the United Nations Office for Project Services

Executive Board of the United Nations Development Programme, the United Nations Population Fund and the United Nations Office for Project Services United Nations Executive Board of the United Nations Development Programme, the United Nations Population Fund and the United Nations Office for Project Services Distr.: General 12 July 2011 Original:

More information

STRATEGIC PLAN AGAINST VIRAL HEPATITIS IN SENEGAL ( ) POLICY BRIEF

STRATEGIC PLAN AGAINST VIRAL HEPATITIS IN SENEGAL ( ) POLICY BRIEF PROGRAMME NATIONAL DE LUTTE CONTRE LES HEPATITES STRATEGIC PLAN AGAINST VIRAL HEPATITIS IN SENEGAL (2019-2023) POLICY BRIEF 1 INVESTING IN THE FIGHT AGAINST HEPATITIS B AND C IN SENEGAL NATIONAL STRATEGIC

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE COMMUNITY NUTRITION PROJECT GRANT (TF095274) August 27, 2009 TO THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE COMMUNITY NUTRITION PROJECT GRANT (TF095274) August 27, 2009 TO THE Public isclosure Authorized Public isclosure Authorized Public isclosure Authorized Public isclosure Authorized ocument of The World Bank RESTRUCTURING PAPER ON A PROPOSE PROJECT RESTRUCTURING OF THE COMMUNITY

More information

National HIV/AIDS Monitoring and Evaluation Plan

National HIV/AIDS Monitoring and Evaluation Plan Malawi National AIDS Commission National HIV/AIDS Monitoring and Evaluation Plan SHORTCUT GUIDE Version 2.0 1 July 2003 National AIDS Commission P.O. Box 30622 Capital City, Lilongwe 3, Malawi Tel: (265)

More information

Towards universal access

Towards universal access Key messages Towards universal access Scaling up priority HIV/AIDS interventions in the health sector September 2009 Progress report Towards universal access provides a comprehensive global update on progress

More information

Botswana Private Sector Health Assessment Scope of Work

Botswana Private Sector Health Assessment Scope of Work Example of a Scope of Work (Botswana) Botswana Private Sector Health Assessment Scope of Work I. BACKGROUND The Republic of Botswana is a stable, democratic country in Southern Africa with an estimated

More information

Country_name (MONGOLIA)

Country_name (MONGOLIA) UNGASS Indicators Country Report Country_name (MONGOLIA) STATUS AT A GLANCE...2 OVERVIEW OF THE AIDS EPIDEMIC...4 Impact Indicators...4 NATIONAL RESPONSE TO THE AIDS EPIDEMIC...5 Most-at-risk populations:

More information

M&E for Accountability & Global Progress Tracking

M&E for Accountability & Global Progress Tracking M&E for Accountability & Global Progress Tracking Monitoring, Operations Research and Evaluation Team UNAIDS/Geneva April 2007 ORIENTATION 2008 UNGASS Country Progress Report - Benefits of UNGASS for M&E

More information

The road towards universal access

The road towards universal access The road towards universal access Scaling up access to HIV prevention, treatment, care and support 22 FEB 2006 The United Nations working together on the road towards universal access. In a letter dated

More information

1. Status at a glance

1. Status at a glance Table of Contents List of Acronyms...3 Introduction...4 1. Status at a glance...5 1.1. Report writing process...5 1.2 The status of the epidemic...5 1.3 Policy and programmatic response...8 1.4. UNGASS

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4078 Project Name

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4078 Project Name PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4078 Project Name HIV/AIDS Project Region AFRICA Sector Health (60%); Other social services (23%); General public administration sector (10%);Central

More information

1.0 BACKGROUND. guide the response from

1.0 BACKGROUND. guide the response from National AIDS Commission 1.0 BACKGROUND The Government of Malawi established the National AIDS Commission (NAC), as a public trust in July 2001 to provide overall leadership and coordination of the national

More information

Integrating prevention & management of STI/HIV/AIDS into reproductive, maternal and newborn health services in China

Integrating prevention & management of STI/HIV/AIDS into reproductive, maternal and newborn health services in China Integrating prevention & management of STI/HIV/AIDS into reproductive, maternal and newborn health services in China China presentation Wang Linhong MD, Professor National Center of MCH, China CDC 1 HIV/AIDS

More information

Monitoring the Declaration of Commitment on HIV/AIDS & UNGASS indicators

Monitoring the Declaration of Commitment on HIV/AIDS & UNGASS indicators Monitoring the Declaration of Commitment on HIV/AIDS & UNGASS indicators José Antonio Izazola Chief, AIDS Financing and Economics Division Evidence, Monitoring and Policy Department UNAIDS Assessment 6.3

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA Project Name. Region. Country. Sector(s) Health (100%) Theme(s)

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA Project Name. Region. Country. Sector(s) Health (100%) Theme(s) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA62480 Project Name

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 67,000,

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 67,000, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020346 Public Disclosure Authorized Project ID P113540 Country Brazil Project Name BR AIDS-SUS Practice

More information

Strategic Planning for HIV/AIDS

Strategic Planning for HIV/AIDS ASAP Regional Training on Epidemiological and Economic Tools for HIV/AIDS Strategic Planning S P Strategic Planning for HIV/AIDS Results-based Strategic Planning Stefano Bertozzi STRATEGIC PLAN S P A framework

More information

SOUTH ASIA HIV PROGRAMME ( ) Red Cross and Red Crescent Global Alliance on HIV

SOUTH ASIA HIV PROGRAMME ( ) Red Cross and Red Crescent Global Alliance on HIV SOUTH ASIA HIV PROGRAMME (2008-2010) Red Cross and Red Crescent Global Alliance on HIV HIV and AIDS in South Asia An estimated 2.67 million people are infected with HIV in South Asia and approximately

More information

South Asia Multi Sector briefs on HIV/AIDS

South Asia Multi Sector briefs on HIV/AIDS South Asia Multi Sector briefs on HIV/AIDS Transport and Infrastructure Why HIV and AIDS Matter to the Transport and other Infrastructure Sectors Between 2-3.5 million people in South Asia are living with

More information

ANNEX 4: Sample TOR for a

ANNEX 4: Sample TOR for a ANNEX 4: Sample TOR for a comprehensive situation analysis of the education sector response to HIV and AIDS The following is a sample TOR for an HIV and AIDS-related situation analysis in the education

More information

HIV/AIDS. Why address HIV/AIDS? Can HIV/AIDS be brought under control in developing countries?

HIV/AIDS. Why address HIV/AIDS? Can HIV/AIDS be brought under control in developing countries? HIV/AIDS at a glance Why address HIV/AIDS? The HIV/AIDS epidemic has spread with ferocious speed. Virtually unknown 20 years ago, HIV has infected more than 60 million people worldwide. Each day, approximately

More information

Rapid Assessment of Sexual and Reproductive Health

Rapid Assessment of Sexual and Reproductive Health NIGER Rapid Assessment of Sexual and Reproductive Health and HIV Linkages This summary highlights the experiences, results and actions from the implementation of the Rapid Assessment Tool for Sexual and

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB6815 Project Name. Malawi Nutrition and HIV/AIDS Project Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB6815 Project Name. Malawi Nutrition and HIV/AIDS Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB6815 Project Name Malawi

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-36840) ON A CREDIT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-36840) ON A CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-36840) ON

More information

South Africa Country Report FY14

South Africa Country Report FY14 USAID ASSIST Project South Africa Country Report FY14 Cooperative Agreement Number: AID-OAA-A-12-00101 Performance Period: October 1, 2013 September 30, 2014 DECEMBER 2014 This annual country report was

More information

Republic of Bulgaria. Reporting period: January 2003 December National Committee on Prevention of AIDS and STDs at the Council of Ministers

Republic of Bulgaria. Reporting period: January 2003 December National Committee on Prevention of AIDS and STDs at the Council of Ministers UNGASS Indicators Country Report Republic of Bulgaria National Committee on Prevention of AIDS and STDs at the Council of Ministers Reporting period: January 2003 December 2005 Table of contents Acronyms

More information

UNGASS COUNTRY PROGRESS REPORT Republic of Armenia

UNGASS COUNTRY PROGRESS REPORT Republic of Armenia UNGASS COUNTRY PROGRESS REPORT Republic of Armenia Reporting period: January 2006 December 2007 I. Status at a glance The Armenia UNGASS Country Progress Report was developed under the overall guidance

More information

Finding the missing children: Proven Strategies for Increasing Identification of HIV+ Children. October 2017

Finding the missing children: Proven Strategies for Increasing Identification of HIV+ Children. October 2017 Finding the missing children: Proven Strategies for Increasing Identification of HIV+ Children October 2017 Agenda Background Results to date Lessons learned and reaching the 1 st 90 2 Source: CHAI analysis

More information

Médecins Monde ZiMBABWe

Médecins Monde ZiMBABWe Médecins Monde zimbabwe médecins monde / zimbabwe / w Médecins monde: A medical NGO HEALTHCARE PLUS Médecins Monde is an international humanitarian organisation providing medical care to vulnerable populations

More information

BROAD FRAME-WORK FOR HIV & AIDS and STI STRATEGIC PLAN FOR SOUTH AFRICA,

BROAD FRAME-WORK FOR HIV & AIDS and STI STRATEGIC PLAN FOR SOUTH AFRICA, BROAD FRAME-WORK FOR HIV & AIDS and STI STRATEGIC PLAN FOR SOUTH AFRICA, 2007-2011 NOVEMBER 2006 health Department: Health REPUBLIC OF SOUTH AFRICA The HIV and AIDS and Sexually Transmitted Infections

More information

Caribbean. Trinidad and Tobago. Custom analysis extract of: UNGASS - National Composite Policy Index (NCPI) COUNTRY: Trinidad and Tobago

Caribbean. Trinidad and Tobago. Custom analysis extract of: UNGASS - National Composite Policy Index (NCPI) COUNTRY: Trinidad and Tobago Custom analysis extract of: UNGASS - National Composite Policy Index (NCPI) 2007 Caribbean Trinidad and Tobago COUNTRY: Trinidad and Tobago Name of the National AIDS Committee Officer in charge: Patricia

More information