Emergency Bridge Stabilization at Mile Watrous Subdivision

Size: px
Start display at page:

Download "Emergency Bridge Stabilization at Mile Watrous Subdivision"

Transcription

1 Emergency Bridge Stabilization at Mile Watrous Subdivision Christophe Deniaud, Ph.D., P.Eng. Bridge Engineer, CN Avenue Edmonton, Alberta, Canada T5J 0K2 Tel: (780) Fax: (780) Tim Saunders, P.Eng. Structural Engineer, CN PO Box Lagimodiere Bvd Winnipeg, Manitoba, Canada R3C 2Z6 Tel: (204) Fax: (204) /

2 ABSTRACT In the spring of 2006, an ongoing monitoring program indicated that the east abutment of the bridge over the South Saskatchewan River at Mile Watrous Subdivision was settling. A geotechnical consultant confirmed that the east embankment of the South Saskatchewan River was experiencing a landslide in the vicinity of the east abutment of the bridge. This landslide was causing the failure of a soil mass that encompassed the abutment of the bridge and unattended to, the slope failure would have been catastrophic with eventual loss of the entire embankment as well as the abutment and the 175 through-truss span resting on it. CN crews as well as multiple contractors were immediately dispatched to the site to begin construction on the preventative and restorative measures. Over a period of one month, work on site continued seven days per week in a race against the accelerating settlement occurring at the east end of the structure. At its peak, settlement of the abutment was occurring at a rate of approximately 3/8 per day, with additional shims added on numerous occasions to keep the track in operation. Furthermore, throughout the entire duration of the emergency, Edmonton to Winnipeg mainline corridor traffic was never stopped. The work on site involved the successful strengthening of the existing abutment and effectively isolating the bridge abutment from the embankment should embankment settlement continue. The response proved to be very successful since a major track and service outage was avoided as well as the avoidance of costs for potential replacement of the entire abutment and span. 2/

3 INTRODUCTION Bridge Description The bridge at Mile Watrous Subdivision is an eight-span steel structure consisting of six decktruss spans, one deck plate girder span and a single 175 foot long through-truss span on the east end. The bridge crosses the South Saskatchewan River on the south side of Saskatoon, Saskatchewan with an overall length of 1501 feet and maximum height of 78 feet (see Figure 1). The single-track structure was built in 1908 and is on the Winnipeg-Edmonton corridor of CN s Western Region. The track profile consists of a 0.40% grade decreasing to the west over the entire length of the bridge. The east abutment of the bridge, where the settlement occurred, is unreinforced concrete founded on five rows of 12 timber piles that were driven to a depth of 17 feet below the base of the abutment. Initial Assessment Vertical misalignment of the east end of the bridge was first reported to the Bridges and Structures department in late October 2005 (see Figure 2). Upon receiving this report a survey is immediately conducted to determine the current track profile and pick up elevation data from other components of the structure including the bearing seat of the east abutment and the bearings, floor beams and stringers of the through-truss (Span 1) resting on this abutment. Although this survey indicates a definite vertical alignment change when compared with the design elevations, there is not any recent data available to compare with in order to establish the rate and acceleration of the potential settlement. As such, this initial survey served as a baseline for a weekly monitoring program consisting of subsequent surveys to confirm any change. This data was also used to establish a vertical curve of the track profile and to determine shim height requirements for the east end of span 1. On November 25, 2005 the east end of Span 1 is shimmed three inches bringing the alignment to an acceptable condition. During the subsequent monitoring surveys, there is no indication of any settlement when compared against the baseline data and as such the monitoring program is put on hold until the spring of Furthermore, there is also no further settlement of the east abutment during the winter. 3/

4 In late February 2006 the East abutment begins to settle again and the monitoring program is reinstated. Weekly surveys are completed to monitor the rate of settlement of the east embankment and its influence on the bridge abutment. Now that new settlement of the east embankment is reported and confirmed, P. Machibroda Engineering, a geotechnical consultant, was commissioned in March to complete a slope stability analysis of the east embankment of the South Saskatchewan River, in the vicinity of the bridge. During the next month, while the geotechnical analysis was being completed, monitoring continued and it is decided to excavate a test pit adjacent the abutment to confirm the condition of the timber piles under the abutment. The excavation is completed and the timber piles are confirmed to be in good condition, free of any deterioration. Results of the geotechnical investigation are received in mid April and confirm that an active landslide is occurring at the east end of the bridge. The soil stratigraphy of the area creates a perched water table behind the embankment, increasing pressure on the back of the abutment as well as increasing the overall weight of the material at the top of the embankment and reducing the factor of safety against a slope failure as indicated in Figure 3. The retrogressive landslide has a failure plane where embankment material is lost at the toe of the slope followed by a vertical settlement of a wedge of material that encompasses the bridge abutment, which explains the elevation changes of the bridge abutment. DETERMINATION OF SOLUTIONS Based on the geotechnical investigation, Machibroda recommends a series of remedial works listed below. 1) Slope stabilization with large ground water wells installed on the river bank 2) Placement of slope indicators throughout the area with weekly monitoring and ongoing survey 3) Placement of fill at the toe of the slope or slope reconstruction using soil reinforcing geogrid 4/

5 4) Regrading (excavation) at the crest of the slope 5) Underpinning of the existing abutment with deep foundations down into the stable glacial till stratum with HP piles all around the perimeter of the abutment. The Network Operation Bridge and Structure Design Group based in Edmonton got involved in April 2006 to design the remedial repairs as the abutment was continuously moving down and started to affect train operations. The preliminary design concludes that it is not possible to drive HP piles all around the perimeter of the existing abutment without affecting train operation. Furthermore, this option would require a large amount of HP piles to carry the vertical loads. The earth pressure behind the abutment would also require additional piles and walls installed further up the crest of the slope with dead man anchor systems. The pile driving operations close to the track with a slope failure situation are also a serious concern to maintain the integrity of the track bed. This solution would require a construction period in the order of a few months with a constant danger to the train operation. The second option consists of large diameter caissons installed on either side of the abutment (Figure 4). This design allows for the installation of the caissons outside the track, which enables continuity of the service. The existing abutment is then to be tied to the caisson concrete cap with Dywidag bars, which are cored into the existing abutment and post-tensioned. In addition, the piling contractor is able to mobilize its equipment within days and to start accessing the underside elevation of the existing abutment. Instead of installing soldier piles and lagging walls perpendicular and away from the track, it is decided to build these retaining walls parallel to the track. This design feature provides two fold benefits: 1) Access for the contractor to both sides of the abutment and 2) Decrease rate of slope movement at the bridge approach. 5/

6 Thus, the construction period is significantly reduced to 6 weeks with an increase confidence in the stability of the construction site. REPAIR DESIGN In cooperation with the piling contractor, readily available 30 diameter pipe piles are sourced out of British Colombia and shipped to the site immediately. While the contractor and CN forces are installing the shoring walls along the track at the back of the East abutment, the design of the repairs is optimized with the available pipe pile size and the available piling equipment. A total of 4 caissons per side are required to support the vertical loads from the abutment and the earth pressure from the moving embankment slope failure. The salvation of the existing abutment requires a change in the design philosophy. The existing abutment was supported on timber piles closely spaced and was cast with unreinforced concrete. Now, the new design ignores the timber piles, which are too short to be effective, and assumes the abutment seat behaves as a beam between the two rows of caissons. The design concludes that steel reinforcement is required and cores are drilled transversally through the abutment to insert high strength Dywidag bars. In addition, a total of 6 out of 20 bars installed are post-tensioned to tie the pile caps and the existing structure together. High strength concrete is used for the pile caps to provide an early strength suitable for post-tensioning operation after 3 days only. CONSTRUCTION AND EXECUTION Work begins onsite with an initial on-site meeting and site orientation with the contractors. Contractors and suppliers retained for the work include: 1. Agra Foundations Ltd. Responsible for pile-driving, caisson pipe installation, caisson concrete placement 2. Western Redi Mix Inc. Concrete Supply 3. P. Machibroda Engineering Ltd. Slope installation, concrete coring 4. F. Peters Excavating Ltd. Site excavation, equipment rentals 6/

7 5. UMA Engineering Ltd. Site Surveying 6. United Rentals Ltd. Miscellaneous rentals 7. Vector Construction Ltd. Grout placement 8. Harris Rebar Reinforcing Steel Supply Excavation The first order of business is the excavation and removal of excess embankment material from the top of the slope to reduce the overall load on the embankment. Concurrent with this excavation, a hydrovacuum truck is employed to locate the underground cables east of the abutment in preparation for driving piles for the retaining wall parallel to the track. Once all cables have been exposed and protected, the pile driving starts. The piles are driven on the south side first followed by the north. Four days are required to install all of the piles required for the retaining wall (see Figure 5 and 6). During this period, the east abutment had settled approximately ¾. Additional shims are placed in order to raise the east end of the bridge span 2-1/2. At this stage an additional measure is taken to assist with monitoring of the settlement through the installation of a cable running between the bridge abutment and the recently driven piles for the retaining wall. This cable is incorporated into the CTC system with the intent that any major movement of the bridge abutment would disconnect the cable shunting the circuit and inducing a stop signal on all approaching signals to the bridge location. Retaining Walls Once all piles are driven for the retaining wall, timber lagging, steel channel walers and tieback bars are installed to complete the retaining wall construction. The wall is constructed progressively lower; therefore at the completion of the retaining wall, the base elevation is 15 feet below the base of rail. 7/

8 Steel Caisson The drill rig is mobilized to the south side of the bridge abutment and installation of the steel caissons commences. The drill rig augurs to a depth of 75 feet and then concrete is placed in the bottom of the hole followed by the installation of the steel pipe (See Figure 7 and 8). Additional concrete is placed to the top of the pipe. This process is repeated for the four caissons on the south side. During the installation of the caissons on the south side, holes are cored in the existing abutment to permit the installation of post-tensioning bars (see Figure 9). During the coring, it becomes evident that the interior of the existing abutment had previously cracked and may become a problem during the post-tensioning phase. Because of this, six Dywidag bars are immediately installed to aid in keeping the existing concrete intact. Once all caissons are installed on the south side, the coring contractor moves to the south side and the north side was prepared for the drill rig to install caissons there. There is concern of overloading the embankment with the large equipment, therefore a small retaining wall is built and piles are driven to transfer the equipment loads directly to the till layer rather than onto the embankment slope. Installation of the caissons proceeds on the north side. The north side proves to be more of a challenge on account of large boulders encountered below grade in the location of the piles. Additional equipment including rock-breakers are employed to assist in the removal of the rock. Formworks and Dywidag Bar Installation After all of the caissons are installed, a concrete mud slab is placed. The remaining Dywidag bars are installed through the post-tensioning ducts and the steel reinforcement for the pile caps is installed (see Figure 10). The construction of the formwork concludes preparations for the placement of concrete for the new pile caps. 28 cubic metres of concrete are required for each pile cap. 8/

9 Once the required strength has been achieved in the concrete pile caps, post-tensioning of the Dywidag bars is required to complete the process of transferring abutment loads to the new substructure. High-capacity jacks are used to post-tension the bars (see Figure 11). Following the post-tensioning, all holes are pressure grouted, as are all internal cracks of the existing abutment. POST-CONSTRUCTION ACTIVITIES The slope indicators are still in place within the vicinity of the abutment and are monitored on a regular basis. So far, these indicators have shown little movement in the embankment and no movement of the abutment. The through-truss bearings had been raised several times with numerous shim plates (see Figure 12) that need to be replaced with steel grillages. This work is scheduled as part of the regular maintenance program. CONCLUSION This effort contributed to the salvation not only of the existing abutment but also of the through-truss span. The cost of replacing both the steel span and the abutment would have been approximately $6,000,000. More importantly the train operation was never completely interrupted and track speed was re-established as soon as the repairs were completed. This achievement averted a major service disruption on the core route between Winnipeg and Edmonton, which prevented the re-routing and delays of trains over an extended period. 9/

10 Figure 1: CN Bridge at Mile Watrous Subdivision Facing East Figure 2: Mile Watrous Subdivision Initial Signs of Settlement 10/

11 Figure 3: Stratigraphic Section through the East embankment Figure 4: Strengthened Abutment with Caissons down to the Till Layer 11/

12 Figure 5: Pile Installation for Retaining Wall Construction Figure 6: Completed Retaining Wall on North Side 12/

13 Figure 7: Caisson Installation on South Side of Abutment Figure 8: Caisson Installation on South Side of Abutment 13/

14 Figure 9: Concrete Coring for Installation of Post-tensioning Reinforcement Figure 10: Placement of Reinforcing Steel and Formwork Construction 14/

15 Figure 11: Post-tensioning of Dywidag Bars Figure 12: East Bearings of Through-Truss Span 1 With Shim Plates Added Throughout the Project 15/

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK Joseph Navarra, P.E, Maryland State Highway Administration, 410-545-8315, jnavarra@sha.state.md.us ABSTRACT The MDSHA

More information

Four simply supported steel plate girders (appear to be an old railcar).

Four simply supported steel plate girders (appear to be an old railcar). BRIDGE INSPECTION BRIDGE NO./NAME N4-005: Akolkolex Crawford FSR (19.0 km) Inspection Date: September 22 nd, 2012 Inspected By: M. Hanson, R. Veitch Year Built: 1982 Number of Spans: 1 Span Lengths: Superstructure

More information

2011 BRIDGE INSPECTION REPORT

2011 BRIDGE INSPECTION REPORT 2011 BRIDGE INSPECTION REPORT BYRD PARK PUMP STATION BRIDGE OVER KANAWHA CANAL April 2011 FINAL December 2011 Looking - from Abutment B to Abutment A Prepared by: WHITMAN, REQUARDT, & ASSOCIATES, LLP 9030

More information

Shifting the Canning Bus Bridge Sideways

Shifting the Canning Bus Bridge Sideways Shifting the Canning Bus Bridge Sideways Ros MacKinlay Design Engineer, Wyche Consulting SYNOPSIS The Perth Mandurah railway proposed in 2002 required the replacement of an existing Kwinana Freeway bus

More information

ACCELERATED BRIDGE REPLACEMENT

ACCELERATED BRIDGE REPLACEMENT Christopher Beck Chief Engineer: Bridge & Structures Northern Indiana Commuter Transportation District 601 North Roeske Avenue Michigan City, IN chris.beck@nictd.com Accelerated Bridge Replacement (ABR)

More information

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017 Introduction Substructure Inspection and Rating That portion of the bridge located below the bearings Abutments Piers Rated separately Purpose is to: Receive the loads from the superstructure Transfer

More information

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill. Bridge Applications Technology The Reinforced Earth Company (RECo) offers a variety of bridge abutment and bridge crossing solutions, each are based on project specific requirements. Bridge abutments are

More information

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA IRFAN A. ALVI, P.E., Alvi Associates, Inc., Baltimore, MD IBC-02-25 KEYWORDS: box girder, counterweight abutment, curved girder, high-performance

More information

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse)

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) AGENDA Project Overview and Need Design and Special Provisions Construction Engineering

More information

Appendix B. Shallow Foundations Report

Appendix B. Shallow Foundations Report 12/10/2013 GEOTECHNICAL MANUAL Appendix B. Shallow Foundations Report PLEASE NOTE A sample foundations report is included here for reference. It is provided as an example of content, format, and organization

More information

\\H\15\ PH9 Inspection Photos

\\H\15\ PH9 Inspection Photos SHOP SLIDE Photo 1. at cracking across the footpath at the end of the Hwy 2 EB to Hwy 684 SB off ramp at the 99 Ave. intersection. Drop in asphalt trail (background) has worsened since 2013 and is now

More information

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A construction camera has been installed to view images of the bridge construction. Images are updated on

More information

Critically damaged bridges & concepts for earthquake recovery

Critically damaged bridges & concepts for earthquake recovery Critically damaged bridges & concepts for earthquake recovery J. Waldin, J. Jennings & P. Routledge Opus International Consultants Ltd, Christchurch, New Zealand 2012 NZSEE Conference ABSTRACT: This paper

More information

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS Louis J. Ruzzi P.E., PennDOT District 11-0 Bridge Engineer John Myler, PennDOT Assistant Construction Engineer, District 11-0 Bala

More information

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report Executive Summary The No. 01607 carries the Trans-Canada Highway over Quartz Creek, approximately 45 km northwest of Golden, BC. As part of an Enhanced Bridge Inspection Program, the BC Ministry of Transportation

More information

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge R04 ABC Project Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge Lead Adopter SHRP2 Solutions Innovative

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 89188 7 th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER OCTOBER 2, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7883 CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 4992 CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge Modular Steel Bridges Stark County Fischer Bridge Bottineau County Oak Creek Bridge This John Deere grain hauler was too heavy for the bridge. OOPS! An excavator and tow truck are needed to remove the

More information

Ahmed Mongi, M.S., P.E. Engineering Division

Ahmed Mongi, M.S., P.E. Engineering Division 1 Ahmed Mongi, M.S., P.E. Engineering Division 2 Honey Creek Bridge Completed in 2006 at a cost of $2.6 Million Precast pier caps and abutments. 3 Honey Creek Bridge Bridge closed for 60 days Simple span

More information

Conditional assessment of Kiri Bridge in Shkoder, Albania

Conditional assessment of Kiri Bridge in Shkoder, Albania Conditional assessment of Kiri Bridge in Shkoder, Albania Gentian Rexhaj 1, Enea Mustafaraj 2 1 2 Department of Civil Engineering, Epoka University, Albania 2 Department of Civil Engineering, Epoka University,

More information

PRELIMINARY GEOTECHNICAL DESIGN

PRELIMINARY GEOTECHNICAL DESIGN PNCC Manawatu River Pedestrian/ Cycle Bridge PRELIMINARY GEOTECHNICAL DESIGN 1 Introduction Opus has been commissioned by the Palmerston North City Council (PNCC) to prepare a Detailed Business Case (DBC)

More information

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014 Updated: 5/15/14 1 What was driver for deciding to slide vs. roll? Overall weight? 2 1. Why the two different slide methods? 2. How much experience should your contractor have to perform the slide work?

More information

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN 7-1.0 INTRODUCTION 7-2.0 RIGID PAVEMENT DESIGN 7-2.01 Cross Sections 7-2.02 Ramps and Loops with Storage Area 7-2.03 Major Forks, Branch

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7685 CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB

More information

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments A.M. Morsy. Department of Civil, Architectural, and Environmental Engineering, The University of Texas

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT STATE BRIDGE NO. 6081 CITY OR COUNTY 053 LOUDOUN TYPE OF BRIDGE REPORT: REGULAR INSPECTION JANUARY 2016 BRIDGE NAME: DIRECTION: FOREST MILLS

More information

Modified Sheet Pile Abutment for Low-Volume Road Bridge

Modified Sheet Pile Abutment for Low-Volume Road Bridge Modified Sheet Pile Abutment for Low-Volume Road Bridge Ryan R. Evans Department of Civil, Construction, and Environmental Engineering Iowa State University 176 Town Engineering Ames, IA 50011 ryevans@iastate.edu

More information

Architect/Contractor/QS/Sub-Contractor/C of W/RE/File ref PiMS Documents Site Visit Report. Item Text Action on

Architect/Contractor/QS/Sub-Contractor/C of W/RE/File ref PiMS Documents Site Visit Report. Item Text Action on Site visit report Project Title Killamarsh Cycleway (TPBN559 SUSTRANS Connect2 - Halfway to Killamarsh (Phase 1)) Project No. 290390 Site Visited Killamarsh Station Road Date of Visit 25 th November 2011

More information

DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA

DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA Brian Lord, Arup Pty Ltd, Australia ABSTRACT Arup was lead designer for Lend Lease on the Victoria Park Drive Modifications

More information

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Filed: 2018-07-04, EB-2018-0108, Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 36508 CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS

More information

Novel treatment technique

Novel treatment technique Final conference Zagreb, 27 th April 2018 TREAT How to choose the optimal rehabilitation technique Novel treatment technique Stanislav Lenart Slovenian National Building and Civil Engineering Institute

More information

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report Final Report VTRC 06-R35 Virginia Transportation Research Council research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report http:/www.virginiadot.org/vtrc/main/online_reports/pdf/06-r35.pdf

More information

Detailed Seismic Assessment and Seismic Improvements of Market Road Underpass

Detailed Seismic Assessment and Seismic Improvements of Market Road Underpass Detailed Seismic Assessment and Seismic Improvements of Market Road Underpass D. Novakov, D. Ashby, T. Chin & A. George Opus International Consultants Ltd, Wellington - Auckland, New Zealand. G. Gregg

More information

Integral bridges and environmental conditions

Integral bridges and environmental conditions Integral bridges and environmental conditions COMISU CLAUDIU-CRISTIAN, BOACĂ GHEORGHITĂ Department of Roads and Foundations Faculty of Civil Engineering and Building Services The "Gheorghe Asachi" Technical

More information

APPENDIX A INTEGRAL ABUTMENTS

APPENDIX A INTEGRAL ABUTMENTS APPENDIX A INTEGRAL ABUTMENTS Appendix A Guidelines for Design of Integral Abutments Rev. 1 - September, 2007 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT

More information

Geotechnical Issues Associated With the Design and Construction of the Middle River Bridge

Geotechnical Issues Associated With the Design and Construction of the Middle River Bridge Missouri University of Science and Technology Scholars' Mine International Conference on Case Histories in Geotechnical Engineering (2013) - Seventh International Conference on Case Histories in Geotechnical

More information

L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015

L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015 Canterbury Bridge Group Ferrymead Bridge L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015 Presenter: Lloyd Greenfield Senior

More information

OVER US 6 LATERAL BRIDGE SLIDE: I-75

OVER US 6 LATERAL BRIDGE SLIDE: I-75 LATERAL BRIDGE SLIDE: I-75 OVER US 6 Bob Beasley, PE, Ohio Bridge Manager, Arcadis U.S., Inc. Todd Lezon, Regional Manager, Kokosing Construction Company, Inc. November 4, 2016 1 Agenda Design Bob Beasley,

More information

Appendix C Guidelines for Design of Integral Abutments March 3, 2003

Appendix C Guidelines for Design of Integral Abutments March 3, 2003 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT s and the UK Highways Agency. They provide guidance and outline the issues that need to be considered and should

More information

PENNDOT e-notification

PENNDOT e-notification PENNDOT e-notification Bureau of Design Engineering Computing Management Division BRADD No. 027 August 30, 2010 Release of Version 3.1.5.0 PennDOT's Bridge Automated Design and Drafting Software (BRADD)

More information

Effect of Pile Orientation in Skewed Integral Abutment Bridges

Effect of Pile Orientation in Skewed Integral Abutment Bridges Effect of Pile Orientation in Skewed Integral Abutment Bridges RABIH NAJIB, Ph.D., PE, Alpha Corporation, Baltimore, Maryland and AMDE M. AMDE, Ph.D., PE, University of Maryland, College Park, Maryland

More information

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and Overview Design criteria for I-90 over Kishwaukee Integral Abutment Bridges (IAB) Design Criteria Design analysis, details and construction Lessons Learned during construction Instrumentation by Illinois

More information

St. Croix River Crossing Bridge Foundation Load Test Project. 1/27/2010 St. Croix River Crossing Bridge - Foundation Load Test Project

St. Croix River Crossing Bridge Foundation Load Test Project. 1/27/2010 St. Croix River Crossing Bridge - Foundation Load Test Project St. Croix River Crossing Bridge Foundation Load Test Project Load Test Sites 4 driven piles Drilled Shaft Site A Site B Load Test Purpose To gather design data for foundation design Allows for more refined

More information

COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES.

COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES. COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES Authors D. Nyborg, Research Physicist, TISEC Inc., Montreal;

More information

Monitored Displacements of a Unique Geosynthetic-Reinforced Walls Supporting Bridge and Approaching Roadway Structures

Monitored Displacements of a Unique Geosynthetic-Reinforced Walls Supporting Bridge and Approaching Roadway Structures Abu-Hejleh, N., Zornberg, J.G., and Wang, T. (). Monitored Displacements of a Unique Geosynthetic-Reinforced Walls Supporting Bridge and Approaching Roadway Structures. Proceedings of the 8th Annual Meeting,

More information

Integral Abutment Bridge Design with Soil Structure Interaction

Integral Abutment Bridge Design with Soil Structure Interaction Integral Abutment Bridge Design with Soil Structure Interaction Thursday, May 11, 2017 3:00 PM 4:00 PM EST Speaker Engineer: Suthichai Saelim Project Location WESTBOROUGH Railroad HOPKINTON Project Location

More information

300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES

300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES 300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES BONACCI GROUP DOCUMENT HISTORY ISSUE REVISION DATE AUTHOR REVIEWER Issued for DTMR Review A October

More information

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Jeff Sizemore, P.E. Geotechnical Design Support Engineer SCDOT Ed Tavera, P.E. Principal Geotechnical Engineer Geoengineers

More information

Figure 3: Analytic procedure

Figure 3: Analytic procedure International Journal of Scientific and Research ublications, Volume 7, Issue 5, May 2017 567 Investigation of Integral Bridge Effect under Dynamic Loading Haymanmyintmaung *,kyawlinnhtat ** * Department

More information

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue FHWA Rhode Island Showcase October 30, 2014 Accent image here Primary Image here Presentation Outline Overview of the Project Scope ABC Project

More information

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection No. 1 2/26/2016 830 MSE Wall V 26 Is ADE 830 MSE Wall to be used in conjunction with NBE 218 Other Abutment

More information

Low-Volume Road Abutment Design Standards

Low-Volume Road Abutment Design Standards Low-Volume Road Abutment Design Standards V.W. Robbins HNTB Corporation 7450 W. 130th St., Suite 400 Overland Park, KS 66213 vrobbins@hntb.com F. Wayne Klaiber Bridge Engineering Center 418 Town Engineering

More information

Retrofit to improve earthquake performance of bridge abutment slopes

Retrofit to improve earthquake performance of bridge abutment slopes Proceedings of the Ninth Pacific Conference on Earthquake Engineering Building an Earthquake-Resilient Society 14-16 April, 2011, Auckland, New Zealand Retrofit to improve earthquake performance of bridge

More information

State-Aid Bridge News August 2, 2005

State-Aid Bridge News August 2, 2005 State-Aid Bridge News August 2, 2005 Bridge Hydraulic Information The FHWA has been inquiring about our Scour Program. In particular, there are two areas of concern; 1. Are our Scour Action Plans current

More information

Stantec Consulting Ltd Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) Fax: (905)

Stantec Consulting Ltd Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) Fax: (905) Filed: 2018-07-04, EB-2018-0108, Exhibit B, Tab 1, Schedule 1, Attachment 4, Page 1 of 10 Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889

More information

5 DAMAGE TO TRANSPORTATION FACILITIES

5 DAMAGE TO TRANSPORTATION FACILITIES 5 DAMAGE TO TRANSPORTATION FACILITIES In the Kocaeli, Turkey earthquake of August 17, 1999, extensive damage of transportation facilities occurred in the Kocaeli and Sakarya region, Turkey as shown in

More information

Using the sharp-crested weir formula the outflow was:

Using the sharp-crested weir formula the outflow was: Date: 2009 July 16 11:00 AM 14 Island Lake Dam Inspection Report Persons Present: Bryon Keene, P.Eng. Harry Stinson Brett Dark (14 Island Lake Association) Peter Peart (14 Island Lake Association) The

More information

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri Adams et al. (2012), FHWA Geosynthetic Reinforced Soil Integrated Bridge System Interim Implementation

More information

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples BY MARTIN P. BURKE, JR. Innumerable bridges both in the U.S. and abroad have been, and continue to be, damaged by the restrained growth

More information

Bengt H. Fellenius. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot. Amsterdam.

Bengt H. Fellenius. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot. Amsterdam. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot Bengt H. Fellenius Amsterdam May 27, 216 Fellenius, B.H. and Nguyen, M.H., 213. Wick Drains and Piling for

More information

3/18/03 CE Keith P. Brabant, P.E.

3/18/03 CE Keith P. Brabant, P.E. 1 Keith P. Brabant, P.E. 2 SELECT GRANULAR BACKFILL 3 4 Maximum of 15% fines Maximum size of 4 inches Free-draining, frictional, and durable Graduation limits referenced by AASHTO T-27 5 US Sieve Size

More information

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 SITE NUMBER AND NAME: NC 52 Pembina River Bridge LEGAL DESCRIPTION: SE 1-50-9-W5M STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 NAD 83 COORDINATES:

More information

ATTACHMENT B8 Incident History

ATTACHMENT B8 Incident History Appendix B GIS/Imagery Outputs ATTACHMENT B8 Incident History Appendix B - GIS/Imagery Outputs Appendix B: Attachment B8 Incident History TABLE OF CONTENTS B.B8-1 INTRODUCTION... 1 B.B8-2 FACT SHEETS...

More information

Hanson Dam s mysteries solved

Hanson Dam s mysteries solved Hanson Dam s mysteries solved Hanson: Earth dams are expected to leak MIKE ARCHBOLD; STAFF WRITER STAFF WRITER LAST UPDATED: APRIL 27TH, 2011 06:34 AM (PDT) It had the makings of a doomsday scenario. Two

More information

Pennsylvania s Experience with LRFD Implementation. By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation

Pennsylvania s Experience with LRFD Implementation. By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation Pennsylvania s Experience with LRFD Implementation By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation Overview Case History Spread Footing Width and Braking force Approach

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: FEBRUARY 12 THROUGH FEBRUARY

More information

Aerial of Conceptual Path and Bridge Tysons-Old Meadow Road Bike/Ped Improvements

Aerial of Conceptual Path and Bridge Tysons-Old Meadow Road Bike/Ped Improvements Aerial of Conceptual Path and Bridge Barnes & Noble at One Place Project Location Corner Center Proposed Bridge Encore Condominiums Regency Club Condominiums Path continues to Dolley Madison Boulevard

More information

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint Introduction The purpose of this white paper is to provide information regarding the potential for fractures

More information

Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3

Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3 F. W. Klaiber, D. J. White, T. J. Wipf, B. M. Phares, V. W. Robbins Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3 Development of Design Methodology August 2004 Sponsored

More information

Ashton Avenue Integral Bridge

Ashton Avenue Integral Bridge Ashton Avenue Integral Bridge Behzad Golfa, Senior Bridge Engineer, GHD Pty Ltd ABSTRACT The Ashton Avenue Bridge is a replacement of the original three-span timber bridge over Perth- Fremantle Rail line

More information

Non-Destructive Testing of Drilled Shafts Current Practices and New Methods

Non-Destructive Testing of Drilled Shafts Current Practices and New Methods Non-Destructive Testing of Drilled Shafts Current Practices and New Methods Brent Robinson, Pile Dynamics, Inc. 2012 Pile Dynamics, Inc. Foundation & Geotechnical Engineering Why Test Integrity? Survey

More information

The short path seepage area is between the dam embankment and the bend in the existing drainage tunnel. This area is highlighted in red on the

The short path seepage area is between the dam embankment and the bend in the existing drainage tunnel. This area is highlighted in red on the 2 The short path seepage area is between the dam embankment and the bend in the existing drainage tunnel. This area is highlighted in red on the picture in the top left hand corner. Water in this pathway

More information

The Structure upon which the ends of a Bridge rests is referred to as an Abutment

The Structure upon which the ends of a Bridge rests is referred to as an Abutment ABUTMENTS The Structure upon which the ends of a Bridge rests is referred to as an Abutment The most common type of Abutment Structure is a Retaining Wall, Although other types of Abutments are also possible

More information

Flume Installation Instructions

Flume Installation Instructions Flume Installation Instructions To ensure a successful installation, it is important to keep the following points in mind: 1) There should be no bend, dips, elbows, or flow junction immediately upstream

More information

Caleb Mitchell. B.S., Kansas State University, 2016 A THESIS. submitted in partial fulfillment of the requirements for the degree MASTER OF SCIENCE

Caleb Mitchell. B.S., Kansas State University, 2016 A THESIS. submitted in partial fulfillment of the requirements for the degree MASTER OF SCIENCE Finite Element Analyses and Proposed Strengthening of a Reinforced Concrete Box Girder Bridge Subjected to Differential Settlement by Caleb Mitchell B.S., Kansas State University, 2016 A THESIS submitted

More information

Integral Abutment Bridges-Development of Soil Model for Soil Structure Interaction in Time History Analysis

Integral Abutment Bridges-Development of Soil Model for Soil Structure Interaction in Time History Analysis International Journal of Engineering Research and Development e-issn: 2278-067X, p-issn: 2278-800X, www.ijerd.com Volume 10, Issue 3 (March 2014), PP.31-40 Integral Abutment Bridges-Development of Soil

More information

Geosynthetic-reinforced soil bridge abutments

Geosynthetic-reinforced soil bridge abutments Geosynthetic-reinforced soil bridge abutments Measuring the performance of geosynthetic reinforcement in a Colorado bridge structure. By Jorge G. Zornberg, Naser Abu-Hejleh, and Trever Wang The technology

More information

Numerical analysis of the embedded abutments of integral bridges

Numerical analysis of the embedded abutments of integral bridges Numerical analysis of the embedded abutments of integral bridges Ming XU Researcher, Dept. of Civil & Env. Engrg., University of Southampton, UK Summary Alan G. BLOODWORTH Lecturer, Dept. of Civil & Env.

More information

B. Stipulated Price (Lump Sum). If Contract is Stipulated Price Contract, payment for Work in this Section is included in total Stipulated Price.

B. Stipulated Price (Lump Sum). If Contract is Stipulated Price Contract, payment for Work in this Section is included in total Stipulated Price. Section 02222 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Abandonment in place of existing sewers, junction structures, manholes, and force mains. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment

More information

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563 Interstate Power and Light Company Burlington Generation Station CCR Surface Impoundment Annual Inspection Report 154.018.012.001 Report issued: December 21, 2016 Hard Hat Services ph: 877-630-7428 hardhatinc.com

More information

Application of pile underpinning technology on shield machine crossing through pile foundations of road bridge

Application of pile underpinning technology on shield machine crossing through pile foundations of road bridge Geotechnical Aspects of Underground Construction in Soft Ground Ng, Huang & Liu (eds) 2009 Taylor & Francis Group, London, ISBN 978-0-415-48475-6 Application of pile underpinning technology on shield machine

More information

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION 3.2.5.0 Since the release of BRADD Version 3.2.4.3, several operational issues have been addressed. This release of BRADD Version 3.2.5.0 contains the following

More information

Use of Ductile Iron Pipe Piles for a New Shared Use Path Bridge over Maribyrnong River in West Melbourne

Use of Ductile Iron Pipe Piles for a New Shared Use Path Bridge over Maribyrnong River in West Melbourne Use of Ductile Iron Pipe Piles for a New Shared Use Path Bridge over Maribyrnong River in West Melbourne Dr Michael Wei 1, Jawad Zeerak 2, David Barton 3 1 Principal Geotechnical, EIC Activities Pty Ltd

More information

BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE

BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE Paul J. Barr Marv W. Halling Conner Huffaker Hugh Boyle Utah State University Department of Civil and Environmental Engineering Logan, Utah September

More information

Integral Bridge Design - Derivation of the Spring Constant for Modelling the Soil-Structure Interaction

Integral Bridge Design - Derivation of the Spring Constant for Modelling the Soil-Structure Interaction Integral Bridge Design - Derivation of the Spring Constant for Modelling the Soil-Structure Interaction Sergei Terzaghi BE(Hons), MIPENZ Gillian Sisk BEng PhD MIEI CEng Synopsis Integral bridges present

More information

Winona Bridge Visual Quality Review Committee

Winona Bridge Visual Quality Review Committee Winona Bridge Visual Quality Review Committee Summary of Preferred Features October 7, 2014 Creating Bridges As Art 1 Summary of Preferred Features Based on Visual Quality Review Committee Final Design

More information

Calaveras Dam Replacement Project. Third Party Due-Diligence Review Investigations and Design of the Left Abutment

Calaveras Dam Replacement Project. Third Party Due-Diligence Review Investigations and Design of the Left Abutment San Francisco Public Utilities Commission Calaveras Dam Replacement Project 11 Third Party Due-Diligence Review Investigations and Design of the Left Abutment Presented By: Steve Verigin Senior Vice President,

More information

DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE

DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE Abstract S. Hassiotis M. ASCE Stevens Institute of Technology, Hoboken, N.J. 07030 sophia.hassiotis@stevens.edu An integral-abutment bridge

More information

Semi-Integral Abutment Bridges

Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Leslie Street Over Hwy 407 Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Semi-Integral Abutment Bridges

More information

CHAPTER 5 MODELING OF THE BRIDGE

CHAPTER 5 MODELING OF THE BRIDGE 62 CHAPTER 5 MODELING OF THE BRIDGE 5.1 MODELING SAP2000, a nonlinear software package was used for modeling and analysing the study bridge. The following list provides details about the element type used

More information

Concrete Doesn t Just Come In Vanilla Anymore

Concrete Doesn t Just Come In Vanilla Anymore feature Part 6: Flowable Fill Concrete Doesn t Just Come In Vanilla Anymore By A. Vance Pool, Senior National Resource Director, NRMCA This is the sixth article in a series on many of the different types

More information

Bank Erosion and Bridge Scour

Bank Erosion and Bridge Scour JULY 2017 NCHRP PRACTICE-READY SOLUTIONS FOR Bank Erosion and Bridge Scour NCHRP NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM RESEARCH TOPIC HIGHLIGHTS INTRODUCTION Bank Erosion and Bridge Scour: NCHRP

More information

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes J. H. Wood John Wood Consulting, Lower Hutt. ABSTRACT: 2012 NZSEE Conference Twelve State Highway (SH) bridges subjected

More information

EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT

EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT Norton et al. Word Count: 8400 Tables: 5 Figures: 13 1 EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT Date submitted: 08/01/02 Date Revised and Resubmitted: 11/15/02

More information

The detection limit for tritium is 300 pci/l

The detection limit for tritium is 300 pci/l New Jersey Department of Environmental Protection - Bureau of Nuclear Engineering (BNE) Investigation of Found in Onsite Vault Background and Installation of Groundwater Monitoring Wells In April of 009,

More information

VIPR and Power plate EXERCISE - 1 EXERCISE Fitness Professionals Ltd 2011 Job No. 2968

VIPR and Power plate EXERCISE - 1 EXERCISE Fitness Professionals Ltd 2011 Job No. 2968 FIT FOR DAILY LIFE To be fit for daily life includes many movement abilities. Dynamic stability, co-ordination, balance, motor control, mobility and efficiency are all vital (including basic strength and

More information