The detection limit for tritium is 300 pci/l

Size: px
Start display at page:

Download "The detection limit for tritium is 300 pci/l"

Transcription

1 New Jersey Department of Environmental Protection - Bureau of Nuclear Engineering (BNE) Investigation of Found in Onsite Vault Background and Installation of Groundwater Monitoring Wells In April of 009, during a planned cable replacement within an onsite cable vault, plant workers at the Oyster Creek Nuclear Generating Station (Oyster Creek) discovered water within the vault. Plant policy is to sample any water collecting onsite in vaults, excavation trenches, and buildings for radioactivity. As a result, sampling of the water that had collected within the vault indicated 0,000 picocuries per Liter tritium. Subsequent to this discovery, 4.5 million pci/l of tritium was detected in an existing, onsite groundwater monitoring well (Well MW-5K-A). Five additional groundwater wells (Wells MW-50, MW-5, MW-5, MW-53, and MW-54) were installed and sampled in the vicinity of the underground cable vault. Existing groundwater monitoring wells were sampled (Wells MW-I-A, MW- I-A, W-, W-C, W-K, W-5C, W-5K, W-3, W-4, W-5 and W-6). These wells are part of Exelon s ongoing voluntary Radiological Groundwater Protection Program (RGPP). As part of Exelon s investigation, they discovered two active pipe leaks. The underground portion of these pipes was replaced during April and May 009. Following this discovery, other nearby pipes underwent pressure testing or excavated and visually inspected and no leakage was found. The inspection of a one-inch stainless steel pipe near the Condensate Storage Tank (CST) was completed in July 009. No leak was detected. In May 009, divers completed an underwater inspection of the inside of a large tank containing water with tritium. This inspection concluded that the tank was not leaking. A pumping well, designated W-55, was installed in May, close to the existing well W-50, in order to conduct a pump test to evaluate hydrogeologic parameters and groundwater flow rates. In August 009, Exelon discovered water leaking into a sump inside the Turbine Building. An investigation revealed that a sixinch aluminum pipe was leaking at the location where the pipe enters through the Turbine Building wall underground. The leaking water had elevated levels of tritium. Exelon made a 4-hour report to the DEP hotline, since some of this water had leaked outside of the building. The leak was stopped and the section of pipe with the leak was replaced. Based on reviews of groundwater elevation and tritium sampling results, additional groundwater monitoring wells were needed in order to better define the groundwater flow paths and the potential for migration of tritium. In September 009, Exelon installed monitoring wells in the Cohansey Formation to assess the potential for vertical migration of tritium from the Cape May Formation into the Cohansey. One well (MW-56I) was installed in the area near existing well MW-5K-A. The second well (MW-57I) was installed east of the Intake Structure in the area of the April 009 leak. A map showing sample locations is available for download here. In March of 00, Exelon completed the drilling of four (4) additional wells in the Cape May Formation (MW-6, MW-64, MW-65, and MW-67) and one () well in the Cohansey Formation (MW-59I) in order to further characterize the groundwater movement in the area. One Cape May well (MW-64) was installed alongside the existing Cohansey well MW-57I. A second well (MW-65) was installed north of existing well W-50 between it and the existing RGPP wells W-5 and W-6. The other two new Cape May wells were installed closer to the CST. One new well (MW-6) is located near the aforementioned oneinch stainless steel pipe near the CST (northwest corner of the Turbine Building). The other new well (MW-67) was installed between the west wall of the Turbine Building and the CST, north of the concrete

2 vault. Wells MW-6 and MW-67 are located in the vicinity of the April 009 release. The newlyinstalled Cohansey Formation well designated MW-59I is co-located with Cape May well, MW-65. In June 00, the DEP and Exelon agreed that additional groundwater monitoring wells were needed in the intermediate and deep Cohansey Formation to further delineate the horizontal and vertical extent of the tritium plume in the Cohansey Formation. As a result, eight (8) new groundwater monitoring wells were installed during June 6 through July 6, 00. Four of the wells (MW-58I, MW-6I, MW-66I and MW-69) were installed in the intermediate Cohansey Formation and four wells (MW-60I, MW-63I, MW-68I and MW-70I) were installed in the deep Cohansey Formation. All of the wells were installed near existing shallow Cohansey and Cape May Formation wells, essentially forming four (4) clusters of wells. Each well cluster includes a shallow, intermediate, and deep Cohansey Formation well along with a Cape May Formation well. The depth of each well is noted on the corresponding table of results. A map showing the locations of the cluster wells is available for download here. In early July 00, two new wells, designated MW-7 and MW-7, were installed in the Cape May Formation. The wells were installed in close proximity to several plant-related system underground pipes/vaults that potentially contain radionuclides (including tritium). Well MW-7 is located along the southwest corner of the Reactor Building near the recently renovated underground piping vault. Well MW-7 is located just north of the Reactor Building. On September 8, 00, a remedial pumping well (MW-73) was installed near the center of the defined shallow Cohansey onsite tritium plume. This well is located on the south side of the circulating water discharge tunnel. It extends into the upper Cohansey Formation, approximately 55-feet deep. It was installed in accordance with a directive issued by the DEP on May 7, 00 that directs Exelon to clean up and remove the discharge of tritium at the Oyster Creek Nuclear Generating Station. A copy of the directive is available for download here. Since November 7, 00, MW-73 has pumped at an approximate rate of 70 gallons per minute. With DEP approval, Exelon is pumping groundwater from remedial well MW-73, continuously measuring the concentration of tritium in the extracted groundwater, and discharging it into the plant s cooling water intake structure in order to reduce the tritium concentration. After being discharged to the plant s intake structure, the extracted groundwater is combined with up to 460,000 gallons of water per minute and pumped through the plant s circulating water system. Up through January 08, 0 million gallons of groundwater have been extracted from pumping well MW-73 and discharged to the plant s intake structure. The BNE is presently receiving weekly split samples from remedial pumping well MW-73. Since pumping of well MW-73 began, tritium concentrations in groundwater monitoring wells, located in the Cape May and Cohansey Formations, have decreased significantly, as indicated by the following DEP split sampling results. The detection limit for tritium is pci/l. MW-5K-A: Highest Reading:,795,335 pci/l Latest Reading: < 37 pci/l MW-50: Highest Reading:,83,074 pci/l Latest Reading: < 43 pci/l MW-55: Highest Reading:,47,70 pci/l Latest Reading: < 44 pci/l MW-56I: Highest Reading:,,800 pci/l Latest Reading:,00 ± 8 pci/l MW-57I: Highest Reading: 76,976 pci/l Latest Reading: 855 ± 73 pci/l MW-67: Highest Reading:,70,000 pci/l Latest Reading: 460 ± 3 pci/l The detection limit for tritium is pci/l

3 At this time, there is no estimate for when the remediation of the entire plume will be completed, however DEP s split sampling results to date indicate that the remedial efforts are having some effect. In addition to monitoring the concentrations of tritium being discharged from the pumping well, Exelon has revised or created new site procedures for the pumping system to ensure that discharge of any extracted groundwater, and evaluation of the impact of discharged groundwater, is done in accordance with U.S. Nuclear Regulatory Commission (NRC) federal regulatory requirements. Liquid (and gaseous) effluent discharges from Oyster Creek are reported to the DEP on a monthly basis. This information is also reported to the NRC on an annual basis in the licensee s Annual Effluent Release Report (the Effluent Report ), available through the NRC website s public library at or at any branch of the Ocean County Public Library. Monitoring and Data Reporting Exelon continues to collect groundwater and surface water samples for tritium analysis to assess the extent and migration of the exiting tritium plumes and to ensure that the tritium levels decrease. The BNE receives splits of these samples for an independent analysis of tritium and gamma emitting radionuclides by the BNE s radiological contract laboratories. Table represents BNE results obtained from split samples of Exelon s onsite groundwater monitoring wells. BNE split sample results from early May 00 through mid-june 00 are not available due to the shutdown of the BNE s Radiological Contract Lab, Centauri Labs, of Montgomery, Alabama on June 9, 00, with no prior notification to the BNE. For this time period, split sample data from Exelon s contract laboratory, Teledyne Brown Engineering, Inc., (Teledyne) have been reported in Table. Immediately following the closing of Centauri Lab s Montgomery lab facility, two short term purchase orders for radiological lab services were consecutively awarded to Eberline Services (Eberline) of Oak Ridge, Tennessee and GEL Laboratories (GEL) of Charleston, South Carolina. Following the expiration of these PO's, a longer-term contract (Waiver of Advertising) was awarded to GEL, on January 0, 0, under the state procurement process. The waiver served as an interim measure (approximately 9 months) while a Request for Proposal (RFP) was developed and put out for open competitive bidding as a multiyear term contract. In August 00, following the shutdown of Centauri Labs, the U.S. Environmental Protection Agency s (EPA) National Air and Radiation Monitoring Laboratory (NAREL) in Montgomery, Alabama, offered to analyze the BNE s split surface water samples for tritium while the BNE secured radioanalytical lab services under the waiver. This is noted on Table (Surface Water). Additional details with regard to the NAREL facility can be found at their website, On October 4, 0, the BNE's three-year term contract for Radiological Environmental Lab Services was awarded to GEL. As the sole contractor, GEL is analyzing all of the BNE's sampling media. s reported in Table were analyzed for tritium and/or gamma emitting radionuclides. No gamma emitting radionuclides have been found. The depth of each well along with the associated groundwater aquifer designation is indicated on Table. Based on the groundwater monitoring wells currently installed in the Cape May and Cohansey Formations, the tritium being detected has not migrated beyond the immediate vicinity of the onsite pipe leaks. No tritium has been detected in any groundwater wells monitored offsite or through the licensee s RGPP. Information on Exelon s RGPP can be found in the licensee s Annual Radiological Environmental Operating Report (the Environmental Report ) available through the U.S. Nuclear Regulatory Commission s website at

4 or at any branch of the Ocean County Public Library. General information on the Oyster Creek Project can be found on Exelon s public website at Exelon groundwater monitoring well split sample data from 009 through the present can be viewed in the licensee s Annual Environmental Monitoring Report, available through the NRC website s public library at Table represents BNE results from split samples of surface water obtained from the plant s intake canal: the main condenser discharge sampling point: and in the discharge canal located at the Route 9 Bridge, which represents the nearest public access point. The DEP s split sample results for tritium and/or gamma emitting radionuclides indicated no activity. A surface water sample taken from the intake canal by Exelon on June, 009 indicated 6,600 pci/l of tritium activity. The DEP did not receive a split of this sample for analysis. The level of tritium activity detected in the intake canal was below the New Jersey Groundwater Quality Standards limit of pci/l and poses no threat to public health and safety. The New Jersey Groundwater Quality Standards are the same as the New Jersey Surface Water Quality Standards and the EPA s drinking water standards for radionuclides. Table 3 represents BNE results obtained from split samples of soil core borings during the installation of the groundwater monitoring wells, MW-50 through MW-55, MW-58I, MW-59I, MW-60I, MW-6, MW- 63I, MW-64, MW-65, MW-66I, MW-67, MW-68I, MW-69I, MW-70I, MW-7, and MW-73. Sampling has shown no detectable levels of gamma emitting radionuclides in any of the soil cores. The DEP will be receiving split soil samples of any additional wells that are installed and will post this data as it becomes available. Throughout the investigation of tritium found onsite at Oyster Creek, BNE staff will continue to participate in ongoing inspections with Exelon and the NRC. Additional information on tritium in groundwater at nuclear power plants can be found at the NRC website address at: Revised: 03/06/8

5 BNE Split Results Table : Groundwater Monitoring Wells MDA NJGWQS MW-5K-A 8.5 Cape May 04/7/09,467,85 ± 4,0 09/5/09 7,50 ± /0/09,358,090 ± 3,003 09/8/09 65,840 ± 74 04/9/09,753,467 ± 4,904 09/30/09 67,80 ± 73 05/0/09,795,335 ± 4,980 0/0/09 60,90 ± /06/09,478,67 ± 4,66 0/07/09 60,630 ± /3/09,304,093 ± 3,40 0/4/09 4,470 ± /0/09 776,787 ±,64 0//09 49,590 ± 65 05/8/09 45,406 ±,007 0/9/09 39,660 ± /0/09 3,30 ±,650 /04/09 3,760 ± /09/09 46,670 ± 658 //09,50 ± 38 06/6/09 63,90 ± 755 /8/09 6,630 ± /3/09 57,60 ± 78 /4/09 6,460 ± /0/09 43,050 ± 63 /0/09 7,400 ± /07/09 48,660 ± 668 /08/09 46,460 ± 6 07/5/09 56,380 ± 666 /5/09,640 ± 44 07//09 65,30 ± 73 //09 4,450 ± /9/09 98,550 ± 868 /9/09 7,360 ± /05/09 94,040 ± 848 0/05/0 8,60 ± //09 48,750 ± 69 0//0 7,40 ± /9/09 35,550 ± 536 0/9/0 9,030 ± 49 08/5/09 4,750 ± 583 0/6/0 37,340 ± /8/09 48,070 ± 65 0/0/0 3,660 ± /3/09,030 ± 957 0/09/0 3,480 ± 44 09/08/09 68,550 ± 79 0/6/0 3,560 ± 3 09/09/09 97,90 ± 866 0/4/0,940 ± 00 09/8/09 08,690 ± 95 03/0/0,670 ± 97 09//09 9,940 ± /09/0 3,40 ± 0 09/3/09 77,890 ± /6/0,70 ± Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

6 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-5K-A 8.5 Cape May 03/3/ ± 56 09//0,900 ± 38 (continued) 03/3/0 4,30 ± 5 09/8/0 9,950 ± /06/0 5,370 ± 7 0/3/0 85 ± 64 04/4/0 4,50 ± 36 0/7/0,40 ± 34 04/0/0 7,30 ± 70 /0/0,0 ± 38 04/7/0 9,600 ± 308 /0/0 3,470 ± /04/0,800* /4/0 6,80 ± 90 05//0 7,390* 0// 46,000 ± /9/0 9,360* 0/5/ 0,00 ± /5/0 8,00* 03/5/ 0,000 ± /0/0 4,70* 04/3/ 4,500 ± /08/0 6,0* 05/0/ 9,70 ± /5/0 4,770* 06/4/ 8, ± //0 3,884 ± /3/ 4,370 ± 48 06/30/0 3,666 ± /6/,450 ± 96 07/07/0 5,849 ± /3/,670 ± 94 07/3/0 6,47 ± 445 0//,480 ± 8 07//0 8,59 ± 49 /6/,450 ± 7 07/7/0 7,6 ± 47 /4/ 557 ± 44 08/04/0 8,87 ± 483 0/8/ 84 ± 83 08//0 8,73 ± 493 0/4/,30 ± 7 08/8/0 9,46 ± /3/ < 3 08/4/0 0,700 ± /8/ 4,0 ± 44 09/08/0 9,400 ± /5/ < 5 *BNE split sample results from 05/04/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

7 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-5K-A 8.5 Cape May 06/0/ < 68 0/8/6 < 4 (continued) 07/03/ < 58 0/0/7 < 4 08/5/ < 63 04/05/7 < 0 09/9/ < 97 07//7 < 36 0/0/ < 73 0/7/7 < 4 /4/ < 4 0/8/8 < 37 /05/ < 7 0/08/3 < 0 0//3 < 6 03/05/3 < 76 04/09/3 < 7 07//3 < 63 0/08/3 < 59 0/3/4 < 85 04/09/4 < 09 07/5/4 < 58 0/4/4 70 ± 58 0/3/5 < 6 04/4/5 < 38 07/5/5 < 7 0/3/5 < 6 0/0/6 < 60 04/05/6 < 0 07/9/6 < 3 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

8 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 04//09,83,074 ± 4,349 09/8/09 6,0 ±,60 04/9/09,4,7 ± 4,44 09/30/09 477,00 ±,890 05/06/09,05,065 ± 4,87 0/0/09 565,00 ±,050 05/3/09,9,943 ± 4,53 0/07/09 39,60 ±,70 05/0/09,97,053 ± 4,9 0/4/09 30,340 ±,550 05/8/09,587,4 ± 3,80 0//09 366,750 ±,660 06/0/09,90,60 ± 3,30 0/8/09 37,940 ±,00 06/09/09,775,50 ± 3,940 /04/09 85, ±,450 06/6/09,608,80 ± 3,890 //09 7,690 ±,430 06/3/09,559,0 ± 3,680 /8/09 343,80 ±,60 07/0/09,6,650 ± 3,70 /4/09 333,790 ±,580 07/07/09 940,90 ±,860 /0/09 353,550 ±,630 07/5/09,094,690 ±,850 /08/09 374,360 ±,670 07//09 94,0 ±,640 /5/09 07,30 ±,50 07/9/09 909,470 ±,600 //09 74,40 ±,430 08/05/09 980,50 ±,690 /9/09 44,980 ±,350 08//09 80,90 ±,460 0/05/0 59,840 ±,40 08/9/09 56,00 ±,040 0//0 57,0 ±,40 08/5/09,45,40 ±,90 0/9/0 73,830 ±,430 08/8/09 866,00 ±,530 0/6/0 7,30 ±,40 08/3/09,600,500 ± 3,440 0/0/0 386,0 ±,670 09/08/09,070,50 ±,80 0/09/0 363,060 ±,60 09/09/09,074,50 ±,830 0/6/0 388,700 ±,670 09/6/09 88,0 ±,480 0/4/0 07,050 ±,30 09/8/09 494,480 ±,90 03/0/0 43, ±,00 09//09 67,730 ±,60 03/09/0 86,460 ±,60 09/3/09 634,360 ±,70 03/6/0 34,80 ± /5/09 65,0 ±,00 03/3/0 80,000 ±,00 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

9 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 03/3/0 73,000 ±,80 0/06/0 9,000 ±,40 (continued) 04/07/0 53,000 ±,00 0/3/0 46,000 ±,870 04/4/0 76,000 ±,090 0/0/0 4,000 ±,430 04//0 95,800 ± 843 0/7/0 33,000 ±,360 04/8/0,000 ±,60 /03/0 5,000 ±,30 05/04/0 5,000* /0/0 34,000 ±,640 05//0 6,000* /7/0 5,000 ±,00 05/8/0 75,000* /3/0,000 ±,350 05/6/0 09,000* /5/0 7,000 ±,60 06/0/0 4,000* 0// 83,000 ±,340 06/08/0 87,000* 0/5/ 3,000 ±,40 06/5/0 48,000* 04/3/ 0,000 ±,030 06//0 95,9 ± /0/ 63,00 ±,70 06/30/0 67,085 ± /4/ 65, ±,40 07/07/0 64,79 ± /3/ 5,800 ±,390 07/4/0 84,564 ± 99 08/6/ 99,000 ±,90 07//0 75,7 ± 93 09/3/ 7,700 ±,080 07/7/0 36,00 ± 788 0// 46,400 ± 94 08/04/0 07,94 ± 760 /6/ 50,700 ± 93 08//0 07,404 ± 768 /08/ 44,500 ±, 08/8/0 9,550 ±,87 0/7/ 5,00 ± /4/0 74,000 ± 3,430 0/4/ 54, ±,540 08/3/0 4,000 ±,50 03/3/ 48,900 ± /08/0 83,500 ±,650 04/8/ 36,400 ±,60 09/5/0 3,000 ±,580 05/5/ 3,900 ± //0 44,000 ±,00 06/0/ 0,900 ± /9/0 05,000 ± 4,000 07/03/ 0,00 ± 688 *BNE split sample results from 05/04/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

10 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 08/4/ 3,000 ± 77 0/7/8 < 43 (continued) 09/9/ 6,0 ± 46 0/0/ 9,000 ± 789 /4/ 3,600 ± 780 /05/, ± 640 0/08/3 8,000 ± 94 0//3 7, ± /05/3 8,350 ± 67 04/08/3 8,500 ± /0/3 8,330 ± 366 0/08/3,500 ± 430 0/4/4 4,600 ± /08/4 3,60 ± /5/4 6,70 ± 38 0/4/4 3,080 ± 47 0/3/5 5,980 ± 38 04/4/5 337 ± 54 07/5/5 733 ± 55 0/3/5,990 ± 8 0/0/6 4,440 ± /05/6,350 ± 73 07/9/6 653 ± 58 0/8/6,00 ± 3 0/0/7 < 76 04/04/7 < 07 07/0/7 < 4 0/7/7 < Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

11 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 04/9/09,38,59 ± 4,083 /9/09 3,680 ± 33 05/06/09,8,494 ± 6,463 0/05/0 34,90 ± /3/09,549,98 ± 3,908 0/9/0 99,360 ± 87 05/0/09,84,459 ± 3,470 0/6/0 98,360 ± 86 05/7/09,99,630 ± 4,060 0/0/0 50,990 ± 63 06/0/09,00,40 ± 3,880 0/09/0 95,00 ± 84 06/09/09,356,880 ± 3,440 0/6/0 7,880 ± 88 06/6/09,53,90 ± 3,360 0/3/0 36,930 ± /3/09 535,990 ±,50 03/0/0 7,50 ± 8 07/0/09 78,470 ±,60 03/09/0 5,50 ± /07/09 80,40 ±,640 03/6/0 8,60 ± /5/09,570,800 ± 3,40 03/3/0 9,80 ± 3 07/9/09,555,80 ± 3,390 03/30/0 5,970 ± 78 08/05/09,433,50 ± 3,50 04/06/0 4,500 ± //09 93,0 ±,60 04/3/0 3,00 ± 43 08/0/09 03,960 ±,40 04/0/0 37,500 ± 5 08/6/09 3,630 ±,550 04/7/0 33,800 ± 5 08/3/09 9,80 ±,80 05/04/0 48,600* 09/6/09 47,000 ±,00 05/5/0 37,800* 09/8/09 4,000 ±,30 06/0/0 38,00* 09//09 4,000 ±,80 09/4/ 6,350 ± 9 09/3/09 697,000 ±,360 04/05/7 < 3 09/5/09 76,000 ±,480 09/8/09 744,000 ±,450 BNE split samples between 0/09/09 and //09, 05//0, 05/9/0, 06/08/0 through 08/04/, and 0/4/ through 0/0/7 were not available. The well was reported dry by Exelon. * BNE split sample results from 05/04/0 through 06/0/0 were not available due to the closing of Centauri Labs Alabama facility. For this time-period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

12 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 04/3/09 < 96 /8/09 < 94 04/9/09 < 90 /4/09 < 94 05/3/09 < 83 /0/09 < 94 05/0/09 < 96 /08/09 < 93 05/7/09 < 88 /5/09 < 67 06/0/09 < 77 //09 < 67 06/09/09 < 75 /9/09 < 76 06/6/09,30 ± 09 0/05/0 < 89 06/3/09 < 73 0//0 < 94 06/30/09 < 84 0/9/0 < 90 07/07/09 < 83 0/6/0 < 87 07/5/09 < 78 0/0/0 < 87 07//09 < 78 0/09/0 < 87 07/9/09 < 77 0/6/0 < 84 08/05/09 < 77 0/3/0 < 85 08//09,50 ± 8 03/0/0 < 85 08/9/09 < 66 03/09/0 < 79 08/5/09 < 66 03/6/0 < 73 09/6/09 < 73 03/30/0 < 86 09/3/09 < 73 04/06/0 < 86 09/30/09 < 7 04/3/0 < 67 0/07/ ± 60 04/0/0 < 67 0/4/ ± 60 04/8/0 < 66 0//09 < 48 05/04/0 < 79* 0/8/ ± 60 05//0 < 77* /04/09 < 5 05/8/0 < 53* //09 < 56 05/5/0 < 78* *BNE split sample results from 05/04/0 through 06/6/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

13 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 06/03/0 < 55* /5/ < 80 (continued) 06/09/0 < 68* /4/ < 04 06/6/0 < 5* 0/7/ < 7 06//0 < 6 0/3/ < 3 06/9/0 < 07 03/3/ < 9 07/07/0 < 0 04/7/ < 03 07/3/0 < /5/ < 53 07//0 < /9/ < 60 07/8/0 < /0/ < 57 08/03/0 < /5/ < 70 08/0/0 < /8/ < 90 08/7/0 < 59 0/0/ < 79 08/5/0 < 34 /4/ < 7 09/8/0 < 45 /05/ < 68 0/3/0 < 0/08/3 < 4 /6/0 < 99 0//3 < /4/0 < 4 03/05/3 < 77 0// < 0 04/09/3 < 40 0/5/ < 7 07/09/3 < 63 03/5/ < 84 0/09/3 < 98 04// < 57 0/4/4 < 85 05/0/ < 97 04/09/4 < 09 06/4/ < 8 07/6/4 < 54 07// < 59 0/3/4 < 37 08/6/ < 69 0/3/5 < 6 09/3/ < 04/4/5 < 40 0// < 69 07/5/5 < 09 *BNE split sample results from 05/04/0 through 06/6/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

14 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 0/3/5 < (continued) 0/0/6 < 64 04/05/6 < 03 07/9/6 < 7 0/7/6 < 9 0/0/7 < 43 04/05/7 < 0 07/0/7 < 38 0/0/7 < 0/7/8 < 37 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

15 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 04/4/09,56 ± 98 /04/09 < 50 04/9/09 4,59 ± 6 //09 < 53 05/0/09 7,0 ± 98 /8/09 < 94 05/06/09 6,43 ± 89 /4/09 < 94 05/3/09,54 ± 7 /0/09 < 94 05/0/09,048 ± 0 /08/09 < 93 05/7/09,93 ± /5/09 < 67 06/0/09 76 ± 8 // ± 67 06/09/09 37 ± 7 /9/09 < 76 06/6/09 < 63 0/05/0 < 89 06/3/09 < 73 0//0 < 93 06/30/09 < 84 0/9/0 < 89 07/07/09 < 83 0/6/0 < 87 07/5/09 < 78 0/0/0 < 87 07//09 < 78 0/09/0 < 87 07/9/09 < 77 0/6/0 < 88 08/05/09 < 77 0/3/0 < 89 08// ± 6 03/0/0 < 96 08/9/09 < 66 03/09/0 < 86 08/5/09 < 66 03/6/0 < 7 09/6/09 < 73 03/30/0 < 67 09/3/09 < 73 04/06/0 < 89 09/30/09 < 7 04/3/0 < 66 0/07/ ± 60 04/0/0 < 0 0/4/ ± 67 04/7/0 < 63 0//09 < 49 05/04/0 < 75* 0/8/09 49 ± 56 05//0 < 78* *BNE split sample results from 05/04/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

16 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 05/8/0 < 68* 07//,940 ± 85 (continued) 05/5/0 < 78* 08/6/ 39 ± 33 06/03/0 < 79* 09/3/ < 0 06/08/0 < 68* 0// < 74 06/5/0 5* /5/ < 78 06//0 < 4 /4/ < 0 06/30/0 < 0 0/7/ < 07/08/0 < 0 0/3/ < 80 07/3/0 < 49 03// < 07//0 < /7/ < 00 07/7/0 < /5/ < 53 08/04/0 < /0/ < 76 08//0 < /03/ < 6 08/7/0 < /5/ < 67 08/5/0 < 35 09/8/ < 90 09/8/0 < 47 0/0/ < 75 0//0 < 06 /4/ < 7 /6/0 < 04 /05/ < 68 /4/0 < 07 0/09/3 < 37 0// < 03 0//3 < 09 0/5/ < 78 03/05/3 < 79 03/5/ 33 ± 45 04/09/3 < 33 04// < 53 07//3 < 06 05/0/ < 96 0/08/3 < 60 06/4/ 7,770 ± 503 0/5/4 < 3 *BNE split sample results from 05/04/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

17 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 04/0/4 < 09 (continued) 07/7/4 < 0 0/4/4 < 44 0/3/5 < 58 04/6/5 < 39 07/5/5 < 8 0/4/5 < 3 0//6 < 6 04/07/6 < 03 07/0/6 < 30 0/0/6 < 4 0//7 < 04/05/7 < 97 07//7 < 38 0//7 < 05 0/9/8 < 43 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

18 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 04//09 3,565 ± 34 /04/09 54 ± 63 04/9/09 46 ± 8 //09,0 ± 73 05/0/09 44 ± 56 /8/ ± 94 05/06/09 5,894 ± 85 /4/09 3,390 ± 3 05/3/09 3,65 ± 46 /0/09 5,950 ± 69 05/0/09,40 ± 8 /08/09,60 ± 05/8/09 4,93 ± 70 /5/09 45 ± 69 06/0/09 6,460 ± 94 // ± 75 06/09/09 4,0 ± 54 /9/ ± 74 06/6/09,690 ± 0 0/05/0 49 ± 84 06/3/09 4,000 ± 47 0//0,535 ± 08 06/30/09,950 ± 3 0/9/0,30 ± 00 07/07/09 3,380 ± 39 0/6/0 5,00 ± 53 07/5/09 8,380 ± 98 0/0/0 4,480 ± 43 07//09 6,070 ± 67 0/09/0 3,470 ± 8 07/9/09 5,050 ± 53 0/6/0 0,670 ± 30 08/05/09 3,440 ± 8 0/3/0 759 ± 79 08//09,590 ± 07 03/0/0 < 90 08/9/09 3,00 ± 8 03/09/0,0 ± 83 08/5/09,760 ± 95 03/6/0 < 70 09/6/09,30 ± 8 03/30/0 < 84 09/3/09,860 ± 95 04/06/0 45 ± 80 09/30/09,50 ± 69 04/3/0 47 ± 68 0/07/09,500 ± 8 04/0/0 4,860 ± 38 0/4/09, ± 05 04/7/0,890 ± 94 0// ± 65 05/04/0 550* 0/8/09 55 ± 60 05//0 368* *BNE split sample results from 05/04/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

19 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 05/8/0 < 49* 05/0/ < 98 (continued) 05/5/0 < 79* 06/4/,040 ± 06/0/0 < 80* 07/3/ 350 ± 49 06/09/0 < 00* 08/6/ 97 ± 43 06/5/0 44* 09/3/ < 06//0 < 7 0//,050 ± 08 06/9/0 < 09 /6/ 749 ± 00 07/08/0 < 09 /4/ 47 ± 3 07/4/0 < 473 0/8/ < 44 07//0 < 47 0/4/ 334 ± 50 07/7/0 < 45 03/3/ 73 ± 44 08/04/0 < 48 04/8/ < 08//0 < /6/ < 49 08/8/0 < 58 06/0/ 659 ± 0 08/5/0 304 ± 66 07/03/,060 ± 67 09/08/0 57 ± 4 08/5/ 38 ± 53 09//0 < 5 09/8/ 3,780 ± /8/0 304 ± 6 0/0/ 3,990 ± 374 0/3/0 343 ± 93 /4/ < 5 0/7/0 809 ± 37 /05/ < 68 /0/0 473 ± 65 0/08/3 < 38 /3/0,00 ± 55 0//3 < 06 /4/0 570 ± 50 03/05/3 < 79 0// < 0 04/09/3 < 39 0/5/ < 9 07/0/3 303 ± 66 03/5/ < 83 0/08/3 < 65 04/3/ < 58 0/4/4 < 3 *BNE split sample results from 05/04/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

20 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 04/09/4 < 09 (continued) 07/6/4 0 ± 40 0/4/4 33 ± 6 0/3/5 < 73 04/4/5 38 ± 54 07/5/5 389 ± 43 0/3/5 56 ± 33 0/0/6 < 55 04/05/6 < 08 07/9/6 < 9 0/8/6 < 9 0/0/7 58 ± 37 04/05/7 < 08 07//7 380 ± 54 0/0/7 668 ± 5 0/7/8 < 6 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

21 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 06/0/09,469,959 ± 3,637 /5/09 3,950 ± 53 07/0/09 0,780 ± 996 //09 50,500 ± /9/09 84,070 ±,460 /9/09 0,770 ± 45 08/5/09 667,030 ±,0 0/05/0 3,30 ± 59 08/8/09,47,70 ± 3,90 0//0 6,40 ± 7 08/3/09 75,630 ±,360 0/9/0 5,30 ± /04/09 560,560 ±,040 0/6/0 66,470 ± /08/09 607,780 ±,30 0/0/0 5,680 ± /4/09 35,90 ±,00 0/09/0 6,970 ± /6/09 55,90 ±,080 0/6/0 34,740 ± 5 09/8/09 3,440 ± 978 0/4/0,80 ± //09 5,960 ±,070 03/0/0 4,630 ± 36 09/3/09 73,70 ±,40 03/09/0,60 ± /5/09 0,770 ±,90 03/6/0 3,90 ± /8/09 346,540 ±,60 03/3/0,400 ± /30/09 6,80 ±,80 03/3/0 0,400 ± 334 0/0/09 0,770 ±,40 04/07/0 7,800 ± 378 0/07/09 79,870 ±,60 04/4/0 9,900 ± 47 0/4/09 90,80 ±,00 04//0 68,800 ± 69 0//09 5,40 ± 99 04/7/0 87,500 ± 80 0/8/09 90,360 ± /04/0 68,000* /04/09 44,050 ± //0 95,000* //09 96,450 ± /9/0 9,800* /8/09 75,490 ± 80 05/6/0 50,800* /4/09 83,350 ± /0/0 56,600* /0/09 94,60 ± 85 06/08/0 53,800* /08/09 40,390 ± /5/0 58,800* *BNE split sample results from 05/04/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

22 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 06//0 65,480 ± /0/ 9,060 ± 669 (continued) 06/30/0 7,079 ± /4/ 3,00 ± 98 07/08/0 88,38 ± /3/ 6,30 ± /4/0 77,3 ± /6/,40 ± 79 07//0 66, ± /3/ 7,0 ± /7/0 53,776 ± 506 0// 8,650 ± 46 08/04/0 5,43 ± 546 /6/ 6,900 ± //0 66,778 ± 607 /08/ 4,980 ± /8/0 6,733 ±,80 0/7/ 9,550 ± 4 08/4/0 7,400 ±,840 0/4/ 0,400 ± /3/0 50,700 ±,00 03/3/ 6,90 ± 98 09/08/0 74, ±,470 04/8/ 4,900 ± /5/0 85,00 ±,680 05/5/ 3,50 ± 60 09//0 53,900 ±,0 06/0/,600 ± 99 09/9/0 36,800 ± /03/,470 ± 363 0/06/0 7,460 ± /4/ < 85 0/3/0 3,000 ± /9/,90 ± 39 0/0/0 8,000 ± 5 0/0/,400 ± 656 0/7/0 7,700 ± 50 /4/ 7 ± 4 /03/0 7,000 ± 640 /05/ 978 ± /0/0,000 ± 439 0/08/3,730 ± 307 /7/0 4,900 ± 49 0//3 64 ± 56 /3/0,400 ± /05/3 94 ± 3 /5/0 30,400 ± /08/3,70 ± 84 0// 4,00 ± 49 07//3,330 ± 85 0/5/ 6,700 ± 59 0/08/3 3,00 ± 63 03/5/ 7,90 ± 55 0/4/4 < 5 04/3/ 5,000 ± /08/4 < 09 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

23 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 07/5/4,00 ± 75 (continued) 0/4/4 539 ± 66 0/3/5 < 67 04/4/5 < 7 07/5/5 < 3 0/3/5 < 0/0/6 < 63 04/05/6 < 05 07/9/6 < 3 0/8/6 < 9 0/0/7 < 74 04/04/7 < 07 07//7 < 4 0/0/7 < 4 0/7/8 < 44 Results in picocuries per liter Sampling frequency is quarterly

24 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-56I 5.9 Cohansey 09/6/09 47,830 ±,870 0/3/0,76,430 ±,870 09/8/09 430,890 ±,790 03/0/0,54,40 ±,900 09/3/09 537,400 ±,000 03/09/0,060,50 ±,70 09/5/09 53,540 ±,990 03/6/0,069,680 ±,740 09/8/09 566,0 ±,070 03/3/0 98,000 ±,690 09/30/09 596,900 ±,0 03/3/0 906,000 ±,660 0/0/09 636,940 ±,80 04/06/0 87,000 ±,60 0/07/09 589,30 ±,090 04/4/0 9,000 ±,470 0/4/09 698,70 ±,80 04/0/0 96,000 ±,470 0//09 765,490 ±,390 04/7/0 990,000 ±,650 0/9/09 897,460 ±,570 05/04/0,,000* /04/09 938,790 ±,630 05//0 979,000* //09 945,70 ±,670 05/8/0 985,000* /8/09 957,790 ±,670 05/5/0 868,000* /4/09 993,90 ±,70 06/0/0,00,000* /0/09,86,030 ±,970 06/08/0,080,000* /08/09,,800 ± 3,00 06/5/0,0* /5/09,66,990 ±,940 06//0 777,484 ±,978 //09,40,40 ±,90 06/30/0 749,60 ±,88 /9/09,056,500 ±,800 07/07/0 70,353 ±,805 0/05/0,06,580 ±,80 07/4/0 60,8 ±,650 0//0 983,540 ±,750 07//0 657,40 ±,764 0/9/0 940,970 ±,640 07/7/0 55,797 ±,57 0/6/0,089,600 ±,800 08/04/0 63,57 ±,86 0/0/0,,600 ±,890 08//0 603,66 ±,79 0/09/0,39,800 ±,880 08/8/0 634,648 ± 3,96 0/6/0 874,00 ±,470 08/4/0 64,000 ±,500 *BNE split sample results from 05/04/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

25 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-56I 5.9 Cohansey 08/3/0 538,000 ± 0,500 0/4/ 4,400 ± 789 (continued) 09/08/0 596,000 ±,700 03/3/ 4,90 ± 7 09/5/0 578,000 ±,30 04/8/ 3,440 ± 40 09//0 96,000 ±,730 05/5/ 5,00 ± 94 09/8/0 333,000 ± 6,490 06/0/ 98,700 ±,080 0/06/0 474,000 ±,80 07/03/,800 ± 409 0/4/0 305,000 ± 5,940 08/4/ 4,00 ±,340 0/0/0 337,000 ±,80 09/9/ 6,50 ± 470 0/7/0 3,000 ± 3,30 0/0/ 6,690 ± 483 /03/0 377,000 ± 7, /4/ 46,700 ±,440 /0/0 338,000 ± 6,60 /05/ 34, ±,070 /7/0 74,000 ±,760 0/08/3 5,350 ± 493 /3/0 4,000 ± 8 0//3 4,800 ± 93 /5/0 3,90 ± 35 03/05/3 6,80 ± 56 0//,340 ± 93 04/08/3 6,00 ± 0/5/ 4,960 ± 36 07//3 8,70 ± 38 03/5/ 5,060 ± 459 0/08/3 4,340 ± 9 04/3/ 5,090 ± 506 0/3/4 8,900 ± 54 05/0/ 3,980 ± /09/4 7,870 ± 64 06/4/ 0,700 ± /5/4 5,630 ± /3/ 7,540 ± 55 0/4/4 4,500 ± /6/ 46,500 ±,90 //4 7,90 ± /3/ 7,800 ± 86 0/3/5 5,090 ± 305 0// 5,490 ± /4/5,00 ± 53 /6/ 5,960 ± 35 06/05/5,980 ± 70 /4/ 6,0 ± 8 07/5/5 7,330 ± 33 0/8/ 5,870 ± 33 0/3/5,30 ± 95 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

26 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-56I 5.9 Cohansey 0/0/6,50 ± 357 (continued) 04/05/6,90 ± 07/9/6,580 ± 0/8/6,770 ± 89 0/7/7 8,030 ± /05/7 9,970 ± 35 07//7 3,340 ± 46 0/0/7 4,070 ± 40 0/7/8,00 ± 8 Results in picocuries per liter

27 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-57I 47.9 Cohansey 09/03/09 536,700 ±,000 0/09/0 4,60 ±,50 09//09 76,976 ±,383 0/6/0 9,860 ±,90 09/6/09 455,60 ±,840 0/4/0 87,30 ±,440 09/8/09 39,930 ±,700 03/0/0 46,90 ±,330 09/3/09 407,43 ±,740 03/09/0 07,840 ±,0 09/5/09 388,670 ±,700 03/6/0 8,560 ±,50 09/8/09 359,0 ±,650 03/3/0 98,000 ±,40 09/30/09 389,40 ±,70 03/3/0 4,000 ± 956 0/0/09 470,360 ±,870 04/07/0 94,000 ±,40 0/07/09 505,0 ±,940 04/4/0 68,000 ±,060 0/4/09 43,30 ±,780 04/0/0 55,000 ±,00 0//09 9,380 ±,480 04/7/0 74,000 ±,0 0/9/09 40,580 ±,740 05/05/0 83,800* /04/09 33,990 ±,570 05//0 60,00* //09 88,900 ±,460 05/9/0 83,800* /8/09 403,090 ±,740 05/5/0 59,800* /4/09 350,30 ±,60 06/0/0 53,600* /0/09 569,690 ±,060 06/08/0 5,900* /08/09 89,460 ±,470 06/5/0 5,* /5/09 549,530 ±,00 06//0 69,680 ± 60 //09 34,700 ±,530 06/9/0 96,565 ± 678 /9/09 53,00 ±,380 07/07/0 9,65 ± 67 0/05/0 94,700 ±,50 07/4/0,60 ± 336 0//0 94,680 ±,50 07//0 55,763 ± 5 0/9/0 637,900 ±,80 07/7/0 5,550 ± 54 0/6/0 48,750 ±,330 08/03/0 40,496 ± 476 0/0/0 77,340 ±,430 08//0 54,53 ± 556 *BNE split sample results from 05/05/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

28 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-57I 47.9 Cohansey 08/8/0 49,698 ±,50 0/4/ 0,600 ± 946 (continued) 08/4/0 50,000 ±,960 03/3/ 4,400 ± /3/0 49, ± /8/ 8,700 ±,0 09/08/0 64,700 ±,80 05/6/ 35, ± /5/0 60, ±,00 06/0/ 34,800 ±,30 09//0 7,700 ± /03/ 3, ±,00 09/9/0 64,700 ±, 08/4/ 9,500 ± 90 0/06/0 54,900 ± /8/ 3,800 ± 690 0/3/0 80,800 ±,60 0/0/ 6,000 ± 74 0/0/0 40,900 ± 773 /4/ 8,700 ± 95 0/7/0 7,450 ± 358 /05/ 5,800 ± 70 /03/0 7,00 ±,380 0/08/3 6,690 ± 557 /0/0 4,700 ± 857 0//3 3,700 ± 46 /6/0 47,600 ± /05/3 5,900 ± 860 /5/0 69,900 ± 86 04/08/3 9, ± 500 0// 8,600 ± 89 07/09/3,900 ± 449 0/5/ 80,00 ±,0 0/08/3,40 ± 0 04/3/ 84,000 ±,670 0/4/4 4,400 ± /0/ 37,400 ±,330 04/09/4 0,900 ± 70 06/4/ 40,700 ±,0 07/5/4 6,940 ± /3/ 7,00 ± 798 0/3/4 6,370 ± 34 08/6/ 49,400 ±,30 0/3/5,760 ± 9 09/3/ 38,700 ±,90 04/4/5,660 ± 0 0// 5,700 ± 55 07/5/5 70 ± 54 /6/ 33,600 ± 768 0/3/5,970 ± 08 /08/ 7,600 ±,00 0/0/6 6,350 ± 5 0/7/ 9,800 ±,40 04/05/6,670 ± 4 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

29 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-57I 47.9 Cohansey 07/9/6,680 ± 8 (continued) 0/7/6 3,500 ± 395 0/0/7 435 ± 64 04/03/7 < 0 07/0/7 < 4 0/0/7 56 ± 47 0/7/8 855 ± 73 Results in picocuries per liter Current sampling frequency is quarterly

30 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-58I 7.0 Cohansey 07//0 < 3 0/0/6 < 6 07/7/0 < 99 04/05/6 < 40 08/03/0 < 7 07/9/6 < 0 08//0 < 8 0/7/6 < 93 08/8/0 < 58 0/0/7 < 8 08/4/0 < 37 04/03/7 < 5 0/4/0 < 0 07/0/7 < 96 0// < 5 0/0/7 < 4 04/3/ < 8 0/7/8 < 83 07// < 8 0// < 55 0/8/ < 40 04/8/ < 8 07/03/ < 7 0/0/ < 6 0/08/3 < 40 04/09/3 < 8 07/09/3 < 6 0/08/3 < 60 0/4/4 < 8 04/09/4 < 55 07/5/4 < 08 0/3/4 < 45 0/3/5 < 69 04/4/5 < 73 07//5 < 6 0/3/5 < 3 Results in picocuries per liter Well Water ID MW-58I is part of the Exelon Nuclear existing Radiological Groundwater Protection Program. Current sampling frequency is quarterly.

31 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-59I 44.0 Cohansey 03/4/0,540 ± 08 09/8/0 < 49 03/30/0,660 ± 7 0/3/0 < 3 04/06/0,000 ± 4 0/7/0 < 45 04/3/0,0 ± 99 /0/0 < 48 04//0,40 ± 07 /3/0 353 ± 9 04/8/0,060 ± 98 /4/0 < 08 05/05/0,580* 0// < 99 05//0,60* 0/5/ < 8 05/8/0,580* 04/3/ < 56 05/6/0,70* 07/3/ < 59 06/0/0 776* 0// < 79 06/08/0 755* 0/7/ < 4 06/6/0 563* 04/8/ < 03 06//0 < 5 07/0/ < 60 06/9/0 < 447 0/0/ < 69 07/07/0 < 438 0/08/3 < 77 07/3/0 < /09/3 < 40 07//0 < /09/3 < 6 07/8/0 < 456 0/09/3 < 5 08/03/0 < 440 0/4/4 < 84 08/0/0 < /09/4 < 58 08/8/0 < /6/4 < 08/4/0 < 36 0/3/4 < 40 09/08/0 < 09 0/3/5 < 66 09//0 < 5 04/4/5 < 75 *BNE split sample results from 05/05/0 through 06/6/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter Current sampling frequency is quarterly.

32 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-59I 44.0 Cohansey 07//5 < (continued) 0/3/5 < 00 0/0/6 < 59 04/05/6 < 4 07/9/6 < 0/7/6 < 9 0/0/7 < 80 04/04/7 534 ± 56 07/0/7 < 0 0/0/7 < 3 0/7/8 < 64 *BNE split sample results from 05/05/0 through 06/6/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter Current sampling frequency is quarterly.

33 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-60I 9.0 Cohansey 07//0 < 0 07//5 < 07 07/7/0 < 98 0/3/5 < 99 08/03/0 < 3 0/0/6 < 60 08//0 < 3 04/05/6 < 6 08/8/0 < /9/6 < 08/4/0 < 36 0/7/6 < 90 0/4/0 < 4 0/0/7 < 8 0// < 3 04/03/7 < 03 04/3/ < 79 07/0/7 < 0 07// < 85 0/0/7 < 0 0// < 75 0/7/8 < 90 0/8/ < 47 04/8/ < 07/03/ < 4 0/0/ < 0 0/08/3 < 37 04/09/3 < 50 07/09/3 < 64 0/08/3 < 54 0/4/4 < 87 04/09/4 < 64 07/5/4 < 3 0/3/4 < 40 0/3/5 < 76 04/4/5 < 78 Results in picocuries per liter Well Water ID MW-60I is part of the Exelon Nuclear existing Radiological Groundwater Protection Program. Current sampling frequency is quarterly.

34 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-6I 7.0 Cohansey 07//0 4,85 ± 98 07//5 < 07/7/0 8,469 ± 3 0/3/5 < 0 08/03/0 0,569 ± 68 0/0/6 < 53 08//0,337 ± 77 04/05/6 < 44 08/8/0,766 ± /9/6 < 08/4/0,000 ± 746 0/8/6 < 88 0// 6,80 ±,40 0/0/7 < 8 04// 390 ±75 04/03/7 < 6 07/3/ < 59 07//7 < 9 0// < 78 0/0/7 < 0/8/ < 3 0/7/8 < 39 04/7/ < 07/03/ < 0 0/03/ < 0 0/08/3 < 40 04/09/3 < 5 07//3 < 6 0/08/3 < 59 0/3/4 < 04/0/4 < 55 07/6/4 < 03 0/4/4 < 38 0/3/5 < 69 04/5/5 < 75 Results in picocuries per liter Well Water ID MW-6I is part of the Exelon Nuclear existing Radiological Groundwater Protection Program. Current sampling frequency is quarterly.

35 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 03/0/0 < 70 09/8/0 < 45 03/7/0 < 9 0/3/0 < 3 03/4/0 < 84 /6/0 < 03 03/30/0 < 83 /4/0 < 03 04/06/0 < 84 0// < 0 04/3/0 < 70 0/5/ < 9 04/0/0 < 65 03/5/ 40 ± 30 04/8/0 < 67 04// < 55 05/04/0 < 80* 05/0/ < 95 05//0 < 76* 06/4/ < 79 05/8/0 < 68* 07// < 60 05/7/0 < 78* 08/6/ < 74 06/03/0 < 00* 09/3/ < 8 06/09/0 < 69* 0// < 77 06/6/0 < 50* /5/ < 78 06/3/0 < 05 /08/ < 06 06/9/0 < 05 0/7/ < 44 07/07/0 < 06 0/3/ < 0 07/3/0 < /3/ < 0 07//0 < 0 04/7/ < 99 07/8/0 < /5/ < 55 08/04/0 < /9/ < 69 08/0/0 3,0 ± /0/ < 64 08/7/0 < /4/ < 70 08/5/0 < 4 09/8/ < 9 *BNE split sample results from 05/04/0 through 06/6/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

36 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 0/0/ < 75 (continued) 03/05/3 < 37 04/08/3 < 70 07//3 < 05 0/09/3 < 00 0/4/4 < 7 04/08/4 < 09 07/5/4 < 0/4/4 < 35 0/3/5 < 75 04/6/5 < 36 07/5/5 < 5 0/4/5 < 07 0/0/6 < 65 04/06/6 < 0 07/9/6 < 33 0/8/6 < 3 0/0/7 < 87 04/04/7 < 06 07//7 < 4 0/0/7 < 4 0/7/8 < 94 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

37 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-63I 9.0 Cohansey 07//0 < 3 07//5 < 07/7/0 < 03 0/3/5 < 06 08/03/0 < 4 0/0/6 < 60 08//0 < 3 04/05/6 < 4 08/7/0 < 56 07/9/6 < 7 08/4/0 < 33 0/8/6 < 90 0/4/0 < 0 0/0/7 < 0// < 5 04/03/7 < 08 04// < 70 07//7 < 48 07/3/ < 80 0/0/7 < 09 0// < 79 0/7/8 < 7 0/8/ < 48 04/7/ < 07/03/ < 07 0/03/ < 0/08/3 < 4 04/09/3 < 53 07//3 < 95 0/08/3 < 80 0/3/4 < 86 04/0/4 < 56 07/6/4 < 07 0/4/4 < 40 0/3/5 < 75 04/5/5 < 87 Results in picocuries per liter Well Water ID MW-63I is part of the Exelon Nuclear existing Radiological Groundwater Protection Program. Current sampling frequency is quarterly.

38 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 03/0/0,930 ± /08/0 5,00 ± /7/0 5,450 ± 68 09//0, ± /4/0,830 ± 30 09/9/0 8,00 ± 63 03/3/0,50 ± 6 0/3/0 4,00 ± /07/0,90 ± 96 0/7/0 3,000 ± /4/0,640 ± 93 /0/0 7,50 ± /0/0,60 ± 0 /3/0 6,00 ± 39 04/7/0 3, ± 348 /5/0 6,060 ± 79 05/05/0,070* 0// 3,650 ± 05//0 7,040* 0/5/,850 ± 9 05/9/0 6,00* 03/5/ 3,490 ± /5/0 5,30* 04/3/ 3,40 ± 5 06/0/0 4,80* 05/0/,680 ± /08/0 6,50* 06/4/,360 ± 90 06/5/0 3,00* 07/3/,050 ± 06//0 0,55 ± 53 08/6/,080 ± 70 06/9/0 6,608 ± /3/ 3,780 ± 45 07/07/0 7,767 ± 47 0//,780 ± 77 07/4/0 3,86 ± 58 /6/ 3,80 ± 85 07//0 3,88 ± 58 /08/,030 ± 30 07/7/0 7,70 ± 480 0/7/,00 ± 38 08/03/0 0,6 ± 536 0/4/ 3,800 ± 4 08//0,38 ± /3/,650 ± 9 08/8/0 0,984 ± 63 04/8/,950 ± 35 08/4/0 40, ±,390 05/6/ 88 ± 80 *BNE split sample results from 05/05/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

39 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 06/0/ < 70 0/0/7 < 38 (continued) 07/03/ < 49 04/03/7 < 05 08/4/ < 83 07/0/7 < 60 09/8/ < 96 0/0/7 < 3 0/0/ 40 ± 38 0/7/8 < 77 /4/ < 5 /05/ < 09 0/08/3 384 ± 80 0//3 6 ± 33 03/05/3 08 ± 38 04/09/3 < 7 07/09/3 < 45 0/08/3 80 ± 66 0/4/4 86 ± 04/09/4 < 09 07/5/4 < 0/3/4 < 4 0/3/5 < 74 04/4/5 < 40 07/5/5 < 4 0/3/5 < 08 0/0/6 < 56 04/05/6 < 00 07/9/6 < 34 0/7/6 < 9 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

40 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 03/0/0 < 69 08/4/0 < 33 03/7/0 < 94 09/8/0 < 46 03/4/0 < 83 0//0 < 03/30/0 < 83 /6/0 < 0 04/06/0 < 85 /4/0 < 07 04/3/0 < 68 0// < 0 04//0 < 67 0/5/ < 8 04/8/0 < 65 03/5/ 93 ± 4 05/05/0 < 74* 04// < 55 05//0 < 74* 05/0/ < 98 05/8/0 < 5* 06/4/ < 76 05/6/0 < 78* 07// < 6 06/0/0 < 8* 08/6/ < 75 06/08/0 < 70* 09/3/ < 9 06/6/0 < 49* 0// < 80 06//0 < 6 /5/ < 78 06/9/0 < 0 /4/ < 0 07/07/0 < 0/7/ < 43 07/3/0 < 469 0/3/ < 75 07//0 < 44 03// < 07/8/0 < 45 04/7/ < 04 08/03/0 < /6/ < 54 08/0/0 < /9/ < 7 08/8/0 < /0/ < 56 *BNE split sample results from 05/05/0 through 06/6/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

41 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 08/5/ < 67 04/04/7 < 5 (continued) 09/8/ < 90 07/0/7 < 57 0/0/ < 75 0/0/7 < 5 /4/ < 7 0/7/8 < 9 /05/ < 7 0/08/3 < 38 0//3 < 0 03/05/3 < 7 04/09/3 < 37 07/09/3 < 57 0/09/3 < 56 0/4/4 < 84 04/09/4 < 09 07/6/4 < 0 0/3/4 < 44 0/3/5 < 70 04/4/5 < 36 07/5/5 < 0/3/5 < 09 0/0/6 < 68 04/05/6 < 04 07/9/6 < 34 0/7/6 < 9 0/0/7 < 85 Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

42 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW-66I 80.0 Cohansey 07//0 < 0/4/5 < 06 07/9/0 < 0//6 < 07 08/05/0 < 8 04/07/6 < 40 08/0/0 < 3 07/0/6 < 7 08/7/0 < 555 0/9/6 < 08/5/0 < 06 0//7 < 0//0 < 04/04/7 < 4 0// < 54 07//7 < 45 04// < 78 0//7 < 04 07/3/ < 88 0/8/8 < 9 0// < 73 04/7/ < 0 07/0/ < 4 0/0/ < 0/09/3 < 03 04/0/3 < 5 07/0/3 < 48 0/09/3 < 70 0/4/4 < 84 04//4 < 68 07/6/4 < 4 0/5/4 < 34 0/4/5 < 74 04/6/5 < 74 07/0/5 < 3 Results in picocuries per liter Well Water ID MW-66I is part of the Exelon Nuclear existing Radiological Groundwater Protection Program. Current sampling frequency is quarterly.

43 BNE Split Results Table : Groundwater Monitoring Wells (continued) MDA NJGWQS MW Cape May 03/0/0 637,40 ±,0 08/5/0 554,000 ± 0,800 03/7/0 78,000 ±,390 08/3/0 570,000 ±,00 03/4/0 787,000 ±,480 09/08/0 577,000 ±, 03/30/0 806,000 ±,50 09/5/0 47,000 ± 8,360 04/06/0 965,000 ±,740 09//0 480,000 ±,90 04/3/0 98,000 ±,450 09/9/0 55,000 ± 0,700 04/0/0 736,000 ±,0 0/06/0 639,000 ±,630 04/8/0 904,000 ±,50 0/4/0 306,000 ± 5,960 05/04/0 70,000* 0/0/0 77,000 ±,990 05//0 893,000* 0/7/0 43,000 ±,380 05/8/0 83,000* /03/0,70,000 ±,400 05/7/0 899,000* /0/0 74,000 ± 3,900 06/03/0 95,000* /7/0 64,000 ±,650 06/09/0 95,000* /3/0 544,000 ± 0,500 06/5/0 94,000* /5/0 676,000 ±,640 06/3/0 688,075 ±,847 0// 83,000 ±,830 06/9/0 630,745 ±,76 0/5/ 759,000 ± 7,360 07/07/0 605,089 ±,698 04/3/ 458,000 ± 8,950 07/4/0 59,45 ±,666 05/0/ 0,000 ± 3,0 07//0 579,843 ±,69 06/4/ 88,000 ± 5,580 07/8/0 579,669 ±,73 07/3/ 00,000 ± 3,890 08/04/0 608,76 ± 3,558 08/6/ 38,000 ± 6,40 08/0/0 563,6 ± 3,438 09/3/ 83,000 ± 3,560 08/7/0 594,373 ± 3,86 0// 0,000 ±,900 *BNE split sample results from 05/04/0 through 06/5/0 were not available due to the closing of Centauri Labs- Alabama facility. For this time period, data reported above are from Exelon s contract lab, Teledyne Brown Engineering. Subsequent samples were analyzed by Eberline Services and GEL Laboratories, both under contract with the NJDEP. Results in picocuries per liter On May, 03, the sampling frequency was reduced from monthly to quarterly

Radon in Florida: Current Status

Radon in Florida: Current Status Radon in Florida: Current Status Clark Eldredge, M.S. Bureau of Environmental Health Florida Department of Health (DOH) April 1, 2015 3/1/2016 1 Current Status The current understanding of radon risk and

More information

NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION. Initial Annual RCRA CCR Unit Inspection Report

NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION. Initial Annual RCRA CCR Unit Inspection Report INITIAL ANNUAL INSPECTION REPORT NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION Initial Annual RCRA CCR Unit Inspection Report PRIMARY BASIN NUMBER 2 SURFACE IMPOUNDMENT Submitted

More information

Radiation Metrics and the Media Confusion Fuels Public Fears

Radiation Metrics and the Media Confusion Fuels Public Fears Radiation Metrics and the Media Confusion Fuels Public Fears Radiation Metrics and the Media Confusion Fuels Public Fears THREE MAIN POINTS Journalists neither know nor CARE about the units by which radiation

More information

THERMAL ENERGY STORAGE TANK DOWN UNDER

THERMAL ENERGY STORAGE TANK DOWN UNDER THERMAL ENERGY STORAGE TANK DOWN UNDER OWNER ENGINEER TANK BUILDER Thermal Energy Storage Tank Walnut, CA Los Angeles area Community College serving over 50,000 students Host to the 2020 U.S. Olympic Track

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: FEBRUARY 12 THROUGH FEBRUARY

More information

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563 Interstate Power and Light Company Burlington Generation Station CCR Surface Impoundment Annual Inspection Report 154.018.012.001 Report issued: December 21, 2016 Hard Hat Services ph: 877-630-7428 hardhatinc.com

More information

Ionizing Radiation. Alpha Particles CHAPTER 1

Ionizing Radiation. Alpha Particles CHAPTER 1 CHAPTER 1 Ionizing Radiation Ionizing radiation is radiation that has sufficient energy to remove electrons from atoms. In this document, it will be referred to simply as radiation. One source of radiation

More information

R A DON IS YOUR FAMILY AT RISK?

R A DON IS YOUR FAMILY AT RISK? A Full Service Radon Testing, Mitigation & Remediation Company providing peace of mind from Radon in homes and businesses throughout Southeastern PA and the Tri-State Area. R A DON IS YOUR FAMILY AT RISK?

More information

TASK 2: ESTABLISH EXERCISE OBJECTIVES AND EXTENT OF PLAY

TASK 2: ESTABLISH EXERCISE OBJECTIVES AND EXTENT OF PLAY Description The RAC Chair establishes a set of objectives for each exercise by negotiations with OROs, RAC members, and the licensee. Responsibility for the demonstration of selected objectives is assigned

More information

Certificate of Completion

Certificate of Completion Love the Lungs You re With 630-325-4443 800-244-4242 Certificate of Completion Every parent or guardian is notified that this facility has performed radon measurements to ensure the health and safety of

More information

4.3.8 Radon Exposure Location and Extent

4.3.8 Radon Exposure Location and Extent 4.3.8 Radon Exposure Radon is a cancer-causing natural radioactive gas that you can't see, smell, or taste. It is a large component of the natural radiation that humans are exposed to and can pose a serious

More information

Radon Action Partnership Packet 2011 Activities for Lung Cancer Awareness Month, Radon Action Week, Radon Action Month, and Throughout the Year

Radon Action Partnership Packet 2011 Activities for Lung Cancer Awareness Month, Radon Action Week, Radon Action Month, and Throughout the Year Radon Action Partnership Packet 2011 Activities for Lung Cancer Awareness Month, Radon Action Week, Radon Action Month, and Throughout the Year Thank you for your interest in being a partner in New Jersey

More information

Hillview Water Company cuts ribbon on $20 million treatment plant project

Hillview Water Company cuts ribbon on $20 million treatment plant project Hillview Water Company cuts ribbon on $20 million treatment plant project by Brian Wilkinson, The Sierra Star Friday, June 2, 2017, 6:06 pm Original Link Participating in the June 2 Hillview Water Company

More information

Thyroid Cancer Investigation Update

Thyroid Cancer Investigation Update Thyroid Cancer Investigation Update Department of Environmental Quality Department of Health and Human Services NCDHHS, NCDEQ Thyroid Cancer Investigation Update March 21, 2019 1 Agenda I. Partner organizations

More information

Part 7: Regulatory Issues and Quality Control. Part 1: Current NRC Regulations Related to Radiation Safety

Part 7: Regulatory Issues and Quality Control. Part 1: Current NRC Regulations Related to Radiation Safety Part 7: Regulatory Issues and Quality Control Part 1: Current NRC Regulations Related to Radiation Safety 1. Secretarial space, hallways, and certain other areas of a department must qualify as an UNRESTRICTED

More information

Radon Action Partnership Packet

Radon Action Partnership Packet Radon Action Partnership Packet Radon Action Partnership Packet Activities for Lung Cancer Awareness Month, Radon Action Week, Radon Action Month, and Throughout the Year Thank you for your interest in

More information

Prepared for: Butte County Department of Water Resource Conservation (BCDWRC) Project No: County of Butte Contract Number: 18050

Prepared for: Butte County Department of Water Resource Conservation (BCDWRC) Project No: County of Butte Contract Number: 18050 10540 White Rock Road, Suite 180 Rancho Cordova, California, 95670 Tel: 916-444-0123 phone Fax: 916-635-8805 fax Prepared for: Butte County Department of Water Resource Conservation (BCDWRC) Project No:

More information

Geismar Site Reviewed: 9/27/16 Effective: 9/27/16 Supersedes: 9/29/14 Preparer: Owner: Approver: EHS Team Member EHS Team Leader LA Hub Director EHS

Geismar Site Reviewed: 9/27/16 Effective: 9/27/16 Supersedes: 9/29/14 Preparer: Owner: Approver: EHS Team Member EHS Team Leader LA Hub Director EHS Procedure No.: EC04 Page: 1 of 12 RECORD OF REVISIONS Date Revision Number Details of Change 09/03 1 Volatile Organic Compound (2.13) definition was added. LDEQ phone numbers were updated. Title V Excursion

More information

Understanding Radon...

Understanding Radon... UNDERSTANDING RADON... AN INTRODUCTION Presented by Matt Loehr, What is Radon? Radon is a radioactive, Noble gas. It does not react with other elements. It s dangerous when it degenerates into its natural

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 11, 2018 EGM-18-001 MEMORANDUM TO: David C. Lew, Acting Regional Administrator, Region I Catherine Haney, Regional Administrator,

More information

Radon test kits also available at:

Radon test kits also available at: Radon test kits also available at: Washoe County Cooperative Extension 4955 Energy Way, Reno 888-723-6610 Incline Village Recreation Center 980 Incline Way, Incline Village 775-832-1300 Carson City Cooperative

More information

MDH GOLD S TANDARD - B UYERS GUIDE

MDH GOLD S TANDARD - B UYERS GUIDE W HAT IS RADON? Radon is a naturally occurring radioactive gas that enters buildings from the surrounding soil. It is colorless, odorless and tasteless. Radon is also the main source of ionizing radiation

More information

CHAPTER 28 RADIATION CONTROL

CHAPTER 28 RADIATION CONTROL CHAPTER 28 RADIATION CONTROL BOARD OF HEALTH ROLE AT A GLANCE Be aware of radioactive materials in the community and request technical assistance in response to incidents involving the possession, handling,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 36508 CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS

More information

Emergency Bridge Stabilization at Mile Watrous Subdivision

Emergency Bridge Stabilization at Mile Watrous Subdivision Emergency Bridge Stabilization at Mile 189.70 Watrous Subdivision Christophe Deniaud, Ph.D., P.Eng. Bridge Engineer, CN 10004-104 Avenue Edmonton, Alberta, Canada T5J 0K2 Tel: (780) 421-6021 Fax: (780)

More information

Letter Health Consultation

Letter Health Consultation Letter Health Consultation OLD FORT FINISHING SITE OLD FORT, NORTH CAROLINA Prepared by the North Carolina Department of Health FEBRUARY 16, 2010 Prepared under a Cooperative Agreement with the U.S. DEPARTMENT

More information

OCCUPATIONAL EXPOSURE IN CANDU NUCLEAR POWER PLANT: INDIVIDUAL DOSIMETRY PROGRAM AT CERNAVODA NPP

OCCUPATIONAL EXPOSURE IN CANDU NUCLEAR POWER PLANT: INDIVIDUAL DOSIMETRY PROGRAM AT CERNAVODA NPP OCCUPATIONAL EXPOSURE IN CANDU NUCLEAR POWER PLANT: INDIVIDUAL DOSIMETRY PROGRAM AT CERNAVODA NPP Catalina Chitu, cchitu@cne.ro, Vasile Simionov, vsimionov@cne.ro CNE Cernavoda NPP, No. 2, Medgidiei Str.

More information

APPENDIX F Freedom of Information Act Documents

APPENDIX F Freedom of Information Act Documents APPENDIX F Freedom of Information Act Documents '81000002' AvFuel Bulk Facility State and Ellsworth Rds. Ann Arbor 48104 Washtenaw Aviation fuel; Kerosene 21 6/3/2004 03S 06E 17 NW SE Interim Response

More information

PFAS at Parafield Airport. November 2018

PFAS at Parafield Airport. November 2018 PFAS at Parafield Airport November 2018 2 Summary PFAS has been detected at low levels in groundwater in isolated monitoring wells set up on the southern and western boundary of Parafield Airport. As a

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7883 CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

Nuclear Radiation Today

Nuclear Radiation Today CHAPTER 10 13 SECTION Nuclear Changes Nuclear Radiation Today KEY IDEAS As you read this section, keep these questions in mind: Where are some common sources of radiation? What are some beneficial uses

More information

Safety & Risk Management Policies and Procedures

Safety & Risk Management Policies and Procedures Safety & Risk Management Policies and Procedures Title: Emergency Eye Wash & Shower Policy Date: August 2013 Rationale: The Occupational Safety and Health Administration (OSHA 29CFR 1910.151) requires

More information

Reducing the Risks From Radon: Information and Interventions A Guide for Health Care Providers. Indoor Air Quality (IAQ)

Reducing the Risks From Radon: Information and Interventions A Guide for Health Care Providers. Indoor Air Quality (IAQ) Reducing the Risks From Radon: Information and Interventions A Guide for Health Care Providers Indoor Air Quality (IAQ) What Is Radon? Radon-222 (radon) is a radioactive gas with a half-life of 3.8 days

More information

Overview Agency For Toxic Substances And Disease Registry

Overview Agency For Toxic Substances And Disease Registry Overview Agency For Toxic Substances And Disease Registry We have made it easy for you to find a PDF Ebooks without any digging. And by having access to our ebooks online or by storing it on your computer,

More information

Eyewash and Safety Showers HM 20 Page 1

Eyewash and Safety Showers HM 20 Page 1 Policy Subject: Safety Showers and Eyewash Effective: 12/01/09 Stations Affected Area/Department: University of Tennessee Reviewed/Revised: 12/15/08 Policy It shall be the policy of the University of Tennessee

More information

in88015.txt at Page 1 of 5 2/25/00

in88015.txt at  Page 1 of 5  2/25/00 in88015.txt at www.nrc.gov Page 1 of 5 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS WASHINGTON, D.C. 20555 NRC INFORMATION NOTICE NO. 88-15: AVAILABILITY

More information

Title of Nomination: Pennsylvania West Nile Virus Surveillance Program Project/System Manager: Eric Conrad Title: Deputy Secretary Agency: PA

Title of Nomination: Pennsylvania West Nile Virus Surveillance Program Project/System Manager: Eric Conrad Title: Deputy Secretary Agency: PA Title of Nomination: Pennsylvania West Nile Virus Surveillance Program Project/System Manager: Eric Conrad Title: Deputy Secretary Agency: PA Department of Environmental Protection Department: PA Department

More information

Contact: or HINKLEY GROUNDWATER REMEDIATION PROJECT

Contact: or HINKLEY GROUNDWATER REMEDIATION PROJECT Remarks by Dr. Ian A. Webster, IRP Manager (from Project Navigator, Ltd.) At Lahontan Regional Water Quality Control Board Meeting, Barstow, CA, January 8, 2014 Contact: iwebster@projectnavigator.com or

More information

Environmental Submersible Pumps

Environmental Submersible Pumps Environmental Submersible Pumps Grundfos 85S Enviro Retrofitted Submersible Pumps These Grundfos submersible pumps are made of stainless steel and retrofitted with PTFE to handle the rigors of contaminated

More information

Updating WENRA Reference Levels for existing reactors in the light of TEPCO Fukushima Dai-ichi accident lessons learned

Updating WENRA Reference Levels for existing reactors in the light of TEPCO Fukushima Dai-ichi accident lessons learned Updating WENRA Reference Levels for existing reactors in the light of TEPCO Fukushima Daiichi accident lessons learned November 2013 Table of Content Updating WENRA Reference Levels for existing reactors

More information

EARTHWORKS OIL AND GAS INDUSTRY CHEMICALS AND HEALTH

EARTHWORKS OIL AND GAS INDUSTRY CHEMICALS AND HEALTH EARTHWORKS OIL AND GAS INDUSTRY CHEMICALS AND HEALTH Precedent Setting Rules on Chemical Disclosure Increasingly, landowners and residents of oil and gas field communities are reporting health impacts

More information

PFAS at the State Level: Case Study from Minnesota

PFAS at the State Level: Case Study from Minnesota PFAS at the State Level: Case Study from Minnesota Presented to the Water Science & Technology Board National Academy of Sciences Ginny Yingling Hydrogeologist May 17, 2018 PFAS in Washington County, MN

More information

Environmental Submersible Pumps

Environmental Submersible Pumps Environmental Submersible Pumps Grundfos 300S Enviro Retrofitted Submersible Pumps These Grundfos submersible pumps are made of stainless steel and retrofitted with PTFE to handle the rigors of contaminated

More information

RADON. Basic Facts, Risks, Health Effects, and Testing

RADON. Basic Facts, Risks, Health Effects, and Testing RADON Basic Facts, Risks, Health Effects, and Testing Basic Facts What is radon and how does it get into your home What is Radon? A naturally occurring radioactive gas that is released in rock, soil, and

More information

Joint Legislative Emergency Management Oversight Committee

Joint Legislative Emergency Management Oversight Committee NC DIVISION OF EMERGENCY MANAGEMENT Joint Legislative Emergency Management Oversight Committee Emergency Management Finances January 16, 2014 NCEM Mission Prepare for: Respond to: Recover from: all hazards

More information

The IAEA Approach to Establishing New Nuclear Power Programmes. Sean Dunlop Nuclear Infrastructure Development Section October 5, 2016

The IAEA Approach to Establishing New Nuclear Power Programmes. Sean Dunlop Nuclear Infrastructure Development Section October 5, 2016 The IAEA Approach to Establishing New Nuclear Power Programmes Sean Dunlop Nuclear Infrastructure Development Section October 5, 2016 Presentation Outline Status of Nuclear Power Development Why Nuclear

More information

OKLAHOMA STATE UNIVERSITY X-RAY MACHINE PROGRAM AND PI HANDBOOK For easy navigation, please use Adobe s bookmark feature.

OKLAHOMA STATE UNIVERSITY X-RAY MACHINE PROGRAM AND PI HANDBOOK For easy navigation, please use Adobe s bookmark feature. OKLAHOMA STATE UNIVERSITY X-RAY MACHINE PROGRAM AND PI HANDBOOK For easy navigation, please use Adobe s bookmark feature. Table of Contents Overview... 2 Section 1: X-ray Program Oversight... 2 1.a: Institutional

More information

Environmental Submersible Pumps

Environmental Submersible Pumps Environmental Submersible Pumps Grundfos 230S Enviro Retrofitted Submersible Pumps These Grundfos submersible pumps are made of stainless steel and retrofitted with PTFE to handle the rigors of contaminated

More information

Radon Detection Specialists, Inc.

Radon Detection Specialists, Inc. Commercial Radon Survey Report Client: Community Consolidated School District 181 Site Address: Hinsdale Middle School 100 S Garfield Survey Date: May 21, 2012 to May 23, 2012 Follow-Up Testing RDS-R-002

More information

B. Stipulated Price (Lump Sum). If Contract is Stipulated Price Contract, payment for Work in this Section is included in total Stipulated Price.

B. Stipulated Price (Lump Sum). If Contract is Stipulated Price Contract, payment for Work in this Section is included in total Stipulated Price. Section 02222 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Abandonment in place of existing sewers, junction structures, manholes, and force mains. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment

More information

Drinking Water Fluoridation Program

Drinking Water Fluoridation Program Exhibit A EASTERN MUNICIPAL WATER DISTRICT Drinking Water Fluoridation Program Jayne Joy, P.E. Director, Environmental & Regulatory Compliance October 22, 2014 www.emwd.org 1 Agenda Background of Fluoridation

More information

EDUCATIONAL INFORMATION

EDUCATIONAL INFORMATION PHARMACEUTICALS AND PERSONAL CARE PRODUCTS (PPCPs) MONITORING PPCPs are a diverse collection of thousands of chemical substances, including prescription and over-the counter therapeutic drugs, veterinary

More information

CITY OF BOISE MERCURY MINIMIZATION. By: Zach Conde

CITY OF BOISE MERCURY MINIMIZATION. By: Zach Conde CITY OF BOISE MERCURY MINIMIZATION By: Zach Conde AREA OF IMPACT Population 223K in the City of Boise 25K In the City of Eagle 12K In the City of Garden City Total of 265K in our area 2 PUBLICLY OWNED

More information

RADIATION SAFETY REFRESHER TRAINING FOR AUGUSTA UNIVERSITY USERS OF RADIOACTIVE MATERIAL

RADIATION SAFETY REFRESHER TRAINING FOR AUGUSTA UNIVERSITY USERS OF RADIOACTIVE MATERIAL RADIATION SAFETY REFRESHER TRAINING FOR AUGUSTA UNIVERSITY USERS OF RADIOACTIVE MATERIAL Environmental Health and Safety Division Course Content Radiation Safety Radiation Dose Limits and Dosimetry Postings

More information

St. Croix River Crossing Bridge Foundation Load Test Project. 1/27/2010 St. Croix River Crossing Bridge - Foundation Load Test Project

St. Croix River Crossing Bridge Foundation Load Test Project. 1/27/2010 St. Croix River Crossing Bridge - Foundation Load Test Project St. Croix River Crossing Bridge Foundation Load Test Project Load Test Sites 4 driven piles Drilled Shaft Site A Site B Load Test Purpose To gather design data for foundation design Allows for more refined

More information

Verification and Validation of Accident Management Guidelines in Indian PHWRs

Verification and Validation of Accident Management Guidelines in Indian PHWRs Verification and Validation of Accident Management Guidelines in Indian PHWRs By RS&A, NPCIL Mumbai, India riteshraj@npcil.co.in IAEA Headquarters, Vienna, Austria, 12 14 December 2016 01/20 NPCIL Nuclear

More information

Table 3-1 Summary of Storm Drain Outfalls

Table 3-1 Summary of Storm Drain Outfalls Table 3-1 Summary of Storm Drain Outfalls Outfall Number Description 005 The drainage area associated with Outfall 005 is to the west of the plant adjacent to and north of Warehouse 2/3, and includes a

More information

Use of Dilute Flowable Backfill for Corrosion Mitigation of Buried Pipe

Use of Dilute Flowable Backfill for Corrosion Mitigation of Buried Pipe Use of Dilute Flowable Backfill for Corrosion Mitigation of Buried Pipe Scott M. Lux Charlie Marsh Tom Carlson U.S. Army Engineer Research and Development Center Report Documentation Page Form Approved

More information

Radon Detection Specialists, Inc. Love the Lungs You re With

Radon Detection Specialists, Inc. Love the Lungs You re With 630-325-4443 800-244-4242 kws@radonresults.com Commercial Radon Survey Report Client: Pleasantdale School District 107 8100 School Street La Grange, Illinois 60525 Survey Date: October 17, 2014 to October

More information

Ionizing Radiation. Michael J. Vala, CHP. Bristol-Myers Squibb

Ionizing Radiation. Michael J. Vala, CHP. Bristol-Myers Squibb Ionizing Radiation Michael J. Vala, CHP Bristol-Myers Squibb michael.vala@bms.com 732-227-5096 2013 American Industrial Hygiene Association, New Jersey Section, Inc. Course Objectives At the end of this

More information

RADON WHERE DOES IT COME FROM?

RADON WHERE DOES IT COME FROM? RADON This is an overview of the subject of radon, as one of the many sources of indoor air pollution. The relative importance of any single source depends on how much of a given pollutant it emits and

More information

Walk for Water. Held by Elmhurst Christian Reformed Church in support of Water Missions International. Sponsorship Opportunities

Walk for Water. Held by Elmhurst Christian Reformed Church in support of Water Missions International. Sponsorship Opportunities Walk for Water Held by Elmhurst Christian Reformed Church in support of Water Missions International Sponsorship Opportunities No one should perish for want of safe water. What is the Walk for Water? The

More information

CHEAC Summary BCC Cannabis Regulations. Distribution, Transportation, Retailers, and Laboratories

CHEAC Summary BCC Cannabis Regulations. Distribution, Transportation, Retailers, and Laboratories CHEAC Summary BCC Cannabis Regulations Distribution, Transportation, Retailers, and Laboratories The Bureau of Cannabis Control (BCC) has released proposed permanent regulations focused on the application,

More information

CARSON CITY FREEWAY. April 9, Nevada Transportation Conference. Jeff Lerud, PE, CPM Senior Project Manager

CARSON CITY FREEWAY. April 9, Nevada Transportation Conference. Jeff Lerud, PE, CPM Senior Project Manager CARSON CITY FREEWAY April 9, 2014 Nevada Transportation Conference Jeff Lerud, PE, CPM Senior Project Manager Presentation Overview Carson Freeway Overview Construction Phases Schedule Budget Questions

More information

ATTACHMENT B8 Incident History

ATTACHMENT B8 Incident History Appendix B GIS/Imagery Outputs ATTACHMENT B8 Incident History Appendix B - GIS/Imagery Outputs Appendix B: Attachment B8 Incident History TABLE OF CONTENTS B.B8-1 INTRODUCTION... 1 B.B8-2 FACT SHEETS...

More information

HUMAN HEALTH AND ECOLOGICAL ASSESSMENT OF THE SIOUX ENERGY CENTER

HUMAN HEALTH AND ECOLOGICAL ASSESSMENT OF THE SIOUX ENERGY CENTER www.haleyaldrich.com REPORT ON HUMAN HEALTH AND ECOLOGICAL ASSESSMENT OF THE SIOUX ENERGY CENTER AMEREN MISSOURI ST. LOUIS, MISSOURI by Haley & Aldrich, Inc. Boston, Massachusetts for Ameren Missouri St.

More information

Radioactive Exposure. Abstract of Article:

Radioactive Exposure. Abstract of Article: Radioactive Exposure Abstract of Article: All ionizing radiations, at sufficiently large exposures, can cause cancer. Many, in carefully controlled exposures, are also used for cancer therapy. Ionizing

More information

PROTECTION IN A NUCLEAR EMERGENCY

PROTECTION IN A NUCLEAR EMERGENCY PROTECTION IN A NUCLEAR EMERGENCY There are 99 nuclear power reactors in the United States producing about one-quarter of the country s electricity. But around each plant is a 50-mile ring that could be

More information

GOOD SCIENCE Vs UNCERTAIN REGULATORY GUIDANCE or HOW CHI/Q AFFECTS NUCLEAR SAFETY

GOOD SCIENCE Vs UNCERTAIN REGULATORY GUIDANCE or HOW CHI/Q AFFECTS NUCLEAR SAFETY GOOD SCIENCE Vs UNCERTAIN REGULATORY GUIDANCE or HOW CHI/Q AFFECTS NUCLEAR SAFETY ABSTRACT For many years in the nuclear industry the calculation of Chi/Q was a dry subject that was limited to meteorologists

More information

Non-Destructive Testing of Drilled Shafts Current Practices and New Methods

Non-Destructive Testing of Drilled Shafts Current Practices and New Methods Non-Destructive Testing of Drilled Shafts Current Practices and New Methods Brent Robinson, Pile Dynamics, Inc. 2012 Pile Dynamics, Inc. Foundation & Geotechnical Engineering Why Test Integrity? Survey

More information

Standardization of Nuclear Component Off-Carrier Processing. ASTM E61 New Orleans, LA January 27, 2015 Ryan Tracy, STERIS Isomedix Services

Standardization of Nuclear Component Off-Carrier Processing. ASTM E61 New Orleans, LA January 27, 2015 Ryan Tracy, STERIS Isomedix Services Standardization of Nuclear Component Off-Carrier Processing ASTM E61 New Orleans, LA January 27, 2015 Ryan Tracy, STERIS Isomedix Services History of Nuclear Component Processing Nuclear components processed

More information

Radon: second leading cause of lung cancer comes from rocks and soil

Radon: second leading cause of lung cancer comes from rocks and soil Radon: second leading cause of lung cancer comes from rocks and soil When naturally occurring uranium breaks down radon gas is produced. It is colourless, odorless, and radioactive. Radon gas also breaks

More information

A mandatory pre-proposal meeting will be held on Tuesday, July 9, 2013 at 1:00 p.m. at the City Hall Multi Purpose Room.

A mandatory pre-proposal meeting will be held on Tuesday, July 9, 2013 at 1:00 p.m. at the City Hall Multi Purpose Room. INVITATION FOR REQUEST FOR PROPOSAL CLOCK TOWER RENOVATIONS GREEN RIVER, WYOMING Notice is hereby given that the City of Green River through the coordination of Green River URA/Main Street Agency (hereafter

More information

Radon Sources. Healthy Indoor Air for America s Homes Radon in the Home Instructional Module

Radon Sources. Healthy Indoor Air for America s Homes Radon in the Home Instructional Module Radon Sources Healthy Indoor Air for America s Homes Radon in the Home Instructional Module Slide #1 What is Radon? Odorless, tasteless gas from natural radioactive decay of uranium and radium Radon decay

More information

Reports Overview. dosimetry services A Mirion Technologies Division. Featuring:

Reports Overview. dosimetry services A Mirion Technologies Division. Featuring: Reports Overview dosimetry services A Mirion Technologies Division Featuring: TABLE OF CONTENTS Overview... 1 Report Definition... 2-3 Occupational Radiation Exposure... 4-5 ALARA Exposure... 6-7 ALARA

More information

Safety Requirements for Long Term Operation or Ageing Aspects and for Design, Construction and Operation of New Nuclear Power Plants

Safety Requirements for Long Term Operation or Ageing Aspects and for Design, Construction and Operation of New Nuclear Power Plants Safety Requirements for Long Term Operation or Ageing Aspects and for Design, Construction and Operation of New Nuclear Power Plants ENSREG Conference, Brussels, 29 June 2015 Dr. Hans Wanner, WENRA Chairman

More information

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A construction camera has been installed to view images of the bridge construction. Images are updated on

More information

Hiroshima / Fukushima: Gender Matters in the Atomic Age

Hiroshima / Fukushima: Gender Matters in the Atomic Age Hiroshima / Fukushima: Gender Matters in the Atomic Age Mary Olson, Nuclear Information and Resource Service (NIRS) www.nirs.org / maryo@nirs.org Presentation posted: http://tinyurl.com/olson2016 Original

More information

Canadian Grain Commission

Canadian Grain Commission Canadian Grain Commission Licensing feed mills Discussion paper February 9, 2015 Ce document est aussi disponible en français. 1 About the Canadian Grain Commission The Canadian Grain Commission is a federal

More information

Environmental Health Information

Environmental Health Information Environmental Health Information Offsite Soils:CMC Heartland Lite Yard Site September 2006 Where is the former CMC Heartland site? The former CMC Heartland site is located in the Hiawatha industrial corridor

More information

Wakefield to Woburn Underground Power Cable Project. Town of Wakefield Board of Selectman Meeting November 13, 2017

Wakefield to Woburn Underground Power Cable Project. Town of Wakefield Board of Selectman Meeting November 13, 2017 Wakefield to Woburn Underground Power Cable Project Town of Wakefield Board of Selectman Meeting November 13, 2017 Project Update, DPW Agreement and Franchise Petition ¾ Provide project update to the Town

More information

Spill and Release Response Procedures

Spill and Release Response Procedures Page #: 1 of 6 Last Reviewed/Update Date: 03/01/16 Spill and Release Response Procedures 1. Purpose / Background This document describes the procedures used by the Massachusetts Institute of Technology

More information

Radiation Safety Guide. Analytical X-Ray Equipment

Radiation Safety Guide. Analytical X-Ray Equipment Radiation Safety Guide Analytical X-Ray Equipment Table of Content Page 1. Radiation 2 A. Radiation Quantities 2 B. Background Radiation 2 C. Biological Effect of Radiation 3 D. Radiation Injury To The

More information

Management of Mining- Impacted Groundwater, Bingham Canyon Mine, Utah, USA

Management of Mining- Impacted Groundwater, Bingham Canyon Mine, Utah, USA Management of Mining- Impacted Groundwater, Bingham Canyon Mine, Utah, USA Kelly Payne Principal Advisor, Closure & Remediation Kennecott Utah Copper LLC This Morning s Discussion Nature of Problem Regulatory

More information

Certification Audit: International Cyanide Management Code - Production Verification Protocol

Certification Audit: International Cyanide Management Code - Production Verification Protocol HINDUSTHAN CHEMICALS COMPANY Certification Audit: International Cyanide Management Code - Production Verification Protocol Summary Audit Findings Report 18-19 February 2014 RMI001_HCC Rev2_20140619 TABLE

More information

Radiobiology Hall 14: Radiologic Terrorism (Completed)

Radiobiology Hall 14: Radiologic Terrorism (Completed) Radiobiology Hall 14: Radiologic Terrorism (Completed) What are a few of the possible scenarios of radiologic terrorism? 1. Detonation of a nuclear major city 2. An attack on a nuclear power station 3.

More information

Pursuant to section 24 of the Nuclear Safety and Control Act, this licence is issued to:

Pursuant to section 24 of the Nuclear Safety and Control Act, this licence is issued to: I) LICENCE NUMBER: II) LICENSEE Pursuant to section 24 of the Nuclear Safety and Control Act, this licence is issued to: Memorial University of Newfoundland 208 Elizabeth Avenue Department of Health and

More information

Southern Exposure 2015 Exercise. July/September, 2015

Southern Exposure 2015 Exercise. July/September, 2015 Southern Exposure 2015 Exercise July/September, 2015 Southern Exposure 2015 (SE15) About 1.5 years of planning. Full Federal Participation Exercise. State of SC volunteered. H.B. Robinson Steam Electric

More information

Adult: > 18 Years ALARA: As low as reasonably achievable ALI:

Adult: > 18 Years ALARA: As low as reasonably achievable ALI: Health Physics Adult: > 18 Years ALARA: As low as reasonably achievable ALI: Annual Limit on Intake. The amount of an isotope that if taken into the body over the course of a year would result in in a

More information

Summary of Patient Release after Radioiodine Therapy Research Review

Summary of Patient Release after Radioiodine Therapy Research Review Summary of Patient Release after Radioiodine Therapy Research Review Introduction This report provides a summary of the Office of Research (RES) staff s efforts to evaluate radiation exposure to members

More information

Amalgam Containment and Recycling: Attaining Zero Mercury Discharge in Dental Office Wastewater

Amalgam Containment and Recycling: Attaining Zero Mercury Discharge in Dental Office Wastewater Amalgam Containment and Recycling: Attaining Zero Mercury Discharge in Dental Office Wastewater Legislation: Regulations Effective December 31, 2013 Amalgam Separator; installation and operation; Requirements.

More information

Quarterly WHS Performance Report

Quarterly WHS Performance Report Facilities and Services Quarterly WHS Performance Report as at 30 May Quarterly WHS Performance Report INTRODUCTION Facilities and Services and Planning and Performance Measurement Divisions are committed

More information

Technical Considerations for NAS Proposed Study of Cancer Risks in Populations Living Near Nuclear Facilities

Technical Considerations for NAS Proposed Study of Cancer Risks in Populations Living Near Nuclear Facilities Technical Considerations for NAS Proposed Study of Cancer Risks in Populations Living Near Nuclear Facilities National Academy of Science July 21, 2011 Irvine, California Electric Power Research Institute

More information

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge Modular Steel Bridges Stark County Fischer Bridge Bottineau County Oak Creek Bridge This John Deere grain hauler was too heavy for the bridge. OOPS! An excavator and tow truck are needed to remove the

More information

State-Aid Bridge News August 2, 2005

State-Aid Bridge News August 2, 2005 State-Aid Bridge News August 2, 2005 Bridge Hydraulic Information The FHWA has been inquiring about our Scour Program. In particular, there are two areas of concern; 1. Are our Scour Action Plans current

More information

Application of Injected ZVI PRB to Control Off-Site Migration of a VOC Plume at a Drycleaner Site in Quebec. Andrzej Przepiora and Simone Smith

Application of Injected ZVI PRB to Control Off-Site Migration of a VOC Plume at a Drycleaner Site in Quebec. Andrzej Przepiora and Simone Smith Application of Injected ZVI PRB to Control Off-Site Migration of a VOC Plume at a Drycleaner Site in Quebec Andrzej Przepiora and Simone Smith RemTech 2016 Oct. 12-14, 2016 Presentation Overview Project

More information

Radionuclides in baby teeth: environmental exposure markers and association with childhood cancer

Radionuclides in baby teeth: environmental exposure markers and association with childhood cancer Radionuclides in baby teeth: environmental exposure markers and association with childhood cancer Sumi Hoshiko, MPH Environmental Health Investigations Branch California Department of Public Health Western

More information

NUCLEAR CONTAMINATION AND HEALTH RISKS FROM THE ENTERGY PALISADES NUCLEAR REACTOR

NUCLEAR CONTAMINATION AND HEALTH RISKS FROM THE ENTERGY PALISADES NUCLEAR REACTOR NUCLEAR CONTAMINATION AND HEALTH RISKS FROM THE ENTERGY PALISADES NUCLEAR REACTOR Radiation and Public Health Project Joseph Mangano, MPH, MBA Executive Director August 19, 2013 TABLE OF CONTENTS Executive

More information

Acid Rock Drainage (ARD) to the Rock Drain and North Fork of Rose Creek, Faro Mine Complex

Acid Rock Drainage (ARD) to the Rock Drain and North Fork of Rose Creek, Faro Mine Complex Acid Rock Drainage (ARD) to the Rock Drain and North Fork of Rose Creek, Faro Mine Complex Paul Ferguson 1, Christoph Wels 1, Dustin Rainey 2, and Carrie Gillis 2 1 Robertson GeoConsultants Inc. Vancouver,

More information

Office of ENERGY Science

Office of ENERGY Science Date: April 29, 2016 U.S. DEPARTMENT OF Office of ENERGY Science SLAC Site Office SLAG National Accelerator Laboratory 2575 Sand Hill Road, MS-.8A Menlo Park, GA 94025 To: Chi Chang Kao, SLAC Laboratory

More information