Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report

Size: px
Start display at page:

Download "Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report"

Transcription

1

2

3 Executive Summary The No carries the Trans-Canada Highway over Quartz Creek, approximately 45 km northwest of Golden, BC. As part of an Enhanced Bridge Inspection Program, the BC Ministry of Transportation and Infrastructure is undertaking the inspection of the bridge which is located in the Southern Interior Region. This document presents the condition of the bridge components as observed during the detailed inspection. Buckland & Taylor's (B&T s) 2014 inspection of the, identified large areas of spalled concrete on the pier legs and crossbeams at Piers 2 and 5 and coating failure with varying degrees of corrosion on the steelwork in the vicinity of the deck joints at both abutments, Pier 2 and Pier 5. Additionally, undermining and erosion were observed at the Pier 3 and 4 foundations raising stability concerns. It is noted that the Ministry has had rock anchors installed to address the stability concerns since the date of the inspection. Based on the inspection results, a series of other recommendations expressed in terms of Maintenance Items, Inspection Items, Rehabilitation Items and Study Items have been proposed to address the deterioration and deficiencies observed during this inspection, and a priority rating is assigned to each. Bridge No

4

5 Table of Contents 1 Introduction Description of Bridge Condition Inspection Inspection Scope Inspection Procedure Approach Roadways and Embankments Abutments East Abutment West Abutment Concrete Piers Steel Piers Steel Pier Foundations Bearings Expansion (Sliding) Bearings - At Abutments Expansion (Sliding) Bearings At Pier 2 and Pier Fixed Bearings At Pier 1 and Pier Fixed Bearings at Pier 3, Pier 4 and the Apex of Delta Pier Longitudinal Girders and Transverse Floorbeams Longitudinal Girders Transverse Floorbeams Bracing/Diaphragms Deck Concrete Roadway Deck Deck Joints Deck Drains Parapets Recommendations Summary and Conclusions...41 Appendix A General Arrangement of Existing Bridge... A-1 Appendix B BC Condition... B-1 Bridge No i

6

7 1 Introduction The BC Ministry of Transportation and Infrastructure is undertaking an enhanced bridge inspection program for two bridge structures in the Southern Interior Region. The scope of work comprises: Inspection of superstructure and substructure; Preparation of a detailed inspection report documenting the condition of the bridge components; and If warranted by the inspection findings, an evaluation and live load evaluation of the inspected steel stringer spans, and substructures; including preparation of an evaluation report. As time and budget allows, the assignment may be expanded to include evaluations, conceptual rehabilitation and/or replacement designs and related cost estimates for the bridges that are found to be deficient as a result of the evaluations. The two bridges to be inspected are listed following: Bridge No Summit Lake Overhead; and Bridge No This report summarizes the inspection findings for Bridge No Quartz Creek Bridge. Bridge No

8 2 Description of Bridge The is located on the Trans-Canada Highway approximately 45 km northwest of Golden, BC and carries the Trans-Canada Highway over Quartz Creek. Figure 1 shows the existing bridge arrangement and a general arrangement drawing of the bridge is included in Appendix A. The bridge carries two traffic lanes and was constructed in The bridge is (119 m) long and consists of a total of eight spans, supported on two concrete abutments and seven internal pier support locations. All spans are 45 ft. (13.7 m) long with the exception of Span 4 & Span 5 which are 60 ft. (18.3 m) long each. For the purpose of this report, the piers and spans are numbered from east to west. Three different types of piers are incorporated in the bridge structure; Piers 1, 2, 5 and 6 are concrete portal frames consisting of a cap beam supported by a pair of columns, Piers 3 and Pier 4 consist of a pair of vertical steel columns with X-bracing while the remaining pier is a delta pier consisting of two inclined steel braced frames rising from the footings of Pier 3 and Pier 4 and meeting at an apex at the bottom of the superstructure. Expansion bearings are located at both abutments and at Pier 2 and Pier 5. Fixed bearings are located at Pier 1, Pier 3, Pier 4, Pier 6 and at the apex of the delta pier. All spans consists of two longitudinal edge girders, arrange in three continuous segments, which support transverse floorbeams at 7.5 ft. (2.3 m) centres. A noncomposite cast-in-place concrete bridge deck is supported by the floorbeams. The deck between the edge barriers provides a 30-0 (9.14 m) roadway width. Expansion joints are present in the deck at Pier 2, Pier 5 and abutment expansion bearing locations. 2 Bridge No

9 Figure 1: General Arrangement Bridge No

10 3 Condition Inspection 3.1 Inspection Scope Under the Terms of Reference for this project, Buckland & Taylor Ltd. (B&T) was retained by the Ministry of Transportation and Infrastructure to perform a detailed inspection of the. All inspections were visual with some nondestructive testing of the concrete deck. The bridge was inspected on September 16th, Inspection Procedure An under-bridge inspection vehicle (snooper truck), as shown in Figure 2, was used to inspect the underside of the concrete deck, longitudinal girders and bracing, transverse crossbeams, bearings, and the upper portions of pier legs. Figure 2: Under-Bridge Inspection Vehicle 4 Bridge No

11 The top surface of the bridge deck, interior faces of the edge barrier and deck joints were visually inspected from the bridge deck, while ground slopes at the abutments, abutment structures, girders and bearings at abutments, and the lower part of piers and columns were inspected by walking on grade. The findings of this inspection have been summarized on the Ministry of Transportation and Infrastructure s Bridge Management Information System Condition Inspection Sheets which have been included in Appendix B. Recommendations in the forms of rehabilitation items, maintenance items and inspection items are summarized in Section Approach Roadways and Embankments The approach roadways are lined with concrete no-post barriers that taper the approach roadways into the bridge. Hazard signage is located at each end of the bridge. There are two large pavement cracks on the west approach to the bridge, the largest of which is located approximately 60 ft. (18.3 m) back from the abutment, shown in Figure 3. The second crack is approximately 20 ft. (6.1 m) from the first crack, across the eastbound lane. It is recommended that the pavement cracks be repaired (Maintenance Item M-1). Bridge No

12 Figure 3: Crack on West Approach Asphalt Erosion of fill material is occurring in the side sloped at both approach embankments and behind the east abutment back-wall, as seen in Figure 6. It is recommended that missing fill material behind the abutment back-walls be replaced and the existing drainage modified to prevent recurrence (Maintenance Item M-2). 6 Bridge No

13 Figure 4: Existing Drainage Culvert at South Wingwall of East Abutment Figure 5: Voids Behind South Wingwall of East Abutment Bridge No

14 3.4 Abutments Each abutment consists of a concrete ballast wall and two concrete bearing pedestals supported on a pile cap and piles. The ballast wall includes wingwall extensions at the four corners of the bridge, as seen in Figure 6 and Figure 7. Figure 6: West Abut. South Wingwall Figure 7: West Abut. South Wingwall Survey prisms have been installed on the face of both east and west ballast walls, possibly in an effort to monitor the abutments for potential movement East Abutment The east abutment ballast wall is delaminated over an estimated 90% of the surface area between the edges of the bridge deck. Delaminated areas were previously identified with spray paint, as seen in Figure 8 and Figure 9. Figure 8: Ballast Wall Delamination Figure 9: Ballast Wall Delamination East Abutment South End East Abutment at North Girder 8 Bridge No

15 While the wingwall extensions are generally in better condition than the ballast wall, unmarked delaminations and small concrete spalls were identified. Furthermore, the top surface of the south wingwall has moderate concrete deterioration believed to be a result of salt damage and stone chips, as seen in Figure 5. The north bearing concrete pedestal is delaminated on the inside corner which was marked with spray paint during a previous inspection. It is recommended that areas of concrete delamination and concrete deterioration in the east abutment be repaired (Rehabilitation Item R-1) West Abutment The west abutment ballast wall is delaminated for approximately 30% of the surface area between the full width of the bridge deck. These delaminations are generally contained within three large areas between the girders, and were previously identified and marked with spray paint. The observed sizes and approximate locations of the three delaminations are as follows: 11 x 3 (3.4 m x 0.9 m) delamination at mid-height of the south girder (see Figure 10); 4 x 1 (1.2 m x 0.3 m) delamination at the centerline of the bridge at the base of the wall; and 15 x 3 (4.6 m x 0.9 m) delamination at mid-height of the north girder (see Figure 11). It is recommended that all concrete delaminations in the west abutment be repaired (Rehabilitation Item R-2). Figure 10: Ballast Wall Delamination Figure 11: Ballast Wall Delamination West Abutment South End West Abutment North End Bridge No

16 3.5 Concrete Piers Piers 1, 2, 5 and 6 consist of a concrete cap beam supported on concrete columns. The columns are founded on separate buried spread footings which were not directly inspected. The concrete on Pier 1 and Pier 6 is generally in good condition with some localized areas with delaminations. A vertical crack is present in the east face of north leg of Pier 6. The crack coincides with the location of the drainage downpipe anchor bolts. The crack is not believed to be a significant structural concern and no repairs are recommended. On Pier 2 and Pier 5 the tops of the column legs and the crossbeams contain extensive cracking, delaminations and spalling of concrete on all faces. At both of these piers large areas of exposed and corroding reinforcement is visible. Given the large areas of delaminated concrete identified at Piers 2 and Pier 5, it is recommended that a rehabilitation program be undertaken (Rehabilitation Item R-3). Figure 12: Vertical Crack in Pier 6 - North Pier Leg 10 Bridge No

17 Figure 13: Vertical Crack in Pier 6 - North Pier Leg Figure 14: Delaminations at Pier 5 Top of Pier Leg Bridge No

18 Figure 15: Delaminations at Pier 2 West Face of Crossbeam Figure 16: Delaminations at Pier 2 - Soffit of Crossbeam 12 Bridge No

19 3.6 Steel Piers Piers 3 and Pier 4 are vertical steel frames consisting of two vertical steel legs braced by diagonal X-bracing. Each steel leg is supported by a reinforced concrete pedestal/ footing that also supports the inclined steel frames comprising the delta pier. The inclined legs of the delta pier are also comprised of a pair of steel legs braced by diagonal X-bracing. The vertical and inclined pier legs at Pier 4 are shown in Figure 17. The uppers portions of the steel piers at Pier 3, Pier 4 and at the apex of the delta pier are all in generally good condition with minor coating failure and localized surface corrosion observed during the inspection, as shown in Figure 18. The condition of the lower portions of steel at Pier 3 and Pier 4 is fair with coating failure and light surface corrosion. No section loss was observed. Figure 17: Vertical and Inclined Pier Leg at Pier 4 Bridge No

20 Figure 18: Inclined Steel Legs at Delta Pier Steel Pier Foundations The Pier 3 and Pier 4 foundations consist of concrete footings cast into the sloped embankments below the bridge Pier 3 Footings The condition of the Pier 3 foundation concrete is rated as good with minor spalling and small delaminations in a small number of locations. However, significant erosion and undermining has occurred on the downhill side of the foundations raising stability concerns, as seen in Figure 19, Figure 20 and Figure 21. B&T is of the understanding that the stability of the foundations is currently being investigated by BCMOT and Tetra Tech and that since the inspection, soil/rock anchors have been installed in an effort to stabilize the foundations. Additionally, it has been reported that the steel pier legs at Piers 3 and 4 may be bowed out of a straight alignment. A bow was observed by B&T at the top of the south vertical leg at Pier 4 but it is unknown if this bow is related to foundation movement or is related to the original construction. It is recommended that in addition to stabilizing the foundations, that the verticality and straightness of the steel pier legs be reviewed as movement or rotation of the foundation can lead to unintended stresses in the pier legs that can impact their capacity. 14 Bridge No

21 Figure 19: Pier 3 North (Left) and South (Right) Foundations Figure 20: Soil Erosion below the South Leg Foundation of Pier 3 Bridge No

22 Figure 21: Soil Erosion below the North Leg Foundation of Pier Pier 4 Footings The Pier 4 footings are in similar condition as the Pier 3 footings but with less erosion observed (see Figure 23). The concrete is in fair to good condition with some minor spalling, localized pitting and small delaminations in a small number of locations. A small spall is present below the east face of the pedestal at the base of the north leg diagonal member. The spall represents an area of reduced concrete cover to the anchor bolts and it is recommended that the concrete be repaired (Maintenance Item M-3). A failed repair patch is present at the base of the south leg diagonal, as shown in Figure 22 which also represents an area of reduced cover and it is recommended that this area also be repaired as part of Maintenance Item M Bridge No

23 Figure 22: Delamination at the Base of Pier 4 South Leg Figure 23: Pier 4 South (Left) and North (Right) Foundations Bridge No

24 Accumulations of soil and loose rock has built up around the north pier leg; see Figure 24 and Figure 25. In addition to loading the pier leg in an unintended manner, this material can lead to deterioration of the protective coating on the steel. It is recommended that the material be removed and measures be taken to prevent material from building up around the steel pier legs (Rehabilitation Item R-4). It was noted that some work had been started at the time of the inspection to remove this overburden material. Figure 24: Soil at Pier 4 North Vertical Figure 25: Soil at Pier 4 North Vertical Similar to the foundations at Pier 3, the soil around the south leg of Pier 4 is eroding raising stability concerns, as seen in Figure 26. The same recommendations made for the Pier 3 foundations are made for the south leg of the Pier 4 foundations. 18 Bridge No

25 Figure 26: Soil Erosion around the South Leg Foundation of Pier Bearings There are two different styles of fixed bearings, and one typical style of expansion bearing on the structure, as discussed in the following sections Expansion (Sliding) Bearings - At Abutments The east and west abutment sliding bearings are comprised of a steel sole plate, welded to the girder bottom flange and a steel masonry plate that is fixed to the concrete pedestal, with a steel bearing plate in between. The top of the bearing plate is fitted into a notch in the sole plate to permit longitudinal movement of the girder, but restricts movement in the transverse direction. Two hold-down anchors per bearing pass through slotted holes in the sole plate to accommodate the longitudinal movements in the bearing. The general arrangement of an abutment bearing is shown below in Figure 27 and Figure 28. Bridge No

26 Figure 27: East Abutment North Bearing Figure 28: West Abutment North Bearing Widespread coating failure and light to moderate surface corrosion was observed on the bearing steel, as seen in Figure 29. No visual evidence of recent bearing movement was observed and it is possible that the bearings may be seized. It is recommended that markings be installed on the bearings to monitor for thermal movement and that bearing rehabilitation be considered if no evidence of movement is found (Study Item S-1). Figure 29: Surface Corrosion NE Bearing 20 Bridge No

27 An anchor bolt for the south bearing on the east abutment has failed or been removed, as seen in Figure 30. It is recommended that the requirement for this anchor be assessed and the connection be restored if deemed structurally necessary (Study Item S-1). Nesting material was observed on the steel members in the vicinity of the west abutment, including the area surrounding the south bearing. It is recommended that the nesting materials be removed (Maintenance Item M-4). Figure 30: Hold-Down Anchor SE Bearing Expansion (Sliding) Bearings At Pier 2 and Pier 5 The bearings at Pier 5 and Pier 2 are of similar type to the abutment expansion bearings. It was observed that although the bearings on the east side of Pier 2 are shown on the original design drawings as fixed bearings they are actually sliding bearings. At each of these locations the bearings are subject to medium to heavy corrosion throughout with some small loss of section in the bearing plates, see Figure 31. There is significant build-up of roadway debris to the inside top surfaces of the bearings at these piers. Bridge No

28 The anchor bolts on both the north and south bearings on the east side of Pier 5 have broken off while the anchor bolts at the west side of Pier 2 are inclined towards the east, as shown in Figure 32. These observations suggest that the girders spanning between Pier 2 and Pier 5 are undergoing longitudinal movement in excessive of the range provided by the bearings. It is recommended that the expansion bearings at Pier 2 and Pier 5 be cleaned, painted and repaired, with any damaged anchor bolts being replaced following an assessment of bearing requirements (Rehabilitation Item R-5 and Study Item S-2). Figure 31: Pier 5 Bearing at Northeast 22 Bridge No

29 Figure 32: Pier 2 Bearing at Northwest Inclined Anchor Bolt Fixed Bearings At Pier 1 and Pier 6 The north and south girders are continuous over both Pier 1 and Pier 6. At these pier locations each girder passes over a single fixed bearing. The bearings consist of a sole plate welded to the bottom flange of the girders. The sole plate bears on a convex surface of a bearing plate that is welded to a masonry plate. Anchor bolts connect the masonry plates to the concrete cap beams. A typical fixed bearing at these locations is shown in Figure 33. These bearings were observed to be in good condition at all locations, with small areas of coating failure and surface corrosion observed. No maintenance is recommended for these bearings at this time. Bridge No

30 Figure 33: North Bearing at Pier Fixed Bearings at Pier 3, Pier 4 and the Apex of Delta Pier The bearings at Pier 3, Pier 4 and at the apex of the delta pier are steel rocker bearing assemblies. The bearings consist of steel bearing plates welded to the bottom of the girder bottom flange and the top of the pier leg column, with a rotational pin connection in between. These bearings are fixed against translation but allow for rotation. Apart from localized coating failure and light surface corrosion, the bearings are generally in good condition. 24 Bridge No

31 Figure 34: Pier 4 North Bearing Figure 35: Bearing at Apex of Delta Pier South Bearing Shown Bridge No

32 3.8 Longitudinal Girders and Transverse Floorbeams Longitudinal Girders The longitudinal girders are riveted plate girders. Girders are continuous between the east abutment and Pier 2, between Pier 2 and Pier 5, and between Pier 5 and the west abutment. K-bracing oriented in the vertical plane connects the girders every 15 ft. (4.5 m) while plan X-bracing connects the girder top and bottom flanges throughout. Generally, the longitudinal girders are in fair to good condition with light to medium surface corrosion and coating failure at a number of locations, particularly at exterior sides of girder webs and at the exterior edges of bottom flanges. More advanced corrosion is present on the girders in the vicinity of the expansion joints at Piers 2 and 5, see Figure 36 and Figure 37. It is recommended that the ends of the girders and bearing stiffeners at Pier 2 and Pier 5 are cleaned and repainted (Rehabilitation Item R-6). Figure 36: Exterior Face of North Girder at Pier 5 26 Bridge No

33 Figure 37: Exterior Faces of North Girder at Pier Transverse Floorbeams The floorbeams are rolled WF-type sections spaced at 7.5 ft. (2.3 m) centres and sit on top of the top flanges of the longitudinal girders. With the exception of the floorbeams adjacent to the deck joints at Piers 2 and 5, the floorbeams are in good condition with minor coating failure and light surface corrosion. The floorbeams at Piers 2 and 5 exhibit widespread coating failure and more advanced surface corrosion which is believed to be due to leaking deck joints. The corrosion is generally located on the top and bottom flanges, as seen in Figure 38, and also at the webs of the end of the floorbeam cantilevers, as shown in Figure 39. Some rust jacking of the concrete deck up off of the floorbeams has been observed due to corrosion of the floorbeam top flanges. It is recommended that the transverse floorbeams at Pier 2 and Pier 5 be cleaned and repainted (Rehabilitation Item R-6). It was observed that some rust jacking may of the deck up off the top flange may be occurring at the abutments as evident by the deck deflections at the second floorbeam and the squeaking noises with passing live load. Bridge No

34 Figure 38: North Floorbeam Cantilevers at Pier 5 Figure 39: North Floorbeam Cantilevers at Pier 5 Looking East 28 Bridge No

35 3.9 Bracing/Diaphragms All of the bracing members, whether plan bracing or K-bracing consist of back-to-back angle sections. The majority of the bracing members are in good condition with only light corrosion and minor coating failure noted. However K-bracing members at Pier 2 and Pier 5 have heavy corrosion due to leakage from expansion joints above, as seen in Figure 40. It is recommended that the bracing at these locations, including all connections, be cleaned and repainted (Rehabilitation Item R-6). Figure 40: K-Bracing Diaphragm at Pier 2 Bridge No

36 Figure 41: K-Bracing Diaphragm at Pier 5 Short bracing angles connect the floorbeams to the longitudinal girders at Pier 2, Pier 5 and both abutments. Cracks have previously been identified at all brace locations in the base plate just above the angle brace and have been marked with red paint, as seen in Figure 42. Because the base plate is bolted to the floorbeam, it is unlikely that the crack will propagate into the floorbeam web and no rehabilitation is recommended. However, it is recommended that the cracks be reviewed during future inspections (Inspection Item I-1). 30 Bridge No

37 Figure 42: Cracks in Baseplate of Bracing Angle Pier 5 Shown (Indicated by Red Arrow) Figure 43: Connection of Bracing and Girder Bridge No

38 3.10 Deck The bridge deck is a cast-in-place concrete deck with expansion joints located at Pier 2, Pier 5 and the east and west abutments. Concrete parapets, cast integral with the deck, are located on each side of the deck and there are no concrete curbs or sidewalks Concrete Roadway Deck Visual inspection and non-destructive testing of the concrete roadway deck surface found that the deck is generally in fair condition with a number of concrete delaminations, totaling approximately 3% of the area. All identified delaminations were marked with spray paint and their areas recorded. The results of the chain dragging are presented in Table 1. Table 1: Concrete Roadway Deck Surface Delaminations Location Approx. Area of EB Delamination Approx. Area of WB Delamination Approx. Total Delamination Area Total Deck Area in Span % of Deck Delamination East Abut. Bent ft 2 58 ft ft ft 2 16% Bent 1 Bent 2 68 ft 2 3 ft 2 71 ft ft 2 5% Bent 2 Bent 3 16 ft 2 7 ft 2 23 ft ft 2 2% Bent 3 Bent 4 15 ft 2 10 ft 2 25 ft ft 2 <1% Bent 4 Bent 5 0 ft 2 10 ft 2 10 ft ft 2 <1% Bent 5 Bent 6 7 ft 2 56 ft 2 63 ft ft 2 4% Bent 6 West Abut. 2 ft 2 10 ft 2 12 ft ft 2 <1% Totals 297 ft ft ft ft 2 3% 32 Bridge No

39 Figure 44: Deck Delaminations in the Eastbound Lane Near the East Abutment Deck Joints The deck joints at Pier 2, Pier 5 and both abutments consist of steel armor plates and rubber compression seals. Generally, the joint seals extend into the edge barriers and terminate on an incline near the back of the barrier, with the exception of the north end at the east abutment where the seal terminates at the toe of the barrier. As a result of previous modifications to the deck, the steel armor plates do not extend to the barrier. Based on the presence of concrete patches on either side of the joints, it is believed that the joints have been replaced previously, as seen in Figure 45 and Figure 46. Bridge No

40 Figure 45: Exp. Joint at Pier 5 Figure 46: Exp. Joint at East Abutment The rubber joint seals were observed to be in fair condition, however the joints themselves were not consistently sealed across the deck which can allow water to pass through the joints. Gaps were observed between the seal and the angle armouring, as seen in Figure 47, and also between the armouring steel and the deck concrete, as seen in Figure 48. The armouring steel has not been extended to the edge of the deck at the north end of the east abutment and the rubber seal is adhered to the concrete, as seen in Figure 49. It is recommended that the joints be properly sealed to prevent further water penetration (Maintenance Item M-5). 34 Bridge No

41 Figure 47: Gap in West Abutment Expansion Joint Seal Figure 48: Gap in Pier 5 Expansion Joint Bridge No

42 Figure 49: Expansion Joint Seal Adhered to the Concrete Barrier at the East Abutment Deck Drains Due to the super-elevated geometry of the bridge deck, all of the deck drains are located on the north side of the bridge at each of the piers as well as at the west abutment. While the deck drains are no longer located at the base of the edge barriers (the result of replacing the parapets with a narrower curb-less design) efforts have been made to taper the surrounding deck surface to promote water flow into the drains, though it is expected that some water will still bypass the drain and run across the expansion joints. The deck drain at Pier 5 is shown in Figure 50. Below the deck, each drain pipe is extended down to the base of each pier and further piped or channeled away from the pier base and embankment areas to mitigate slope degradation. 36 Bridge No

43 Figure 50: Deck Drain at North End of Pier 5 Expansion Joint 3.11 Parapets The original barriers and curbs have been replaced by a solid concrete parapet. The parapet is integral with the bridge deck and stands 32" (810 mm) tall (as measured from the top of the deck). The parapets are generally in good to fair condition with small cracks, pitting and scrapes from snow plows, as seen in Figure 51. Several reflectors have also been damaged and/or broken off and it appears that several cracks in the barriers have been injected with epoxy. Bridge No

44 Figure 51: Typical Condition of Concrete Edge Barrier (North Barrier Shown) The edge of the bridge deck appear to have been replaced when the new parapets were constructed as evidenced by the presence of a cold joint approximately 12" (300 mm) from the toe of the barrier, as seen in Figure 51. This joint is also visible on the deck soffit, as seen in Figure 52. Localized spalls were observed at the joint location, as seen in Figure 53, and it is recommended that these spalls be repaired (Maintenance Item M-6). Figure 52: Joint in Deck from Parapet Figure 53: Spalling at Joint Location Construction 38 Bridge No

45 4 Recommendations Buckland & Taylor 2014 Inspection of the found that most structural components of the bridge are generally in fair to good condition. Deficiencies were identified for some components. A series of recommendations have been developed based on the inspection results and these recommendations have been broken into the following four categories: Maintenance Items: those items that require action; Inspection Items: those items that require continued monitoring; Rehabilitation Items: those items requiring specialized funding or equipment or of sufficient size to be beyond the scope of a maintenance contract; and Study Items: those items that require specialized inspections or investigation. Each item is assigned a priority rating of 1, 2 or 3 indicating the work related to that item should be performed within the next 1, 5 or 10 years, respectively. The list of recommendations is as follows: Maintenance Items: Item Description Priority Rating M-1 Repair Cracks in Approach Roadway Asphalt; refer to Section Replace eroded material behind abutment back walls and modify drainage M-2 to prevent recurrence; refer to Section M-3 Repair concrete deterioration art Pier 4 footings; refer to Section Remove nesting material from steelwork at the west abutment; refer M-4 to Section Seal gaps between joint seals and armouring steel and concrete; refer M-5 to Section M-6 Repair spalls in deck soffit at cold joint location; refer to Section Inspection Items: Item I-1 Description Monitor condition of cracks in base plate for bracing angles at Pier 2, Pier 5 and abutment floorbeams; refer to Section 3.9. Priority Rating 2 Bridge No

46 Rehabilitation Items: Item R-1 R-2 R-3 R-4 R-5 R-6 Description Repair concrete delaminations and areas of deterioration at east abutment; refer to Section Repair concrete delaminations at west abutment back wall; refer to Section Repair areas of concrete delamination and spalling at Piers 2 and 5; refer to Section 3.5. Remove buildup of soil and rock and install measures to prevent recurrence at base of Pier 4; refer to Section Clean and recoat bearing steel at Pier 2 and 5 and replace anchor bolts if deemed necessary from Study Item S-2; refer to Section Clean and recoat steelwork adjacent to joints at Piers 2 and 5; refer to Section 3.8.1, and 3.9. Priority Rating Study Items: Item S-1 S-2 Description Install markings on abutment bearings to determine if they are moving and assess requirement for hold down anchors on expansion bearings; refer to Section Assess requirement for hold down anchors on bridge bearings at Pier 2 and 5; refer to Section Priority Rating Bridge No

47 5 Summary and Conclusions Buckland & Taylor was retained by the BC Ministry of Transportation and Infrastructure to conduct detailed inspections as part of the 2014 Enhanced Bridge Inspection Program. This report pertains to the condition inspection of Quartz Creek Bridge No The inspection identified areas of delaminated concrete on the backwalls of both abutments, large areas of spalled concrete on the concrete pier legs and crossbeams. Coating failure with varying degrees of corrosion on the steel components was also observed in the vicinity of the deck joints at the abutments and Piers 2 and 5, including stringers, floorbeams, bracing and bearings. Undermining and erosion were observed at the Pier 3 and 4 foundations raising stability concerns and it is noted that the BCMOT has since had rock anchors installed at these locations. Based on the inspection results, a series of recommendations expressed in terms of Maintenance Items, Inspection Items, Rehabilitation Items and Study Items were proposed to address the relatively minor deterioration and deficiencies observed during this inspection and a priority rating has been assigned to these recommended items. Bridge No

48

49 Appendix A General Arrangement of Existing Bridge Bridge No A-1

50

51 Appendix B BC Condition Bridge No B-1

52

53

54

2011 BRIDGE INSPECTION REPORT

2011 BRIDGE INSPECTION REPORT 2011 BRIDGE INSPECTION REPORT BYRD PARK PUMP STATION BRIDGE OVER KANAWHA CANAL April 2011 FINAL December 2011 Looking - from Abutment B to Abutment A Prepared by: WHITMAN, REQUARDT, & ASSOCIATES, LLP 9030

More information

Four simply supported steel plate girders (appear to be an old railcar).

Four simply supported steel plate girders (appear to be an old railcar). BRIDGE INSPECTION BRIDGE NO./NAME N4-005: Akolkolex Crawford FSR (19.0 km) Inspection Date: September 22 nd, 2012 Inspected By: M. Hanson, R. Veitch Year Built: 1982 Number of Spans: 1 Span Lengths: Superstructure

More information

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017 Introduction Substructure Inspection and Rating That portion of the bridge located below the bearings Abutments Piers Rated separately Purpose is to: Receive the loads from the superstructure Transfer

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT STATE BRIDGE NO. 6081 CITY OR COUNTY 053 LOUDOUN TYPE OF BRIDGE REPORT: REGULAR INSPECTION JANUARY 2016 BRIDGE NAME: DIRECTION: FOREST MILLS

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 4992 CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA IRFAN A. ALVI, P.E., Alvi Associates, Inc., Baltimore, MD IBC-02-25 KEYWORDS: box girder, counterweight abutment, curved girder, high-performance

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7685 CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7883 CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

Appendix C Guidelines for Design of Integral Abutments March 3, 2003

Appendix C Guidelines for Design of Integral Abutments March 3, 2003 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT s and the UK Highways Agency. They provide guidance and outline the issues that need to be considered and should

More information

APPENDIX A INTEGRAL ABUTMENTS

APPENDIX A INTEGRAL ABUTMENTS APPENDIX A INTEGRAL ABUTMENTS Appendix A Guidelines for Design of Integral Abutments Rev. 1 - September, 2007 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT

More information

Conditional assessment of Kiri Bridge in Shkoder, Albania

Conditional assessment of Kiri Bridge in Shkoder, Albania Conditional assessment of Kiri Bridge in Shkoder, Albania Gentian Rexhaj 1, Enea Mustafaraj 2 1 2 Department of Civil Engineering, Epoka University, Albania 2 Department of Civil Engineering, Epoka University,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 36508 CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 89188 7 th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER OCTOBER 2, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

Semi-Integral Abutment Bridges

Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Leslie Street Over Hwy 407 Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Semi-Integral Abutment Bridges

More information

PENNDOT e-notification

PENNDOT e-notification PENNDOT e-notification Bureau of Design Engineering Computing Management Division BRADD No. 027 August 30, 2010 Release of Version 3.1.5.0 PennDOT's Bridge Automated Design and Drafting Software (BRADD)

More information

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK Joseph Navarra, P.E, Maryland State Highway Administration, 410-545-8315, jnavarra@sha.state.md.us ABSTRACT The MDSHA

More information

\\H\15\ PH9 Inspection Photos

\\H\15\ PH9 Inspection Photos SHOP SLIDE Photo 1. at cracking across the footpath at the end of the Hwy 2 EB to Hwy 684 SB off ramp at the 99 Ave. intersection. Drop in asphalt trail (background) has worsened since 2013 and is now

More information

Integral Abutment Bridge Design with Soil Structure Interaction

Integral Abutment Bridge Design with Soil Structure Interaction Integral Abutment Bridge Design with Soil Structure Interaction Thursday, May 11, 2017 3:00 PM 4:00 PM EST Speaker Engineer: Suthichai Saelim Project Location WESTBOROUGH Railroad HOPKINTON Project Location

More information

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection No. 1 2/26/2016 830 MSE Wall V 26 Is ADE 830 MSE Wall to be used in conjunction with NBE 218 Other Abutment

More information

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN 7-1.0 INTRODUCTION 7-2.0 RIGID PAVEMENT DESIGN 7-2.01 Cross Sections 7-2.02 Ramps and Loops with Storage Area 7-2.03 Major Forks, Branch

More information

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014 Updated: 5/15/14 1 What was driver for deciding to slide vs. roll? Overall weight? 2 1. Why the two different slide methods? 2. How much experience should your contractor have to perform the slide work?

More information

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint Introduction The purpose of this white paper is to provide information regarding the potential for fractures

More information

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples BY MARTIN P. BURKE, JR. Innumerable bridges both in the U.S. and abroad have been, and continue to be, damaged by the restrained growth

More information

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and Overview Design criteria for I-90 over Kishwaukee Integral Abutment Bridges (IAB) Design Criteria Design analysis, details and construction Lessons Learned during construction Instrumentation by Illinois

More information

Ahmed Mongi, M.S., P.E. Engineering Division

Ahmed Mongi, M.S., P.E. Engineering Division 1 Ahmed Mongi, M.S., P.E. Engineering Division 2 Honey Creek Bridge Completed in 2006 at a cost of $2.6 Million Precast pier caps and abutments. 3 Honey Creek Bridge Bridge closed for 60 days Simple span

More information

Integral bridges and environmental conditions

Integral bridges and environmental conditions Integral bridges and environmental conditions COMISU CLAUDIU-CRISTIAN, BOACĂ GHEORGHITĂ Department of Roads and Foundations Faculty of Civil Engineering and Building Services The "Gheorghe Asachi" Technical

More information

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS Louis J. Ruzzi P.E., PennDOT District 11-0 Bridge Engineer John Myler, PennDOT Assistant Construction Engineer, District 11-0 Bala

More information

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A construction camera has been installed to view images of the bridge construction. Images are updated on

More information

Appendix B. Shallow Foundations Report

Appendix B. Shallow Foundations Report 12/10/2013 GEOTECHNICAL MANUAL Appendix B. Shallow Foundations Report PLEASE NOTE A sample foundations report is included here for reference. It is provided as an example of content, format, and organization

More information

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION 3.2.5.0 Since the release of BRADD Version 3.2.4.3, several operational issues have been addressed. This release of BRADD Version 3.2.5.0 contains the following

More information

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report Final Report VTRC 06-R35 Virginia Transportation Research Council research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report http:/www.virginiadot.org/vtrc/main/online_reports/pdf/06-r35.pdf

More information

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue FHWA Rhode Island Showcase October 30, 2014 Accent image here Primary Image here Presentation Outline Overview of the Project Scope ABC Project

More information

BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE

BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE Paul J. Barr Marv W. Halling Conner Huffaker Hugh Boyle Utah State University Department of Civil and Environmental Engineering Logan, Utah September

More information

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse)

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) AGENDA Project Overview and Need Design and Special Provisions Construction Engineering

More information

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 SITE NUMBER AND NAME: NC 52 Pembina River Bridge LEGAL DESCRIPTION: SE 1-50-9-W5M STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 NAD 83 COORDINATES:

More information

Shifting the Canning Bus Bridge Sideways

Shifting the Canning Bus Bridge Sideways Shifting the Canning Bus Bridge Sideways Ros MacKinlay Design Engineer, Wyche Consulting SYNOPSIS The Perth Mandurah railway proposed in 2002 required the replacement of an existing Kwinana Freeway bus

More information

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge Modular Steel Bridges Stark County Fischer Bridge Bottineau County Oak Creek Bridge This John Deere grain hauler was too heavy for the bridge. OOPS! An excavator and tow truck are needed to remove the

More information

Emergency Bridge Stabilization at Mile Watrous Subdivision

Emergency Bridge Stabilization at Mile Watrous Subdivision Emergency Bridge Stabilization at Mile 189.70 Watrous Subdivision Christophe Deniaud, Ph.D., P.Eng. Bridge Engineer, CN 10004-104 Avenue Edmonton, Alberta, Canada T5J 0K2 Tel: (780) 421-6021 Fax: (780)

More information

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes J. H. Wood John Wood Consulting, Lower Hutt. ABSTRACT: 2012 NZSEE Conference Twelve State Highway (SH) bridges subjected

More information

DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA

DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA Brian Lord, Arup Pty Ltd, Australia ABSTRACT Arup was lead designer for Lend Lease on the Victoria Park Drive Modifications

More information

2017 UNDERWATER BRIDGE INSPECTION REPORT. TWP 332 over ROOT RIVER. Date of Inspection: Equipment Used: 10/22/2016. Town or Township Highway Agency

2017 UNDERWATER BRIDGE INSPECTION REPORT. TWP 332 over ROOT RIVER. Date of Inspection: Equipment Used: 10/22/2016. Town or Township Highway Agency 2017 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # L4870 TWP 332 over ROOT RIVER DISTRICT: District 6 COUNTY: Fillmore CITY/TOWNSHIP: JORDAN STATE: Minnesota Date of Inspection: Equipment Used: 10/22/2016

More information

Update on Seismic Behavior and Design of

Update on Seismic Behavior and Design of Update on Seismic Behavior and Design of Steel Plate Girder Bid Bridges Ahmad M. Itani, Ph.D., P.E., S.E. Professor Department of Civil and Environmental Engineering University of Nevada, Reno Background

More information

1 Study the drawings and the installation. 2 Ensure that you have the correct components. 3 Follow the manufacturer s instructions

1 Study the drawings and the installation. 2 Ensure that you have the correct components. 3 Follow the manufacturer s instructions 1 Study the drawings and the installation plan ahead of time. Consider laying the components out in the approximate order in which they will be installed. This will help workers become familiar with the

More information

Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures

Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures InTrans Project Reports Institute for Transportation 9-2015 Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures Brent Phares Institute for Transportation, bphares@iastate.edu

More information

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill. Bridge Applications Technology The Reinforced Earth Company (RECo) offers a variety of bridge abutment and bridge crossing solutions, each are based on project specific requirements. Bridge abutments are

More information

Bahavior and Analysis of an Integral Abutment Bridge

Bahavior and Analysis of an Integral Abutment Bridge Utah State University DigitalCommons@USU All Graduate Theses and Dissertations Graduate Studies 2013 Bahavior and Analysis of an Integral Abutment Bridge Conner D. Huffaker Follow this and additional works

More information

OVER US 6 LATERAL BRIDGE SLIDE: I-75

OVER US 6 LATERAL BRIDGE SLIDE: I-75 LATERAL BRIDGE SLIDE: I-75 OVER US 6 Bob Beasley, PE, Ohio Bridge Manager, Arcadis U.S., Inc. Todd Lezon, Regional Manager, Kokosing Construction Company, Inc. November 4, 2016 1 Agenda Design Bob Beasley,

More information

CHAPTER 5 MODELING OF THE BRIDGE

CHAPTER 5 MODELING OF THE BRIDGE 62 CHAPTER 5 MODELING OF THE BRIDGE 5.1 MODELING SAP2000, a nonlinear software package was used for modeling and analysing the study bridge. The following list provides details about the element type used

More information

STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END

STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END by Zhengyu Liu Research Team: Zhengyu Liu, Graduate Research Student, Bridge Engineering Center, Iowa State University Brent M Phares, Director,

More information

Numerical analysis of the embedded abutments of integral bridges

Numerical analysis of the embedded abutments of integral bridges Numerical analysis of the embedded abutments of integral bridges Ming XU Researcher, Dept. of Civil & Env. Engrg., University of Southampton, UK Summary Alan G. BLOODWORTH Lecturer, Dept. of Civil & Env.

More information

5 DAMAGE TO TRANSPORTATION FACILITIES

5 DAMAGE TO TRANSPORTATION FACILITIES 5 DAMAGE TO TRANSPORTATION FACILITIES In the Kocaeli, Turkey earthquake of August 17, 1999, extensive damage of transportation facilities occurred in the Kocaeli and Sakarya region, Turkey as shown in

More information

Potholes: Prevent Before They Present

Potholes: Prevent Before They Present : Prevent Before They Present Dave Bergner, M.A., PWLF Mike Hale, P.E., P.L.S, M.S.C.E. TRB/ AASHTO Transportation Infrastructure Maintenance and Operations Conference, July 21, 2015 Des Moines, IA c.

More information

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments A.M. Morsy. Department of Civil, Architectural, and Environmental Engineering, The University of Texas

More information

Using the sharp-crested weir formula the outflow was:

Using the sharp-crested weir formula the outflow was: Date: 2009 July 16 11:00 AM 14 Island Lake Dam Inspection Report Persons Present: Bryon Keene, P.Eng. Harry Stinson Brett Dark (14 Island Lake Association) Peter Peart (14 Island Lake Association) The

More information

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION 3.2.0.0 Since the release of BRADD Version 3.1.6.2, several major enhancements have been made to the software and many reported operational issues have been

More information

300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES

300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES 300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES BONACCI GROUP DOCUMENT HISTORY ISSUE REVISION DATE AUTHOR REVIEWER Issued for DTMR Review A October

More information

Integral Abutment Bridges Australian and US Practice

Integral Abutment Bridges Australian and US Practice Integral Abutment Bridges Australian and US Practice John Connal (M.Eng Sci., B.E. (civil) (Hons), Dip. C.E., F.I.E.Aust, M. ASCE, M. IABSE) Maunsell Australia Pty Ltd SYNOPSIS The structural system offered

More information

Figure 3: Analytic procedure

Figure 3: Analytic procedure International Journal of Scientific and Research ublications, Volume 7, Issue 5, May 2017 567 Investigation of Integral Bridge Effect under Dynamic Loading Haymanmyintmaung *,kyawlinnhtat ** * Department

More information

Critically damaged bridges & concepts for earthquake recovery

Critically damaged bridges & concepts for earthquake recovery Critically damaged bridges & concepts for earthquake recovery J. Waldin, J. Jennings & P. Routledge Opus International Consultants Ltd, Christchurch, New Zealand 2012 NZSEE Conference ABSTRACT: This paper

More information

EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT

EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT Norton et al. Word Count: 8400 Tables: 5 Figures: 13 1 EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT Date submitted: 08/01/02 Date Revised and Resubmitted: 11/15/02

More information

Inspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin.

Inspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin. Inspection Report River Falls Hydroelectric Project FERC Project No. P-10489 Junction Falls Dam River Falls, Wisconsin Prepared for: River Falls Municipal Utilities River Falls, Wisconsin December 2009

More information

Keywords: integral abutment bridge, pile head abutment connection, finite element method.

Keywords: integral abutment bridge, pile head abutment connection, finite element method. Global Journal of Researches in Engineering: e Civil And Structural Engineering Volume 15 Issue 1 Version 1.0 Year 2015 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global

More information

Design of Dingley Bypass Integral Bridges

Design of Dingley Bypass Integral Bridges Design of Dingley Bypass Integral Bridges Dr. Kabir Patoary Principal Engineer Bridges GHD Elder St South Underpass Tekla Model Presentation Outline 1. Overview of Dingley Bypass 2. Design of Integral

More information

Comparative Study of Behaviour of Integral and Bearing Type Bridge under Temperature Loading

Comparative Study of Behaviour of Integral and Bearing Type Bridge under Temperature Loading IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 03, 2015 ISSN (online): 2321-0613 Comparative Study of Behaviour of Integral and Bearing Type Bridge under ing B. J. Shah

More information

DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE

DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE Abstract S. Hassiotis M. ASCE Stevens Institute of Technology, Hoboken, N.J. 07030 sophia.hassiotis@stevens.edu An integral-abutment bridge

More information

Effect of Pile Orientation in Skewed Integral Abutment Bridges

Effect of Pile Orientation in Skewed Integral Abutment Bridges Effect of Pile Orientation in Skewed Integral Abutment Bridges RABIH NAJIB, Ph.D., PE, Alpha Corporation, Baltimore, Maryland and AMDE M. AMDE, Ph.D., PE, University of Maryland, College Park, Maryland

More information

Winona Bridge Visual Quality Review Committee

Winona Bridge Visual Quality Review Committee Winona Bridge Visual Quality Review Committee Summary of Preferred Features October 7, 2014 Creating Bridges As Art 1 Summary of Preferred Features Based on Visual Quality Review Committee Final Design

More information

Low-Volume Road Abutment Design Standards

Low-Volume Road Abutment Design Standards Low-Volume Road Abutment Design Standards V.W. Robbins HNTB Corporation 7450 W. 130th St., Suite 400 Overland Park, KS 66213 vrobbins@hntb.com F. Wayne Klaiber Bridge Engineering Center 418 Town Engineering

More information

Independent Hybrid Corrosion Protection Appraisal

Independent Hybrid Corrosion Protection Appraisal Transportation Concrete Preservation Technologies Ltd 07/05/2015 Independent Hybrid Corrosion Protection Appraisal On behalf of: Concrete Preservation Technologies Ltd. Prepared by:... Checked by:... Wayne

More information

PRELIMINARY GEOTECHNICAL DESIGN

PRELIMINARY GEOTECHNICAL DESIGN PNCC Manawatu River Pedestrian/ Cycle Bridge PRELIMINARY GEOTECHNICAL DESIGN 1 Introduction Opus has been commissioned by the Palmerston North City Council (PNCC) to prepare a Detailed Business Case (DBC)

More information

COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES.

COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES. COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES Authors D. Nyborg, Research Physicist, TISEC Inc., Montreal;

More information

2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # CR

2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # CR 2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # 88756 CR 597 over RICE RIVER DISTRICT: District 1 COUNTY: St. Louis CITY/TOWNSHIP: ANGORA STATE: Minnesota Date of Inspection: Equipment Used: 06/21/2016

More information

Ashton Avenue Integral Bridge

Ashton Avenue Integral Bridge Ashton Avenue Integral Bridge Behzad Golfa, Senior Bridge Engineer, GHD Pty Ltd ABSTRACT The Ashton Avenue Bridge is a replacement of the original three-span timber bridge over Perth- Fremantle Rail line

More information

Clay Sewer Pipe-Joint Infiltration Leak-Rate Testing

Clay Sewer Pipe-Joint Infiltration Leak-Rate Testing Clay Sewer Pipe-Joint Infiltration Leak-Rate Testing 1. ABSTRACT While numbers of small to large older cities are undertaking repairs and maintenance, several other newer cities are planning on installing

More information

Forces in Wingwalls from Thermal Expansion of Skewed Semi-Integral Bridges

Forces in Wingwalls from Thermal Expansion of Skewed Semi-Integral Bridges Forces in Wingwalls from Thermal Expansion of Skewed Semi-Integral Bridges Eric Steinberg, Ph.D., P.E. Shad Sargand, Ph.D. for the Ohio Department of Transportation Office of Research and Development and

More information

Modified Sheet Pile Abutment for Low-Volume Road Bridge

Modified Sheet Pile Abutment for Low-Volume Road Bridge Modified Sheet Pile Abutment for Low-Volume Road Bridge Ryan R. Evans Department of Civil, Construction, and Environmental Engineering Iowa State University 176 Town Engineering Ames, IA 50011 ryevans@iastate.edu

More information

Detailed Seismic Assessment and Seismic Improvements of Market Road Underpass

Detailed Seismic Assessment and Seismic Improvements of Market Road Underpass Detailed Seismic Assessment and Seismic Improvements of Market Road Underpass D. Novakov, D. Ashby, T. Chin & A. George Opus International Consultants Ltd, Wellington - Auckland, New Zealand. G. Gregg

More information

Rahvusvaheline puitarhitektuuri konverents

Rahvusvaheline puitarhitektuuri konverents Experiences from Modern Timber Bridge Building Rahvusvaheline puitarhitektuuri konverents Tallinn 25-26.11.2015 Hauke Burkart NPRA Bridge Section Topics Short history of modern Norwegian timber bridges

More information

Precast Concrete Elements for Accelerated Bridge Construction

Precast Concrete Elements for Accelerated Bridge Construction Precast Concrete Elements for Accelerated Bridge Construction Volume 3. Laboratory Testing, Field Testing, and Evaluation of a Precast Concrete Bridge: Black Hawk County Final Report January 2009 Sponsored

More information

Aerial of Conceptual Path and Bridge Tysons-Old Meadow Road Bike/Ped Improvements

Aerial of Conceptual Path and Bridge Tysons-Old Meadow Road Bike/Ped Improvements Aerial of Conceptual Path and Bridge Barnes & Noble at One Place Project Location Corner Center Proposed Bridge Encore Condominiums Regency Club Condominiums Path continues to Dolley Madison Boulevard

More information

Structural health monitoring of the reinforced concrete plug joint system for existing concrete bridges

Structural health monitoring of the reinforced concrete plug joint system for existing concrete bridges Proceedings of the 9th International Conference on Structural Dynamics, EURODYN 214 Porto, Portugal, 3 June - 2 July 214 A. Cunha, E. Caetano, P. Ribeiro, G. Müller (eds.) ISSN: 2311-92; ISBN: 978-972-752-165-4

More information

Flume Installation Instructions

Flume Installation Instructions Flume Installation Instructions To ensure a successful installation, it is important to keep the following points in mind: 1) There should be no bend, dips, elbows, or flow junction immediately upstream

More information

EAH 422 ADVANCED WATER RESOURCES ENGINEERING

EAH 422 ADVANCED WATER RESOURCES ENGINEERING EAH 422 ADVANCED WATER RESOURCES ENGINEERING Bridge Hydraulics Prof. Aminuddin Ab. Ghani References The Art And Science Of River Engineering Bridge Failure Pier scour Pier scour Pier scour Bridge Failure

More information

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge R04 ABC Project Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge Lead Adopter SHRP2 Solutions Innovative

More information

AN EXPERIMENTAL INVESTIGATION ON BEHAVIOR OF RC PARAPET WALL OF ABUTMENT UNDER COLLISION

AN EXPERIMENTAL INVESTIGATION ON BEHAVIOR OF RC PARAPET WALL OF ABUTMENT UNDER COLLISION International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 9, September 2018, pp. 1831 1838, Article ID: IJCIET_09_09_177 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=9

More information

THERMAL BEHAVIOR OF IDOT INTEGRAL ABUTMENT BRIDGES AND PROPOSED DESIGN MODIFICATIONS

THERMAL BEHAVIOR OF IDOT INTEGRAL ABUTMENT BRIDGES AND PROPOSED DESIGN MODIFICATIONS CIVIL ENGINEERING STUDIES Illinois Center for Transportation Series No. 12-022 UILU-ENG-2012-2025 ISSN: 0197-9191 THERMAL BEHAVIOR OF IDOT INTEGRAL ABUTMENT BRIDGES AND PROPOSED DESIGN MODIFICATIONS Prepared

More information

Design of Picton Railway Overbridge for Mine Subsidence

Design of Picton Railway Overbridge for Mine Subsidence Design of Picton Railway Overbridge for Mine Subsidence Geraint Jones Long Bai Small Bridges Conference 24 November 2015 Introduction - Presentation Structure >Project Background >Longwall Mining >Location

More information

CORRIENTE RESOURCES INC.

CORRIENTE RESOURCES INC. CORRIENTE RESOURCES INC. MIRADOR PROJECT Bridge Review from Site to Puerto Bolivar, Ecuador OVER20YEARSOF SERVICE ConsultantsInternational Inc. 1983-2003 1212-750West Pender Street Vancouver BritishColumbia

More information

ACCELERATED BRIDGE REPLACEMENT

ACCELERATED BRIDGE REPLACEMENT Christopher Beck Chief Engineer: Bridge & Structures Northern Indiana Commuter Transportation District 601 North Roeske Avenue Michigan City, IN chris.beck@nictd.com Accelerated Bridge Replacement (ABR)

More information

An Integral Abutment Bridge with Precast Concrete Piles

An Integral Abutment Bridge with Precast Concrete Piles An Integral Abutment Bridge with Precast Concrete Piles Final Report May 2007 Sponsored by the Iowa Highway Research Board (IHRB Project TR-438) and the Iowa Department of Transportation (CTRE Project

More information

EFFECTS OF SKEWED ABUTMENTS ON CURVED BRIDGE CONSTRUCTION RESPONSE. Tyler Goodman. Spring 2013

EFFECTS OF SKEWED ABUTMENTS ON CURVED BRIDGE CONSTRUCTION RESPONSE. Tyler Goodman. Spring 2013 THE PENNSYLVANIA STATE UNIVERSITY SCHREYER HONORS COLLEGE DEPARTMENT OF CIVIL AND ENVIROMENTAL ENGINEERING EFFECTS OF SKEWED ABUTMENTS ON CURVED BRIDGE CONSTRUCTION RESPONSE Tyler Goodman Spring 2013 A

More information

Product Information Packet

Product Information Packet Product Information Packet Pendulum Full Rack Product Part Number: 410706 Patents: #D562670, Patent Pending Pendulum Full Rack shown with optional pull-up arches. Table of Contents Introduction..... 1

More information

L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015

L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015 Canterbury Bridge Group Ferrymead Bridge L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015 Presenter: Lloyd Greenfield Senior

More information

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Jeff Sizemore, P.E. Geotechnical Design Support Engineer SCDOT Ed Tavera, P.E. Principal Geotechnical Engineer Geoengineers

More information

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Filed: 2018-07-04, EB-2018-0108, Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889

More information

Evaluation of the Foundation and Wingwalls of Skewed Semi-Integral Bridges with Wall. Abutments. A thesis presented to.

Evaluation of the Foundation and Wingwalls of Skewed Semi-Integral Bridges with Wall. Abutments. A thesis presented to. Evaluation of the Foundation and Wingwalls of Skewed Semi-Integral Bridges with Wall Abutments A thesis presented to the faculty of the Russ College of Engineering and Technology of Ohio University In

More information

Field and Analytical Studies of the First Folded Plate Girder Bridge

Field and Analytical Studies of the First Folded Plate Girder Bridge University of Massachusetts Amherst ScholarWorks@UMass Amherst Masters Theses Dissertations and Theses 2014 Field and Analytical Studies of the First Folded Plate Girder Bridge Man Hou Sit University of

More information

EFFECTS OF SPATIAL VARIATION OF SEISMIC INPUTS ON BRIDGE LONGITUDINAL RESPONSE

EFFECTS OF SPATIAL VARIATION OF SEISMIC INPUTS ON BRIDGE LONGITUDINAL RESPONSE 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 24 Paper No. 64 EFFECTS OF SPATIAL VARIATION OF SEISMIC INPUTS ON BRIDGE LONGITUDINAL RESPONSE Jiachen WANG 1, Athol

More information

Integral Abutment Bridges-Development of Soil Model for Soil Structure Interaction in Time History Analysis

Integral Abutment Bridges-Development of Soil Model for Soil Structure Interaction in Time History Analysis International Journal of Engineering Research and Development e-issn: 2278-067X, p-issn: 2278-800X, www.ijerd.com Volume 10, Issue 3 (March 2014), PP.31-40 Integral Abutment Bridges-Development of Soil

More information