ATTACHMENT B8 Incident History
|
|
- Jesse Matthew Booth
- 5 years ago
- Views:
Transcription
1 Appendix B GIS/Imagery Outputs ATTACHMENT B8 Incident History
2 Appendix B - GIS/Imagery Outputs Appendix B: Attachment B8 Incident History TABLE OF CONTENTS B.B8-1 INTRODUCTION... 1 B.B8-2 FACT SHEETS... 3 B.B8-3 EVOLUTION OF THE LEFT ABUTMENT ROCKFILL TRENCH List of Tables Table B.B8-1 Summary of incidents at Fundão... 1 List of Figures Figure B.B8-1 Incidents at Fundão shown in plan... 2 Page B.B8-i
3 B.B8-1 INTRODUCTION The list of incidents documented over the life of the Fundão facility are given below in Table B.B8-1 and shown in plan on Figure B.B8-1. Section B.B8-2 includes the fact sheets for each incident. Section B.B8-3 includes documentation on the evolution of the left abutment open channel. Table B.B8-1 Summary of incidents at Fundão Abutment Date Elevation Incident Type - April 13, Piping Right July 9, Main Gallery settlement Left June 26, m Seepage Left November 25, Secondary Gallery sinkhole Left March, m Saturation of slope and ponding of water Left June, m Seepage Left November 15, m Seepage, cracks on slope Left December 26, m Upwelling at El. 860 m, cracks on crest Right July 18, m Seepage Left August 26, Slope movements, saturation Right January 30, m Seepage Left April 16, m Saturation of slope Left May 18, m Saturation of slope Left July 9, m Saturation of slope Page B.B8-1
4 Figure B.B8-1 Incidents at Fundão shown in plan Page B.B8-2
5 B.B8-2 FACT SHEETS April 13, 2009 Piping Incident A leak on the downstream face of Dike 1 above the Principal Foundation Drain developed. A berm was placed immediately on top of the leak, but this did not stop the flow. Tailings deposition was diverted from Fundão, the Dike 1 reservoir drained, and the Principal and Auxiliary Foundation Drains excavated on the upstream and downstream side of Dike 1 for inspection. Both drains were noted to have defects such as erosion of the filter layers and clogging of drain material with fines. Both drains were decommissioned by plugging on the upstream side of Dike 1. The downstream remnants were extended past the Reinforcement Berm placed on the downstream slope of Dike 1. The base drains were replaced with one blanket drain at El. 826 m with 27 Kananet pipes. Old Dike 1A was constructed to allow continued deposition of tailings in Fundão while the El. 826 m blanket drain was constructed. April 13, 2009 site inspection photo [23] showing piping on the downstream face of Dike 1. The Principal Foundation Drain can be seen to the right of the spring. ITRB and Andrew Robertson engineering audit reports and [24]. October, 2010 construction photo showing plugging of the Auxiliary Foundation Drain to the left with the excavated Principal Foundation Drain to the right. None Page B.B8-3
6 July 9, 2010 Main Gallery Settlement The module between Joint 26 and 27 experienced settlement which manifested as a vortex at the surface of the tailings. Tailings deposition in this area was suspended and an inspection showed tailings entering the Gallery through a large crack. New Dike 1A was built to shield this area from tailings deposition while jet grouting was completed on the foundation of the Gallery. July, 2010 site inspection photo [25] showing the vortex that formed at the surface of the tailings above the settlement. Samarco 2010 presentation [27], Samarco 2010 presentation [28], GMAIA 2010 inspection [26] July, 2010 inspection photo from GMAIA [26] showing the inflow of tailings to the Gallery. Joint references differ between sources, the second most common being the leak having occurred between Joints 22 and 23 instead of 26 and 27. This is due to different stationing having been used on drawings over time. Page B.B8-4
7 June 26, 2012 Left Abutment Seepage at El. 845 m Seepage was noted at El. 845 m on the non-setback part of the dike crest at the left abutment. VOGBR attributed this to the damming of water in the Grota da Vale which was upstream of the seepage location. The saturated upstream raise material was excavated and a drain installed. The drain consisted of a geotextile, granular material and coarse rockfill. No formal drain exit was installed until around May, 2015 in the form of a concrete channel that discharged into a buried pipe crossing the left abutment access road to the left abutment concrete channel. Flow records for this drain were not available. Marked up September 2, 2012 Samarco aerial image shown. Photo from VOGBR 2013 report [29]. Samarco weekly reports, VOGBR 2013 report [29] None Page B.B8-5
8 November 25, 2012 Secondary Gallery Sinkhole Sinkhole discovered on the El. 855 m bench at the setback portion of Dike 1 at the left abutment. This sinkhole was located above the Secondary Gallery at Joint 18. An inspection revealed slug discharge of tailings and water from the tailings side of the Secondary Gallery. Joint 18 was grouted internally. November 25, 2012 inspection photo [30] showing the sinkhole. Samarco 2012 inspection [30] December 14, 2012 inspection photo [30] showing evolution of the sinkhole since November 25. None Page B.B8-6
9 March 2013 Seepage at Left Abutment at El. 855 m and Ponding of Surface Water The weekly report from the week of March 25, 2013 notes a saturated region at the left abutment. After a review of aerial images, part of the reason for saturation and ponding could be lack of surface drainage control on the left abutment roads above the dam. Topography shows this area to be ~El. 855 m. A buried drain (Drain 1) was put in, leading to a geotextile-wrapped rockfill trench (Drain 2) on the left setback. The buried drain was an inverted trapezoid, geotextile-wrapped rockfill drain. The geotextile-wrapped rockfill trench (Drain 2) eventually became a large open channel on the setback platform as the dam was raised around it. Details on the evolution of this drain are given on the last fact sheet of this section. Weekly report from week of March 25, March 2, 2013 Samarco aerial image showing the Secondary Gallery sinkhole to the left and a region of saturation and ponding to the right at the dam s contact with the left abutment. Weekly reports None Page B.B8-7
10 June 2013 Seepage at Left Abutment at El. 855 m There are a number of conflicting records on the elevation and date of this seepage incident: Source Date of Incident Elevation of Incident ITRB June, m Samarco [31] June, m August, m VOGBR [13] August, m There is no mention of seepage events in the June or August, 2013 weekly reports, but drain construction activities were mentioned in the June reports. This drain (likely Drain 1 from March, 2013) was connected to the open channel wrapped in geotextile running down the left abutment (likely Drain 2). No signs of this activity can be seen in the August, 2013 aerial image. It is possible that the incident took place during end of buried drain (Drain 1) construction in June. The drains that were already going to be executed as part of the March, 2013 saturation event were used to address this new seepage event. No clear description or photos of this drain are available except from weekly reports that seem to show: 1 m layer of sand being placed upstream of the buried drain (Drain 1); construction was started in April, The sand being connected to the rockfill trench (Drain 2). Construction photo from June 17-23, 2013 weekly report showing the geotextile and sand placement, with the beginnings of the rockfill trench to the left. Construction photo from June 17-23, 2013 weekly report showing the beginnings of the rockfill trench. Page B.B8-8
11 June 2013 Seepage at Left Abutment at El. 855 m Document from Samarco [31] showing details of the November 2013 seepage event and mention of the June 2013 incident. Document from Samarco [31] showing details of the drains constructed at the left abutment to address the November and August, 2013 incident. The August, 2013 incident was referred to in a previous slide as the June, 2013 incident. ITRB, weekly reports, Samarco 2013 document [31], VOGBR document [13] Dates and elevation as listed in the section. Page B.B8-9
12 June 2013 Seepage at Left Abutment at El. 855 m November 15, 2013 Left Abutment Seepage and Cracks at El. 860 m There are a number of conflicting records on the elevation and date of this seepage incident: Source Date of Incident Elevation of Incident ITRB November, m Samarco [31] Between November 15 and 17, m VOGBR [13] November, m The slope face was saturated and localized slumping was noted. Longitudinal cracks appeared. Cracks at higher elevations were dry. An inverted drain (Drain 3) was placed and connected to the one placed at El. 855 m (Drain 1) which was connected to the rockfill trench (Drain 2). Document from Samarco [31] showing details of the November 2013 seepage event and mention of the June, 2013 incident. Samarco 2013 document [31], VOGBR 2013 inspection [13] Document from Samarco [31] showing details of the saturated and slumped slope in November, Dates and elevation as listed in the section. Page B.B8-10
13 December 26, 2013 Left Abutment Upwelling at El. 860 m and Cracks on Crest Upwelling incident noted in December 23-30, 2013 Samarco weekly report and confirmed to be observed on December 26, 2013 in December 2013 Samarco monthly geotechnical inspection report. Cracks noted in December 30, 2013 to January 5, 2014 Samarco weekly report and confirmed to be observed on December 26, 2013 in December 2013 Samarco monthly geotechnical inspection report. Upwelling elevation inconsistencies between sources: Weekly report states El. 855 m. Aerial image taken by drone on December 27, 2013 shows sand placement at ~El. 858 m. For consistency with naming convention for other seepage incidents, this will be referred to as the El. 860 m upwelling since it is on the downstream face of the El. 860 m bench. 1 m of sand was placed on the slope face to retain fines. Setback was raised following the sand placement. Cracks were noted to be approximately 10 mm wide and 60 m long along the crest. Photo from December 23-29, 2013 weekly report showing placement of sand over area of upwelling. Photo from December 23-29, 2013 weekly report showing placement of sand over area of upwelling. Page B.B8-11
14 December 26, 2013 Left Abutment Upwelling at El. 860 m and Cracks on Crest December 30, 2013 to January 1, 2014 weekly report describing temporary cessation of operation at the left abutment due to cracks. Weekly reports, geotechnical inspection report December 26, 2013 inspection photo from Samarco geotechnical inspection report showing a crack on the crest. None Page B.B8-12
15 July 18, 2014 Right Abutment Seepage at El. 855 m There are a number of conflicting records on the elevation and date of this seepage incident: Source Date of Incident Elevation of Incident ITRB Not stated 855 m Samarco [14] July 18, m VOGBR [13] Late m The incident was discussed in detail by Samarco [14] which concluded: The interface between the soil backfill and sand tailings as part of the Auxiliary Spillway construction works has become a preferred seepage path. The closest piezometer to the seepage incident is approximately 50 m away on Section AA. This piezometer (16LI011) showed the water level to be below the point of seepage. The saturated slope was excavated and replaced with a sand and gravel drain which can be seen in the drone aerial image taken on August 4, During a site visit in April 2015, VOGBR noted saturation of the bench downstream of the drain and recommended replacing the drain with one of VOGBR s design. This was done in May, Flow from this drain was regularly monitored and reported in instrumentation and weekly reports. July, 2014 inspection photo showing seepage outbreak on the downstream face of Dike 1. Location plan showing the seepage outbreak in relation to the earthworks extent for the Auxiliary Spillway. Page B.B8-13
16 July 18, 2014 Right Abutment Seepage at El. 855 m Sand tailings Backfill July, 2014 inspection photo showing the sand and gravel drain placed. Samarco 2014 inspection [14], VOGBR [13] Marked up photo from the Auxiliary Spillway construction period showing the interface between the backfill and sand tailings. Dates and elevation as listed in the section. Page B.B8-14
17 August 26, 2014 Left Abutment Setback Slope Movement At 6:00 AM on August 27, 2014, cracks were observed on the upstream beach, dam crest and downstream slope of the setback. The cracks showed differential thicknesses, some on crest ~6 cm, reaching up to 3x as thick on the upstream bench. Uplift at the toe of the El. 865 m bench was noted by the ITRB. Water was not observed on the upstream beach and crest, only normal saturation of sand tailings. At the toe of the El. 865 m bench, saturation was noted. Samarco designed and implemented a Reinforcement Berm. Piezometers and survey monuments were also installed. September 2014 inspection photo showing saturation of material at the toe of the El 865 m bench. Location plan showing the mapped cracks. Samarco 2014 inspection [32], Samarco surveys [33, 34] None Page B.B8-15
18 January 30, 2015 Right Abutment Seepage at El. 860 m There are a number of conflicting records on the elevation and date of this seepage incident: Source Date of Incident Elevation of Incident ITRB Not stated 855 m Samarco [35] January 30, m VOGBR [13] January 30, m According to topography, this incident occurred on the downstream face of the El. 860 m bench at El 858 m. This is one bench above the incident that occurred in July, Incident discussed in detail by Samarco [35] which concluded: The interface between the soil backfill and sand tailings as part of the Auxiliary Spillway construction works has become a preferred seepage path. The closest piezometer to the seepage incident is approximately 50 m away on Section AA. This piezometer (16LI010) showed the water level to be below the point of seepage. The saturated slope was excavated and replaced with a sand and gravel drain. During a site visit in April, 2015, VOGBR recommended replacing the drain with one of VOGBR s design. This was done in May, Flow from this drain was regularly monitored and reported in instrumentation and weekly reports. Location plan showing the seepage outbreak in relation to the earthworks extent for the Auxiliary Spillway. Samarco 2015 [35], VOGBR 2015 inspection [13], ITRB report January, 2015 construction photo showing the beginning of stripping for placement of drain material on the slope [35]. Dates and elevations as noted in Section. Page B.B8-16
19 April 16, 2015 Saturation at Left Abutment, El. 867 m Saturation above and below the El. 860 m blanket drain was noted by Samarco in the monthly geotechnical report. A photograph shows saturation at El. 867 m just above the on-going construction of the El. 860 m blanket drain. Drone aerial images from February 27, 2015 to April 24, 2015 show saturation at the location of the monthly report photograph. Photo from monthly geotechnical report showing saturation at the toe of the slope above the El. 860 m blanket drain. February 27, 2015 aerial image. March 20, 2015 aerial image. Samarco 2015 inspection [36] April 24, 2015 aerial image. None Page B.B8-17
20 May 18, 2015 Saturation at Left Abutment, El. 820 m Saturation of slope was noted by Samarco in the monthly geotechnical inspection report. Marked up May, 2015 inspection photo from the Samarco geotechnical inspection report showing saturation of the slope left of the concrete channel. Samarco 2015 inspection [36] None Page B.B8-18
21 July 9, 2015 Saturation at Left Abutment, El. 820 m Saturation of the slope was noted by VOGBR during the July, 2015 site visit as part of Regular Safety Inspections. This appears to be the same saturation that was noted by Samarco in May, July, 2015 inspection photo from VOGBR showing saturated slope between El. 830 m and El. 820 m bench. VOGBR 2015 inspection [13] None Page B.B8-19
22 B.B8-3 EVOLUTION OF THE LEFT ABUTMENT ROCKFILL TRENCH Evolution of the Left Abutment Rockfill Trench (Drain 2) The rockfill trench (Drain 2) was initially put in as part of June, 2013 seepage incident and receives water from the El. 855 m buried drain (Drain 1) and the El. 860 m drain (Drain 3 installed in November, 2013). Water from this drain was permitted to sheet flow across the setback plateau and access road to Grota da Vale. As the setback was raised around this trench, it became a large open channel lined with geotextile. This can be seen in the drone aerial image taken on December 27, By January 29, 2015, the aerial image shows the open channel having been buried with a light grey material. It is unclear whether this is drain rock or dry tailings sand. During a May interview with a Samarco employee, the buried open channel was recounted to have an outlet in the form of a buried pipe. The alignment of this pipe is unknown to the Panel, but based on site photographs and aerial images, it is likely at the exposed toe of the El. 860 m blanket drain. Ponded water is consistently noted at this location. VOGBR completed a drain design in May, 2014 to convey water from the buried El. 855 m drain (Drain 1) to the left abutment concrete channel. No records were found of this design having been implemented. However, as part of the design process, VOGBR conducted a site visit and took photographs of the open channel as it existed in March, Open channel lined with geotextile Marked up drone aerial image taken December 27, Marked up drone aerial image taken January 29, Page B.B8-20
23 Evolution of the Left Abutment Rockfill Trench (Drain 2) Marked up drone aerial image taken May 27, Marked up drone aerial image taken June 22, March 27, 2014 site visit photo from VOGBR showing the open channel looking down the slope of the dam toward the plateau of the left setback. March 27, 2014 site visit photo from VOGBR showing the open channel looking upslope towards the dam crest. The erosion on the setback plateau can be seen to the right of the photo. Page B.B8-21
24 Evolution of the Left Abutment Rockfill Trench (Drain 2) July 10, 2014 site visit photo from VOGBR showing a pipe conveying water from the open channel through the access road berm. The water then sheet flows across the access road to Grota da Vale which is to the right of the photo. VOGBR 2014 [11] January 16, 2015 construction photo showing the buried open channel with light grey material. None Page B.B8-22
APPENDIX H. Limit Equilibrium Analysis of Dike 1 Abutments Prior to Failure
APPENDIX H Limit Equilibrium Analysis of Dike 1 Abutments August 25, 2016 Appendix H Limit Equilibrium Analysis of Dike 1 Abutments TABLE OF CONTENTS H1 INTRODUCTION... 1 H2 ENGINEERING PROPERTIES OF THE
More informationSTRUCTURAL STABILITY ASSESSMENT
STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Fly Ash Pond Big Sandy Plant Louisa, Kentucky October, 2016 Prepared for: Kentucky Power Big Sandy Plant Louisa, Kentucky Prepared by: American Electric Power
More informationThe short path seepage area is between the dam embankment and the bend in the existing drainage tunnel. This area is highlighted in red on the
2 The short path seepage area is between the dam embankment and the bend in the existing drainage tunnel. This area is highlighted in red on the picture in the top left hand corner. Water in this pathway
More informationGrade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway
Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Jeff Sizemore, P.E. Geotechnical Design Support Engineer SCDOT Ed Tavera, P.E. Principal Geotechnical Engineer Geoengineers
More informationAppendix B. Shallow Foundations Report
12/10/2013 GEOTECHNICAL MANUAL Appendix B. Shallow Foundations Report PLEASE NOTE A sample foundations report is included here for reference. It is provided as an example of content, format, and organization
More informationInspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin.
Inspection Report River Falls Hydroelectric Project FERC Project No. P-10489 Junction Falls Dam River Falls, Wisconsin Prepared for: River Falls Municipal Utilities River Falls, Wisconsin December 2009
More informationThe Fontenelle Dam Incident: The Investigation, Likely Causes, and Lessons (Eventually) Learned 8/3/11
The Fontenelle Dam Incident: The Investigation, Likely Causes, and Lessons (Eventually) Learned 8/3/11 Presented to: Association of State Dam Safety Officials, Annual Conference, Washington DC, September
More information\\H\15\ PH9 Inspection Photos
SHOP SLIDE Photo 1. at cracking across the footpath at the end of the Hwy 2 EB to Hwy 684 SB off ramp at the 99 Ave. intersection. Drop in asphalt trail (background) has worsened since 2013 and is now
More informationMemorandum AECOM tel fax ABN
AECOM Australia Pty Ltd Level 10, Tower Two 727 Collins Street Melbourne VIC 3008 Australia www.aecom.com +61 3 9653 1234 tel +61 3 9654 7117 fax ABN 20 093 846 925 Memorandum To David Hitchcock Page 1
More informationNORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION. Initial Annual RCRA CCR Unit Inspection Report
INITIAL ANNUAL INSPECTION REPORT NORTHERN INDIANA PUBLIC SERVICE COMPANY MICHIGAN CITY GENERATING STATION Initial Annual RCRA CCR Unit Inspection Report PRIMARY BASIN NUMBER 2 SURFACE IMPOUNDMENT Submitted
More informationDefra RESEARCH CONTRACT RESERVOIR SAFETY ADVICE TASK B : EARLY DETECTION OF INTERNAL EROSION. FEASIBILITY REPORT Volume 2 of 2 : Appendices
Defra RESEARCH CONTRACT RESERVOIR SAFETY ADVICE TASK B : EARLY DETECTION OF INTERNAL EROSION FEASIBILITY REPORT Volume 2 of 2 : Appendices Ref. XU0248/ 201 Revision A02 November 2003 Hill Park Court Springfield
More informationSEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN
SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN 7-1.0 INTRODUCTION 7-2.0 RIGID PAVEMENT DESIGN 7-2.01 Cross Sections 7-2.02 Ramps and Loops with Storage Area 7-2.03 Major Forks, Branch
More informationUsing the sharp-crested weir formula the outflow was:
Date: 2009 July 16 11:00 AM 14 Island Lake Dam Inspection Report Persons Present: Bryon Keene, P.Eng. Harry Stinson Brett Dark (14 Island Lake Association) Peter Peart (14 Island Lake Association) The
More informationHard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563
Interstate Power and Light Company Burlington Generation Station CCR Surface Impoundment Annual Inspection Report 154.018.012.001 Report issued: December 21, 2016 Hard Hat Services ph: 877-630-7428 hardhatinc.com
More informationNovel treatment technique
Final conference Zagreb, 27 th April 2018 TREAT How to choose the optimal rehabilitation technique Novel treatment technique Stanislav Lenart Slovenian National Building and Civil Engineering Institute
More informationBengt H. Fellenius. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot. Amsterdam.
Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot Bengt H. Fellenius Amsterdam May 27, 216 Fellenius, B.H. and Nguyen, M.H., 213. Wick Drains and Piling for
More informationHanson Dam s mysteries solved
Hanson Dam s mysteries solved Hanson: Earth dams are expected to leak MIKE ARCHBOLD; STAFF WRITER STAFF WRITER LAST UPDATED: APRIL 27TH, 2011 06:34 AM (PDT) It had the makings of a doomsday scenario. Two
More information3/18/03 CE Keith P. Brabant, P.E.
1 Keith P. Brabant, P.E. 2 SELECT GRANULAR BACKFILL 3 4 Maximum of 15% fines Maximum size of 4 inches Free-draining, frictional, and durable Graduation limits referenced by AASHTO T-27 5 US Sieve Size
More informationSTONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39
SITE NUMBER AND NAME: NC 52 Pembina River Bridge LEGAL DESCRIPTION: SE 1-50-9-W5M STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 NAD 83 COORDINATES:
More informationFINAL COVER SYSTEM SURFACE WATER MANAGEMENT SYSTEM DESIGN
DRAFT ONONDAGA LAKE SEDIMENT CONSOLIDATION AREA CIVIL & GEOTECHNICAL FINAL DESIGN BBAPPENDIX K. FINAL COVER SYSTEM SURFACE WATER MANAGEMENT SYSTEM DESIGN p:\honeywell -syr\ - lake detail design\ reports\.
More informationDrainage and Detention Report. for. Charity Auto Sales. located at: East 116 th Street North Collinsville, OK Revised August 22, 2016
Drainage and Detention Report for Charity Auto Sales located at: 9 East 6 th Street North Collinsville, OK 742 Revised August 22, 26 Olsson Associates, Inc. 9 N. Birch Street, Suite 2 Owasso, OK 74 (98)
More informationLANDFILL STABILITY ISSUES
LANDFILL STABILITY ISSUES 1 2006 APWA International Congress & Exposition Kansas City, Missouri Timothy D. Stark, Ph.D., P.E. University of Illinois at Urbana-Champaign OUTLINE 2 Current Situation Liner
More informationAPPENDIX A INTEGRAL ABUTMENTS
APPENDIX A INTEGRAL ABUTMENTS Appendix A Guidelines for Design of Integral Abutments Rev. 1 - September, 2007 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT
More informationThe compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.
FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: FEBRUARY 12 THROUGH FEBRUARY
More informationStormwater Mitigation Worksheet
Planning & Development Dept. Infrastructure Division P.O. Box 11706, or 155 Johnston Street Rock Hill, South Carolina 29731 1706 Phone: 803 329 5515 FAX: 803 329 7228 www.cityofrockhill.com Date Received:
More informationFlume Installation Instructions
Flume Installation Instructions To ensure a successful installation, it is important to keep the following points in mind: 1) There should be no bend, dips, elbows, or flow junction immediately upstream
More informationAdam D. James, P.E., CFM Eric Y. Chow, P.E., CFM. NRCS DAM RISK ASSESSMENTS Sites 6 and 8 Eddy and Chaves Counties, New Mexico
Adam D. James, P.E., CFM Eric Y. Chow, P.E., CFM NRCS DAM RISK ASSESSMENTS Sites 6 and 8 Eddy and Chaves Counties, New Mexico Cottonwood Walnut Creek watershed, drains east to the Pecos River Purpose to
More informationPRELIMINARY GEOTECHNICAL DESIGN
PNCC Manawatu River Pedestrian/ Cycle Bridge PRELIMINARY GEOTECHNICAL DESIGN 1 Introduction Opus has been commissioned by the Palmerston North City Council (PNCC) to prepare a Detailed Business Case (DBC)
More informationAssessing potential cracking zones in embankment dams
Southern Cross University epublications@scu 23rd Australasian Conference on the Mechanics of Structures and Materials 2014 Assessing potential cracking zones in embankment dams Ke He University of New
More informationUrban Drainage and Flood Control District. Goldsmith Iliff Pond E-19 Survey
Urban Drainage and Flood Control District Goldsmith Gulch @ Iliff Pond E-19 Survey GOLDSMITH GULCH @ ILIFF ALERT ID: 653/654 LID: ILFC2 Prepared by: HDR Engineering, Inc. 303 E 17 th Ave. Suite 700 Denver
More informationCHAPTER 11 APPENDIX D
OFFICE OF STRUCTURES STRUCTURE HYDROLOGY AND HYDRAULICS DIVISION CHAPTER 11 APPENDIX D SCOUR COUNTERMEASURES FOR PIERS AND ABUTMENTS MAY 2015 Maryland SHA Office of Structures, Chapter 11, Appendix D May2015Page
More informationWick Drains and Piling for Cai Mep Container Port, Vietnam. Bengt H. Fellenius. Sower's Lecture Atlanta May 8, 2012
Wick Drains and Piling for Cai Mep Container Port, Vietnam Bengt H. Fellenius Sower's Lecture Atlanta May 8, 2012 1 The Mekong Saigon/HoChiMinhCity The General Area 3 Thi Vai Port Cai Mep Port 4 Artist
More informationEmergency Bridge Stabilization at Mile Watrous Subdivision
Emergency Bridge Stabilization at Mile 189.70 Watrous Subdivision Christophe Deniaud, Ph.D., P.Eng. Bridge Engineer, CN 10004-104 Avenue Edmonton, Alberta, Canada T5J 0K2 Tel: (780) 421-6021 Fax: (780)
More informationEAH 422 ADVANCED WATER RESOURCES ENGINEERING
EAH 422 ADVANCED WATER RESOURCES ENGINEERING Bridge Hydraulics Prof. Aminuddin Ab. Ghani References The Art And Science Of River Engineering Bridge Failure Pier scour Pier scour Pier scour Bridge Failure
More informationGeosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri
Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri Adams et al. (2012), FHWA Geosynthetic Reinforced Soil Integrated Bridge System Interim Implementation
More informationSEEPAGE ANALYSIS OF TWO CASE HISTORIES OF PIPING INDUCED BY EXCAVATIONS IN COHESIONLESS SOILS
ICCI2004, The First International Conference on Construction IT, Beijing, CHINA, August 12 th - 14 th SEEPAGE ANALYSIS OF TWO CASE HISTORIES OF PIPING INDUCED BY EXCAVATIONS IN COHESIONLESS SOILS Cai,
More informationAppendix C Guidelines for Design of Integral Abutments March 3, 2003
These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT s and the UK Highways Agency. They provide guidance and outline the issues that need to be considered and should
More informationPrepared for: Butte County Department of Water Resource Conservation (BCDWRC) Project No: County of Butte Contract Number: 18050
10540 White Rock Road, Suite 180 Rancho Cordova, California, 95670 Tel: 916-444-0123 phone Fax: 916-635-8805 fax Prepared for: Butte County Department of Water Resource Conservation (BCDWRC) Project No:
More informationShifting the Canning Bus Bridge Sideways
Shifting the Canning Bus Bridge Sideways Ros MacKinlay Design Engineer, Wyche Consulting SYNOPSIS The Perth Mandurah railway proposed in 2002 required the replacement of an existing Kwinana Freeway bus
More informationGeotechnical Issues Associated With the Design and Construction of the Middle River Bridge
Missouri University of Science and Technology Scholars' Mine International Conference on Case Histories in Geotechnical Engineering (2013) - Seventh International Conference on Case Histories in Geotechnical
More informationReport on Visit to North Eastern October By Oliver Hawes (Geotechnical Engineer)
Report on Visit to North Eastern October 2009 By Oliver Hawes (Geotechnical Engineer) Introduction I was invited to visit Northeastern India by Shantanoo Bhattacharyya of the Eastern Vetiver Network India
More informationB. Stipulated Price (Lump Sum). If Contract is Stipulated Price Contract, payment for Work in this Section is included in total Stipulated Price.
Section 02222 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Abandonment in place of existing sewers, junction structures, manholes, and force mains. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment
More informationUNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7883 CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,
More informationClay Sewer Pipe-Joint Infiltration Leak-Rate Testing
Clay Sewer Pipe-Joint Infiltration Leak-Rate Testing 1. ABSTRACT While numbers of small to large older cities are undertaking repairs and maintenance, several other newer cities are planning on installing
More informationMICHIGAN STATE UNIVERSITY CONSTRUCTION STANDARDS
PAGE 312323-1 SECTION 312323 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS 1.2 SUMMARY A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationFLOWABLE FILL Controlled Low-Strength Materials
FLOWABLE FILL FLOWABLE FILL Controlled Low-Strength Materials Unshrinkable Fill Controlled Density Fill Flowable Mortar Flowable Fly Ash Fly Ash Slurry Plastic Soil Cement Soil Cement Slurry What is Flowable
More informationPEAK FLOW REDUCTION OPPORTUNITIES IN THE CASCADE CREEK TRIBUTARIES. Final Report. Olmsted County, MN November 2008 Project Number:
PEAK FLOW REDUCTION OPPORTUNITIES IN THE CASCADE CREEK TRIBUTARIES Final Report Olmsted County, MN November 28 Project Number: 362-614 COUNTY OF OLMSTED PEAK FLOW REDUCTION OPPORTUNITIES IN THE CASCADE
More informationGeosynthetic-reinforced soil bridge abutments
Geosynthetic-reinforced soil bridge abutments Measuring the performance of geosynthetic reinforcement in a Colorado bridge structure. By Jorge G. Zornberg, Naser Abu-Hejleh, and Trever Wang The technology
More informationL. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015
Canterbury Bridge Group Ferrymead Bridge L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015 Presenter: Lloyd Greenfield Senior
More informationApplication of pile underpinning technology on shield machine crossing through pile foundations of road bridge
Geotechnical Aspects of Underground Construction in Soft Ground Ng, Huang & Liu (eds) 2009 Taylor & Francis Group, London, ISBN 978-0-415-48475-6 Application of pile underpinning technology on shield machine
More informationMatrix (Partially Grouted) Riprap Lab Flume Study
Matrix (Partially Grouted) Riprap Lab Flume Study Jeffrey D. G. Marr, Principal Investigator St. Anthony Falls Laboratory University of Minnesota April 2015 Research Project Final Report 2015-15 To request
More informationBank Erosion and Bridge Scour
JULY 2017 NCHRP PRACTICE-READY SOLUTIONS FOR Bank Erosion and Bridge Scour NCHRP NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM RESEARCH TOPIC HIGHLIGHTS INTRODUCTION Bank Erosion and Bridge Scour: NCHRP
More informationFEASIBILITY REPORT ENVIRONMENTAL IMPACT STATEMENT COASTAL STORM DAMAGE REDUCTION PROJECT
FEASIBILITY REPORT AND ENVIRONMENTAL IMPACT STATEMENT COASTAL STORM DAMAGE REDUCTION PROJECT SURF CITY AND NORTH TOPSAIL BEACH NORTH CAROLINA Appendix E Sand Compatibility Analysis Appendix E: Sand Compatibility
More informationUse of Dilute Flowable Backfill for Corrosion Mitigation of Buried Pipe
Use of Dilute Flowable Backfill for Corrosion Mitigation of Buried Pipe Scott M. Lux Charlie Marsh Tom Carlson U.S. Army Engineer Research and Development Center Report Documentation Page Form Approved
More informationCalaveras Dam Replacement Project. Third Party Due-Diligence Review Investigations and Design of the Left Abutment
San Francisco Public Utilities Commission Calaveras Dam Replacement Project 11 Third Party Due-Diligence Review Investigations and Design of the Left Abutment Presented By: Steve Verigin Senior Vice President,
More informationRetrofit to improve earthquake performance of bridge abutment slopes
Proceedings of the Ninth Pacific Conference on Earthquake Engineering Building an Earthquake-Resilient Society 14-16 April, 2011, Auckland, New Zealand Retrofit to improve earthquake performance of bridge
More informationAcid Rock Drainage (ARD) to the Rock Drain and North Fork of Rose Creek, Faro Mine Complex
Acid Rock Drainage (ARD) to the Rock Drain and North Fork of Rose Creek, Faro Mine Complex Paul Ferguson 1, Christoph Wels 1, Dustin Rainey 2, and Carrie Gillis 2 1 Robertson GeoConsultants Inc. Vancouver,
More informationThe detection limit for tritium is 300 pci/l
New Jersey Department of Environmental Protection - Bureau of Nuclear Engineering (BNE) Investigation of Found in Onsite Vault Background and Installation of Groundwater Monitoring Wells In April of 009,
More informationUNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 89188 7 th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER OCTOBER 2, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,
More informationUNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 4992 CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,
More informationIntroduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017
Introduction Substructure Inspection and Rating That portion of the bridge located below the bearings Abutments Piers Rated separately Purpose is to: Receive the loads from the superstructure Transfer
More informationDesign of Dingley Bypass Integral Bridges
Design of Dingley Bypass Integral Bridges Dr. Kabir Patoary Principal Engineer Bridges GHD Elder St South Underpass Tekla Model Presentation Outline 1. Overview of Dingley Bypass 2. Design of Integral
More informationTown of Sherborn - Board of Health Regulations I SEWAGE DISPOSAL
I SEWAGE DISPOSAL INTRODUCTION These Regulations are adopted in accordance with Title 1, Regulation 2 of the State Environmental Code and Article 1 of the State Sanitary Code and are intended to supplement
More informationFour simply supported steel plate girders (appear to be an old railcar).
BRIDGE INSPECTION BRIDGE NO./NAME N4-005: Akolkolex Crawford FSR (19.0 km) Inspection Date: September 22 nd, 2012 Inspected By: M. Hanson, R. Veitch Year Built: 1982 Number of Spans: 1 Span Lengths: Superstructure
More informationDraft. Not yet Approved. Natural Waterways 2012
Natural Waterways 2012 3.1 General 1 3 5 3.1.1 Scope (2012) 1 3 5 3.1.2 Importance (1992) R(2012) 1 3 5 3.2 Hydrologic Capacity of Waterway Openings1 1 3 5 3.2.1 General (2012) 1 3 5 3.2.2 Drainage Basin
More informationPrepared for Friends of the Corte Madera Creek Watershed. By Ross Taylor and Associates
CATALOG OF STREAM CROSSINGS WITH CULVERTS AND OTHER MANMADE IMPEDIMENTS TO FISH PASSAGE LOCATED ON ANADROMOUS STREAM REACHES WITHIN FAIRFAX CREEK, CORTE MADERA CREEK WATERSHED, MARIN COUNTY, CA. Prepared
More information2011 BRIDGE INSPECTION REPORT
2011 BRIDGE INSPECTION REPORT BYRD PARK PUMP STATION BRIDGE OVER KANAWHA CANAL April 2011 FINAL December 2011 Looking - from Abutment B to Abutment A Prepared by: WHITMAN, REQUARDT, & ASSOCIATES, LLP 9030
More informationStatus of Implementation of Approved Rehabilitation Plans: ARA Sites in Halton Region ( )
ttachment #5 to LPS96-15 Status of Implementation of pproved Rehabilitation Plans: R Sites in Halton Region (2012-2014) Site Name, R Rehabilitation/End-use Description Status of Implementation of pproved
More informationStantec Consulting Ltd Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) Fax: (905)
Filed: 2018-07-04, EB-2018-0108, Exhibit B, Tab 1, Schedule 1, Attachment 4, Page 1 of 10 Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889
More informationAhmed Mongi, M.S., P.E. Engineering Division
1 Ahmed Mongi, M.S., P.E. Engineering Division 2 Honey Creek Bridge Completed in 2006 at a cost of $2.6 Million Precast pier caps and abutments. 3 Honey Creek Bridge Bridge closed for 60 days Simple span
More informationTechnology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.
Bridge Applications Technology The Reinforced Earth Company (RECo) offers a variety of bridge abutment and bridge crossing solutions, each are based on project specific requirements. Bridge abutments are
More informationRTKC- East Abutment Extension Individual Permit Application November 15, Figure 1. East Abutment Extension General Vicinity Map
RTKC- East Abutment Extension November 15, 2016 2.1. Figure 1. East Abutment Extension General Vicinity Map WP NATURAL RESOURCE CONSULTING, INC. 4 RTKC- East Abutment Extension November 15, 2016 2.2. Figure
More informationModified Sheet Pile Abutment for Low-Volume Road Bridge
Modified Sheet Pile Abutment for Low-Volume Road Bridge Ryan R. Evans Department of Civil, Construction, and Environmental Engineering Iowa State University 176 Town Engineering Ames, IA 50011 ryevans@iastate.edu
More informationMONO CREEK SEDIMENT TRANSPORT AND FLOODPLAIN CONNECTIVITY STUDY
MONO CREEK SEDIMENT TRANSPORT AND FLOODPLAIN CONNECTIVITY STUDY TABLE OF CONTENTS Page 1.0 INTRODUCTION... 1 2.0 STUDY OBJECTIVES... 1 3.0 STUDY AREA... 2 3.1 Upper Adjustable Study Reach (RM 3.5-3.7)...
More informationVol. 18,No Sichuan Water Power. MgO ,,610072) MgO. MgO. MgO. MgO. MgO. MgO. MgO, MgO. MgO
18 2 1 9 9 9 6 Sichuan Water Power Vol. 18 No. 2 1 9 9 9 2 0 6 MgO ( 610072) 10 20 MgO MgO 12 MgO MgO MgO MgO 1 MgO 20 MgO MgO MgO MgO MgO MgO 20 12 MgO MgO MgO 20 MgO MgO MgO 10 : 2 MgO 10 2. 1 1987 1989
More informationTable 3-1 Summary of Storm Drain Outfalls
Table 3-1 Summary of Storm Drain Outfalls Outfall Number Description 005 The drainage area associated with Outfall 005 is to the west of the plant adjacent to and north of Warehouse 2/3, and includes a
More informationSTORMWATER MANAGEMENT REPORT
STORMWATER MANAGEMENT REPORT HOG HILL BROOK Island Pond Road and West Side Drive Atkinson, New Hampshire December 21, 2009 KNA Project No. 09-0722-1 Prepared For: Prepared By: Ted Stewart, Road Agent Town
More informationMONTANA FLUME. User s Manual. Montana (Short Parshall) Flume User s Manual
MONTANA FLUME User s Manual i Montana (Short Parshall) Flume User s Manual TABLE OF CONTENTS Introduction to the Montana Flume... 1 Function... 1 Design... 1 Standards... 2 Accuracy... 3 Dimensions...
More informationACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK
ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK Joseph Navarra, P.E, Maryland State Highway Administration, 410-545-8315, jnavarra@sha.state.md.us ABSTRACT The MDSHA
More informationIdentifying Number MPC-354. Project Title: Geotechnical Limit to Scour at Spill-through Abutments. University: The University of Wyoming
Identifying Number MPC-354 Project Title: Geotechnical Limit to Scour at Spill-through Abutments University: The University of Wyoming Principal Investigators: Robert Ettema PhD, PE College of Engineering
More informationArchitect/Contractor/QS/Sub-Contractor/C of W/RE/File ref PiMS Documents Site Visit Report. Item Text Action on
Site visit report Project Title Killamarsh Cycleway (TPBN559 SUSTRANS Connect2 - Halfway to Killamarsh (Phase 1)) Project No. 290390 Site Visited Killamarsh Station Road Date of Visit 25 th November 2011
More informationLITTLE DELL OUTLET STRUCTURE, UTAH
TA7 \-134 no.hl- 89-7 c. 2 -CE- Propectyoftt. United Stat Govt'rnment TECHNICAL REPORT HL-89-7 LITTLE DELL OUTLET STRUCTURE, UTAH Hydraulic Model Investigation by Bobby P. Fletcher Hydraulics Laboratory
More informationNCHRP REPORT (2)
National Cooperative Highway Research Program NCHRP REPORT 4-5 () ABUTMENT SCOUR IN COHESIVE MATERIALS J.-L. Briaud, H.-C. Chen, K.-A Chang, S. J. Oh, X. Chen October 009 Transportation Research Board
More informationTHE VETIVER SYSTEM FOR SLOPE AND ROAD STABILIZATION AND EROSION CONTROL IN THE DEMOCRATIC REPBULIC OF THE CONGO. BY Eng.
THE VETIVER SYSTEM FOR SLOPE AND ROAD STABILIZATION AND EROSION CONTROL IN THE DEMOCRATIC REPBULIC OF THE CONGO BY Eng. Alain NDONA NZEY DR Congo country-wide data * Land area is equal to 2.345.410 square
More informationFiled: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8
Filed: 2018-07-04, EB-2018-0108, Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889
More informationREASSESSMENT OF THE ST. FRANCIS DAM FAILURE
REASSESSMENT OF THE ST. FRANCIS DAM FAILURE By J. David Rogers, C. E., C. E.G., and David J. McMahon, C.E. INTRODUCTION The St. Francis Dam was a curved concrete gravity dam built by the City of Los Angeles
More informationDetection. at first sight. One of the newest trends
NDT Specialist Sami Hemminki, Inspecta, Finland, describes the benefits of guided wave ultrasonic testing. Detection at first sight One of the newest trends in pipeline testing is the use of guided wave
More informationAnalyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes
Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes J. H. Wood John Wood Consulting, Lower Hutt. ABSTRACT: 2012 NZSEE Conference Twelve State Highway (SH) bridges subjected
More informationThe Structure upon which the ends of a Bridge rests is referred to as an Abutment
ABUTMENTS The Structure upon which the ends of a Bridge rests is referred to as an Abutment The most common type of Abutment Structure is a Retaining Wall, Although other types of Abutments are also possible
More informationExecutive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report
Executive Summary The No. 01607 carries the Trans-Canada Highway over Quartz Creek, approximately 45 km northwest of Golden, BC. As part of an Enhanced Bridge Inspection Program, the BC Ministry of Transportation
More informationTwo Dimensional Computer Modeling of
\N P? v&cu&ae yoomk Two Dimensional Computer Modeling of Green River at Dinosaur National Monument and Canyonlands National Park For: Water Rights Branch Water Resources Division National Park Service
More information2006 RALSTON AFTERBAY WATER TEMPERATURE INVESTIGATION STUDY REPORT
Placer County Water Agency Middle Fork American River Project (FERC Project No. 2079) 2006 RALSTON AFTERBAY WATER TEMPERATURE INVESTIGATION STUDY REPORT Placer County Water Agency 144 Ferguson Road Auburn,
More informationFun With Foam Deep Injection
Fun With Foam Deep Injection Stephen Cruise Environmental Resource Specialist Where were we? Original Project Culvert to Bridge Fish Passage Improvement Modular Concrete Block bridge design Pacific Bridge
More informationSilica it s more than just dust!
Silica it s more than just dust! The health hazards of silica (quartz) in construction work Division of Occupational Safety & Health (DOSH) Purpose of this training The purpose of this training is to alert
More informationDecember 12, Mr. Ronald Gilbert, P.E. City Engineer City of Bessemer 1930 Second Avenue North Suite 150 Bessemer, AL 35020
December 12, 2014 Mr. Ronald Gilbert, P.E. City Engineer City of Bessemer 130 Second Avenue North Suite Bessemer, AL 3020 Re: The proposed new development of Pediatrics West McAdory Bell Hill Road Bessemer,
More informationMonitored Displacements of a Unique Geosynthetic-Reinforced Walls Supporting Bridge and Approaching Roadway Structures
Abu-Hejleh, N., Zornberg, J.G., and Wang, T. (). Monitored Displacements of a Unique Geosynthetic-Reinforced Walls Supporting Bridge and Approaching Roadway Structures. Proceedings of the 8th Annual Meeting,
More informationA how to guide. NWHA 2010 February 16,
A how to guide. NWHA 2010 February 16, 2010 1 Public Safety begins with keeping messaging simple. NWHA 2010 February 16, 2010 2 What is a Public Safety Plan? A brief document that exhibits all safety devices:
More informationNILE RIVER WATER RESOURCES ANALYSIS
Tenth International Water Technology Conference, IWTC1 26, Alexandria, Egypt 39 NILE RIVER WATER RESOURCES ANALYSIS Medhat Aziz 1 and Sherine Ismail 2 1 Deputy Director, Nile Research Institute (NRI),
More informationFINAL AND TEMPORARY REHABILITATION PRINCIPLES. BLOOMFIELD GROUP REPORT 2014 Rix s Creek
Rix s Creek Lane Singleton NSW 2330 AUSTRALIA PO Box 4 East Maitland NSW 2323 T: 61 2 6578 8888 F: 61 2 6571 1066 ABN 25 003 824 244 FINAL AND TEMPORARY REHABILITATION PRINCIPLES BLOOMFIELD GROUP REPORT
More information