ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue

Size: px
Start display at page:

Download "ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue"

Transcription

1 ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue FHWA Rhode Island Showcase October 30, 2014 Accent image here Primary Image here

2 Presentation Outline Overview of the Project Scope ABC Project Planning ABC Design & Construction Construction / Contractor Perspective

3 FHWA Every Day Counts Initiative Designed to identify and deploy innovation aimed at shortening project delivery, enhancing the safety of our roadways and protecting the environment.

4 RIDOT Goals Safety Innovative Using Accelerated Bridge Construction Methods Precast substructure, PBE s Minimize Time Road closure eliminated phasing Cost Effective Balanced accelerating construction with user costs Efficient Intermodal Transportation Network Restored link from East Bay to Providence Crossing

5 RIDOT Goals (Continued) Public Attentiveness Minimize Public Impact Replace in 20 days with ABC, 2+ years conventional Increase Public Awareness City Officials Attended Council Meeting Outreach through multiple media venues: radio, social, paper, internet, link to web cam on DOT website, door to door with handouts

6 Overview of the Project Scope Accelerated Replacement of Bridge No. 465 I-195 On-Ramp (DR-2) over Warren Avenue

7 Site Location WB I-195 EB I-195 TAUNTON AVE N Bridge 465

8 Summary of Existing Bridge BRIDGE SUPERSTRUCTURE: Precast Prestressed Concrete I-beams and Reinforced concrete Tee beams BRIDGE SPAN: 3 simply supported spans of /8 (span 1) 61-1½ (span 2), /8 (span 3) BRIDGE WIDTH: SUBSTRUCTURE: 23 0 curb to curb, 28 2 out to out Unreinforced concrete gravity abutments on piles and two column reinforced concrete bents on piles BRIDGE SKEW: 25 o 9 6 BRIDGE SIDEWALKS: ROADWAY SURFACE: Safety walks on both sides 3 bituminous wearing surface

9 Existing Bridge Condition

10 Overview of Project Scope Bridge 465 Replace Superstructure & Piers Evaluate Abutments Consider Feasibility of ABC Methods I-195 Westbound On-Ramp Approaches Full Depth Construction for Bridge Replacement Guardrail Replacement Pavement Milling & Overlay Warren Avenue Sidewalk Replacement Wheelchair Ramp Upgrade Pavement Milling & Overlay WARREN AVE ON-RAMP TAUNTON AVE Bridge 465 N

11 Why ABC for New Bridge? No phase construction option due to narrow 23 0 roadway width Significant reduction of bridge closure time Detour options available Reduce impact to traffic and the public

12 ABC Project Planning Accelerated Replacement of Bridge No. 465 I-195 On-Ramp (DR-2) over Warren Avenue

13 FHWA Framework for Decision-Making

14 Rapid Onsite Construction Factors High Traffic Volumes YES Emergency Replacement Necessary YES Evacuation Route NO Required Lane Closures / Detours YES Impact on Total Project Critical Path YES Use Prefabrication

15 Closure of I-195 On-Ramp (Bridge 465) One Month Duration Closure of On-Ramp over Warren Ave

16 Closure of Ramps Two Weekends Closure of I-195 Off-Ramp (Exit 5) Two Weekends Closure of On-Ramp over Warren Ave & Closure of Warren Avenue below Bridge 465 (including sidewalks)

17 Milestones #1 Weekend Closure Demolition Re-Open Warren Ave and Exit 5 Ramp #2 Weekend Closure Place Superstructure Re-Open Warren Ave and Exit 5 Ramp #3 One Month Duration - Complete Bridge Construction Re-open On-ramp Traffic Over Warren Avenue #4 Substantial Completion Complete All Work for Bridge 465 And Warren Avenue.

18 Incentive / Disincentive #1 Completion of Weekend Closure #1 - $400 Per Hour Maximum Incentive $20,000 #2 Completion of Weekend Closure #2 - $400 Per Hour Maximum Incentive $20,000 #3 Bridge Open to Traffic $12,000 Per Calendar Day Maximum Incentive $120,000 Liquidated Damages Substantial Completion $1,500 Per Day

19 Incentive / Disincentive Vehicle Operating Cost Value of Travel Time Savings N Bridge 465 P

20 ABC Design & Construction Accelerated Replacement of Bridge No. 465 I-195 On-Ramp (DR-2) over Warren Avenue

21 Overview map Bridge 465 Constructed in 1959

22 Bridge 465 LBG Scope of Work Replace Superstructure & Piers Analyze Abutments & Wingwalls for LRFD Compliance Revise profile to meet 14-3 Minimum Clearance Consider ABC Methods

23 Bridge 465 Proposed Improvements & Deviation from Original Scope Full Bridge Replacement: Replace Superstructure Replace Abutments Replace Wingwalls Replace Pier Cap, Columns & Footings

24 Project ABC Methods and Techniques Prefabricated Bridge Elements & Systems (PBES) Modular Construction Structure Erection Techniques Geotechnical Techniques

25 Bridge 465 Prefabricated Elements STEEL BEAM

26 Bridge 465 Prefabricated Elements PRESTRESSED CONCRETE BEAMS AND PRECAST DECK PANELS

27 Bridge 465 Prefabricated Elements NEXT BEAM

28 Bridge 465 Prefabricated Elements Prefabricated Substructure

29 Bridge 465 Proposed Single Span Option 80 29

30 Bridge 465 Laydown Areas A B B

31 Proposed Transverse Section

32 Superstructure Modular Unit

33 Superstructure Modular Unit

34 FOUNDATION SUPPORT IMPROVEMENTS

35 Proposed Abutment

36 North Abutment Foundation

37 North Abutment Foundation

38 Abutment Footing Closure Pour

39 Abutment Footing Closure Pour

40 Precast Wingwall Footing

41 Precast Abutment Stem Elements

42 Precast Abutment Stem Elements

43 Precast Wingwall Stems & Footings

44 Precast Wingwall Stems & Footings

45 Completed Precast North Abutment

46 Completed Precast North Abutment

47 Remaining Construction Install bearing assemblies. Install superstructure modular units. Install diaphragms between beams S2 and S3. Form and place the reinforcement and concrete for the superstructure closure pour. Place the precast approach slabs and place the reinforcement and concrete for the approach closure pour. Form and place concrete for the safety barrier closure pour. Place the approach roadway base material. Place the bridge wearing surface. Install the strip seal at the north abutment and saw cut pavement and the south abutment.

48 Construction / Contractor Perspective Accelerated Replacement of Bridge No. 465 I-195 On-Ramp (DR-2) over Warren Avenue

49 History

50 Factors Considered Pre-Bid Fit for Aetna Bridge Incentive/Disincentive Duration of Project XXX

51 Key to Success Proper Planning Communication with Owner/Engineer Capable Resident Engineer Quality Subcontractors XXX

52 Challenges Tolerances for Precast Time Allowed for Submittals Precasters Preparedness (mass concrete, 3D modeling, schedule, etc) Area for Construction (equipment, fill, etc) XXX Unknowns weather, equipment breakdowns, etc.

53 Thank You David Fish, P.E. Managing Engineer, RIDOT Jessica Rodas Project Manager, RIDOT Phineas Fowler, P.E. Principal Structural Engineer, Louis Berger John Fitzgerald, P.E. Senior Structural Engineer, Louis Berger Jeffrey Bostock Vice President, AETNA Bridge Co.

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS Louis J. Ruzzi P.E., PennDOT District 11-0 Bridge Engineer John Myler, PennDOT Assistant Construction Engineer, District 11-0 Bala

More information

OVER US 6 LATERAL BRIDGE SLIDE: I-75

OVER US 6 LATERAL BRIDGE SLIDE: I-75 LATERAL BRIDGE SLIDE: I-75 OVER US 6 Bob Beasley, PE, Ohio Bridge Manager, Arcadis U.S., Inc. Todd Lezon, Regional Manager, Kokosing Construction Company, Inc. November 4, 2016 1 Agenda Design Bob Beasley,

More information

Ahmed Mongi, M.S., P.E. Engineering Division

Ahmed Mongi, M.S., P.E. Engineering Division 1 Ahmed Mongi, M.S., P.E. Engineering Division 2 Honey Creek Bridge Completed in 2006 at a cost of $2.6 Million Precast pier caps and abutments. 3 Honey Creek Bridge Bridge closed for 60 days Simple span

More information

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA IRFAN A. ALVI, P.E., Alvi Associates, Inc., Baltimore, MD IBC-02-25 KEYWORDS: box girder, counterweight abutment, curved girder, high-performance

More information

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK Joseph Navarra, P.E, Maryland State Highway Administration, 410-545-8315, jnavarra@sha.state.md.us ABSTRACT The MDSHA

More information

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge R04 ABC Project Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge Lead Adopter SHRP2 Solutions Innovative

More information

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A construction camera has been installed to view images of the bridge construction. Images are updated on

More information

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse)

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) AGENDA Project Overview and Need Design and Special Provisions Construction Engineering

More information

ACCELERATED BRIDGE REPLACEMENT

ACCELERATED BRIDGE REPLACEMENT Christopher Beck Chief Engineer: Bridge & Structures Northern Indiana Commuter Transportation District 601 North Roeske Avenue Michigan City, IN chris.beck@nictd.com Accelerated Bridge Replacement (ABR)

More information

Integral Abutment Bridge Design with Soil Structure Interaction

Integral Abutment Bridge Design with Soil Structure Interaction Integral Abutment Bridge Design with Soil Structure Interaction Thursday, May 11, 2017 3:00 PM 4:00 PM EST Speaker Engineer: Suthichai Saelim Project Location WESTBOROUGH Railroad HOPKINTON Project Location

More information

2011 BRIDGE INSPECTION REPORT

2011 BRIDGE INSPECTION REPORT 2011 BRIDGE INSPECTION REPORT BYRD PARK PUMP STATION BRIDGE OVER KANAWHA CANAL April 2011 FINAL December 2011 Looking - from Abutment B to Abutment A Prepared by: WHITMAN, REQUARDT, & ASSOCIATES, LLP 9030

More information

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN 7-1.0 INTRODUCTION 7-2.0 RIGID PAVEMENT DESIGN 7-2.01 Cross Sections 7-2.02 Ramps and Loops with Storage Area 7-2.03 Major Forks, Branch

More information

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and Overview Design criteria for I-90 over Kishwaukee Integral Abutment Bridges (IAB) Design Criteria Design analysis, details and construction Lessons Learned during construction Instrumentation by Illinois

More information

State-Aid Bridge News August 2, 2005

State-Aid Bridge News August 2, 2005 State-Aid Bridge News August 2, 2005 Bridge Hydraulic Information The FHWA has been inquiring about our Scour Program. In particular, there are two areas of concern; 1. Are our Scour Action Plans current

More information

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION 3.2.0.0 Since the release of BRADD Version 3.1.6.2, several major enhancements have been made to the software and many reported operational issues have been

More information

PENNDOT e-notification

PENNDOT e-notification PENNDOT e-notification Bureau of Design Engineering Computing Management Division BRADD No. 027 August 30, 2010 Release of Version 3.1.5.0 PennDOT's Bridge Automated Design and Drafting Software (BRADD)

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 4992 CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

Shifting the Canning Bus Bridge Sideways

Shifting the Canning Bus Bridge Sideways Shifting the Canning Bus Bridge Sideways Ros MacKinlay Design Engineer, Wyche Consulting SYNOPSIS The Perth Mandurah railway proposed in 2002 required the replacement of an existing Kwinana Freeway bus

More information

Community Meetings November 10 and 12, 2015

Community Meetings November 10 and 12, 2015 Metro Purple Line Extension Section 1 Community Meetings November 10 and 12, 2015 La Cienega Station Agenda Introduction Meeting Purpose Project toverview & Shdl Schedule Roadway Decking Installation Detour

More information

Semi-Integral Abutment Bridges

Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Leslie Street Over Hwy 407 Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Semi-Integral Abutment Bridges

More information

Appendix C Guidelines for Design of Integral Abutments March 3, 2003

Appendix C Guidelines for Design of Integral Abutments March 3, 2003 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT s and the UK Highways Agency. They provide guidance and outline the issues that need to be considered and should

More information

American Society of Highway. Beardsley Connector Project. Jacob Dean

American Society of Highway. Beardsley Connector Project. Jacob Dean American Society of Highway Engineers (ASHE) Beardsley Connector Project Gary Fromm, PE Design Manager Jacobs Jacob Dean Project Manager Haydon Building Corp. Thinking Outside the Box: Why Go In Circles?

More information

Four simply supported steel plate girders (appear to be an old railcar).

Four simply supported steel plate girders (appear to be an old railcar). BRIDGE INSPECTION BRIDGE NO./NAME N4-005: Akolkolex Crawford FSR (19.0 km) Inspection Date: September 22 nd, 2012 Inspected By: M. Hanson, R. Veitch Year Built: 1982 Number of Spans: 1 Span Lengths: Superstructure

More information

Pennsylvania s Experience with LRFD Implementation. By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation

Pennsylvania s Experience with LRFD Implementation. By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation Pennsylvania s Experience with LRFD Implementation By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation Overview Case History Spread Footing Width and Braking force Approach

More information

APPENDIX A INTEGRAL ABUTMENTS

APPENDIX A INTEGRAL ABUTMENTS APPENDIX A INTEGRAL ABUTMENTS Appendix A Guidelines for Design of Integral Abutments Rev. 1 - September, 2007 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT

More information

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report Executive Summary The No. 01607 carries the Trans-Canada Highway over Quartz Creek, approximately 45 km northwest of Golden, BC. As part of an Enhanced Bridge Inspection Program, the BC Ministry of Transportation

More information

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION 3.2.5.0 Since the release of BRADD Version 3.2.4.3, several operational issues have been addressed. This release of BRADD Version 3.2.5.0 contains the following

More information

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill. Bridge Applications Technology The Reinforced Earth Company (RECo) offers a variety of bridge abutment and bridge crossing solutions, each are based on project specific requirements. Bridge abutments are

More information

Aerial of Conceptual Path and Bridge Tysons-Old Meadow Road Bike/Ped Improvements

Aerial of Conceptual Path and Bridge Tysons-Old Meadow Road Bike/Ped Improvements Aerial of Conceptual Path and Bridge Barnes & Noble at One Place Project Location Corner Center Proposed Bridge Encore Condominiums Regency Club Condominiums Path continues to Dolley Madison Boulevard

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 89188 7 th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER OCTOBER 2, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7685 CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB

More information

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014 Updated: 5/15/14 1 What was driver for deciding to slide vs. roll? Overall weight? 2 1. Why the two different slide methods? 2. How much experience should your contractor have to perform the slide work?

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 36508 CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS

More information

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge Modular Steel Bridges Stark County Fischer Bridge Bottineau County Oak Creek Bridge This John Deere grain hauler was too heavy for the bridge. OOPS! An excavator and tow truck are needed to remove the

More information

Modified Sheet Pile Abutment for Low-Volume Road Bridge

Modified Sheet Pile Abutment for Low-Volume Road Bridge Modified Sheet Pile Abutment for Low-Volume Road Bridge Ryan R. Evans Department of Civil, Construction, and Environmental Engineering Iowa State University 176 Town Engineering Ames, IA 50011 ryevans@iastate.edu

More information

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report Final Report VTRC 06-R35 Virginia Transportation Research Council research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report http:/www.virginiadot.org/vtrc/main/online_reports/pdf/06-r35.pdf

More information

Critically damaged bridges & concepts for earthquake recovery

Critically damaged bridges & concepts for earthquake recovery Critically damaged bridges & concepts for earthquake recovery J. Waldin, J. Jennings & P. Routledge Opus International Consultants Ltd, Christchurch, New Zealand 2012 NZSEE Conference ABSTRACT: This paper

More information

Conditional assessment of Kiri Bridge in Shkoder, Albania

Conditional assessment of Kiri Bridge in Shkoder, Albania Conditional assessment of Kiri Bridge in Shkoder, Albania Gentian Rexhaj 1, Enea Mustafaraj 2 1 2 Department of Civil Engineering, Epoka University, Albania 2 Department of Civil Engineering, Epoka University,

More information

Precast Concrete Elements for Accelerated Bridge Construction

Precast Concrete Elements for Accelerated Bridge Construction Precast Concrete Elements for Accelerated Bridge Construction Volume 3. Laboratory Testing, Field Testing, and Evaluation of a Precast Concrete Bridge: Black Hawk County Final Report January 2009 Sponsored

More information

Appendix B. Shallow Foundations Report

Appendix B. Shallow Foundations Report 12/10/2013 GEOTECHNICAL MANUAL Appendix B. Shallow Foundations Report PLEASE NOTE A sample foundations report is included here for reference. It is provided as an example of content, format, and organization

More information

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection No. 1 2/26/2016 830 MSE Wall V 26 Is ADE 830 MSE Wall to be used in conjunction with NBE 218 Other Abutment

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7883 CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

5 DAMAGE TO TRANSPORTATION FACILITIES

5 DAMAGE TO TRANSPORTATION FACILITIES 5 DAMAGE TO TRANSPORTATION FACILITIES In the Kocaeli, Turkey earthquake of August 17, 1999, extensive damage of transportation facilities occurred in the Kocaeli and Sakarya region, Turkey as shown in

More information

Update on Seismic Behavior and Design of

Update on Seismic Behavior and Design of Update on Seismic Behavior and Design of Steel Plate Girder Bid Bridges Ahmad M. Itani, Ph.D., P.E., S.E. Professor Department of Civil and Environmental Engineering University of Nevada, Reno Background

More information

2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # CR

2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # CR 2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # 88756 CR 597 over RICE RIVER DISTRICT: District 1 COUNTY: St. Louis CITY/TOWNSHIP: ANGORA STATE: Minnesota Date of Inspection: Equipment Used: 06/21/2016

More information

Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3

Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3 F. W. Klaiber, D. J. White, T. J. Wipf, B. M. Phares, V. W. Robbins Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3 Development of Design Methodology August 2004 Sponsored

More information

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples BY MARTIN P. BURKE, JR. Innumerable bridges both in the U.S. and abroad have been, and continue to be, damaged by the restrained growth

More information

Integral Abutment Bridges Australian and US Practice

Integral Abutment Bridges Australian and US Practice Integral Abutment Bridges Australian and US Practice John Connal (M.Eng Sci., B.E. (civil) (Hons), Dip. C.E., F.I.E.Aust, M. ASCE, M. IABSE) Maunsell Australia Pty Ltd SYNOPSIS The structural system offered

More information

Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures

Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures InTrans Project Reports Institute for Transportation 9-2015 Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures Brent Phares Institute for Transportation, bphares@iastate.edu

More information

Emergency Bridge Stabilization at Mile Watrous Subdivision

Emergency Bridge Stabilization at Mile Watrous Subdivision Emergency Bridge Stabilization at Mile 189.70 Watrous Subdivision Christophe Deniaud, Ph.D., P.Eng. Bridge Engineer, CN 10004-104 Avenue Edmonton, Alberta, Canada T5J 0K2 Tel: (780) 421-6021 Fax: (780)

More information

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Jeff Sizemore, P.E. Geotechnical Design Support Engineer SCDOT Ed Tavera, P.E. Principal Geotechnical Engineer Geoengineers

More information

Figure 3: Analytic procedure

Figure 3: Analytic procedure International Journal of Scientific and Research ublications, Volume 7, Issue 5, May 2017 567 Investigation of Integral Bridge Effect under Dynamic Loading Haymanmyintmaung *,kyawlinnhtat ** * Department

More information

DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA

DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA DESIGN AND CONSTRUCTION OF BR1449 VICTORIA PARK DRIVE MODIFICATIONS, BURSWOOD, WA Brian Lord, Arup Pty Ltd, Australia ABSTRACT Arup was lead designer for Lend Lease on the Victoria Park Drive Modifications

More information

Walney Road Bridge Replacement and Road Widening

Walney Road Bridge Replacement and Road Widening R e s p o n s e t o Request for Proposals Walney Road Bridge Replacement and Road Widening ORIGINAL A Design-Build Projec t From: Westfield Boulevard (Route 6755) - To: Willard Road (Route 6215) and From:

More information

Low-Volume Road Abutment Design Standards

Low-Volume Road Abutment Design Standards Low-Volume Road Abutment Design Standards V.W. Robbins HNTB Corporation 7450 W. 130th St., Suite 400 Overland Park, KS 66213 vrobbins@hntb.com F. Wayne Klaiber Bridge Engineering Center 418 Town Engineering

More information

Culvert Safety Inspection Report (CSIR)

Culvert Safety Inspection Report (CSIR) Conference Workshop Culvert Safety Inspection Report (CSIR) Rich Kathrens MDOT Bridge Safety Inspection Engineer kathrens@michigan.gov March 22, 2015 Culvert Safety Inspection Updates Pre 2015 CSIR CSIR

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT STATE BRIDGE NO. 6081 CITY OR COUNTY 053 LOUDOUN TYPE OF BRIDGE REPORT: REGULAR INSPECTION JANUARY 2016 BRIDGE NAME: DIRECTION: FOREST MILLS

More information

BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE

BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE BEHAVIOR AND ANALYSIS OF AN INTEGRAL ABUTMENT BRIDGE Paul J. Barr Marv W. Halling Conner Huffaker Hugh Boyle Utah State University Department of Civil and Environmental Engineering Logan, Utah September

More information

Integral bridges and environmental conditions

Integral bridges and environmental conditions Integral bridges and environmental conditions COMISU CLAUDIU-CRISTIAN, BOACĂ GHEORGHITĂ Department of Roads and Foundations Faculty of Civil Engineering and Building Services The "Gheorghe Asachi" Technical

More information

Bahavior and Analysis of an Integral Abutment Bridge

Bahavior and Analysis of an Integral Abutment Bridge Utah State University DigitalCommons@USU All Graduate Theses and Dissertations Graduate Studies 2013 Bahavior and Analysis of an Integral Abutment Bridge Conner D. Huffaker Follow this and additional works

More information

L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015

L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015 Canterbury Bridge Group Ferrymead Bridge L. Greenfield Christchurch City Council M. Cowan Opus International Consultants W. du Plessis HEB Construction 26 March 2015 Presenter: Lloyd Greenfield Senior

More information

An Integral Abutment Bridge with Precast Concrete Piles

An Integral Abutment Bridge with Precast Concrete Piles An Integral Abutment Bridge with Precast Concrete Piles Final Report May 2007 Sponsored by the Iowa Highway Research Board (IHRB Project TR-438) and the Iowa Department of Transportation (CTRE Project

More information

Detailed Seismic Assessment and Seismic Improvements of Market Road Underpass

Detailed Seismic Assessment and Seismic Improvements of Market Road Underpass Detailed Seismic Assessment and Seismic Improvements of Market Road Underpass D. Novakov, D. Ashby, T. Chin & A. George Opus International Consultants Ltd, Wellington - Auckland, New Zealand. G. Gregg

More information

\\H\15\ PH9 Inspection Photos

\\H\15\ PH9 Inspection Photos SHOP SLIDE Photo 1. at cracking across the footpath at the end of the Hwy 2 EB to Hwy 684 SB off ramp at the 99 Ave. intersection. Drop in asphalt trail (background) has worsened since 2013 and is now

More information

EFFECTS OF SKEWED ABUTMENTS ON CURVED BRIDGE CONSTRUCTION RESPONSE. Tyler Goodman. Spring 2013

EFFECTS OF SKEWED ABUTMENTS ON CURVED BRIDGE CONSTRUCTION RESPONSE. Tyler Goodman. Spring 2013 THE PENNSYLVANIA STATE UNIVERSITY SCHREYER HONORS COLLEGE DEPARTMENT OF CIVIL AND ENVIROMENTAL ENGINEERING EFFECTS OF SKEWED ABUTMENTS ON CURVED BRIDGE CONSTRUCTION RESPONSE Tyler Goodman Spring 2013 A

More information

Comparative Study of Behaviour of Integral and Bearing Type Bridge under Temperature Loading

Comparative Study of Behaviour of Integral and Bearing Type Bridge under Temperature Loading IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 03, 2015 ISSN (online): 2321-0613 Comparative Study of Behaviour of Integral and Bearing Type Bridge under ing B. J. Shah

More information

CORTE MADERA TOWN COUNCIL STAFF REPORT TOWN MANAGER, MAYOR AND MEMBERS OF THE TOWN COUNCIL KELLY CROWE, ASSOCIATE CIVIL ENGINEER

CORTE MADERA TOWN COUNCIL STAFF REPORT TOWN MANAGER, MAYOR AND MEMBERS OF THE TOWN COUNCIL KELLY CROWE, ASSOCIATE CIVIL ENGINEER CORTE MADERA TOWN COUNCIL STAFF REPORT REPORT DATE: October 12, 2016 MEETING DATE: October 18, 2016 TO: FROM: SUBJECT: PURPOSE: TOWN MANAGER, MAYOR AND MEMBERS OF THE TOWN COUNCIL KELLY CROWE, ASSOCIATE

More information

Ashton Avenue Integral Bridge

Ashton Avenue Integral Bridge Ashton Avenue Integral Bridge Behzad Golfa, Senior Bridge Engineer, GHD Pty Ltd ABSTRACT The Ashton Avenue Bridge is a replacement of the original three-span timber bridge over Perth- Fremantle Rail line

More information

CE 332 Construction Engineering and Management. MS Project - Recitation

CE 332 Construction Engineering and Management. MS Project - Recitation CE 332 Construction Engineering and Management MS Project - Recitation MICROSOFT PROJECT Microsoft Project is a project management software, developed and sold by Microsoft, which is designed to assist

More information

Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota

Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota Kamal Saffarinia 1, G. Kenneth Young 2, J. Sterling Jones 3, and Stuart Stein 4 This paper investigates two-dimensional

More information

Med School Design and Construction Schedule Med School - Classic WBS Layout w/ WBS S 20-Jul-16 09: d 452d 03-Aug-15 A 09-May-18 0d 6.

Med School Design and Construction Schedule Med School - Classic WBS Layout w/ WBS S 20-Jul-16 09: d 452d 03-Aug-15 A 09-May-18 0d 6. Med School Design and Construction Schedule 755d 452d 03-Aug-15 A 09-May-18 0d 6.89% s 701d 432d 19-Aug-15 A 21-Mar-18 0d 0% 147 Institution Approvals (Trustees) 0d 0d 19-Aug-15 A 100% EVHR 000-000-1000

More information

2017 UNDERWATER BRIDGE INSPECTION REPORT. TWP 332 over ROOT RIVER. Date of Inspection: Equipment Used: 10/22/2016. Town or Township Highway Agency

2017 UNDERWATER BRIDGE INSPECTION REPORT. TWP 332 over ROOT RIVER. Date of Inspection: Equipment Used: 10/22/2016. Town or Township Highway Agency 2017 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # L4870 TWP 332 over ROOT RIVER DISTRICT: District 6 COUNTY: Fillmore CITY/TOWNSHIP: JORDAN STATE: Minnesota Date of Inspection: Equipment Used: 10/22/2016

More information

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments A.M. Morsy. Department of Civil, Architectural, and Environmental Engineering, The University of Texas

More information

The Impact of Economic, Technological and Environmental Changes on Winter Maintenance Operations Plans and Policies: Adapting to the New Normal

The Impact of Economic, Technological and Environmental Changes on Winter Maintenance Operations Plans and Policies: Adapting to the New Normal : Adapting to the New Normal Dave Bergner, M.A., PWLF TRB International Winter Maintenance Conference April, 2016, Ft. Collins, CO TRB 2016 Winter Maintenance Conf. c. MVA, LLC 1 Learning Objectives: Recognize

More information

Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways

Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways ANNUAL REPORT FOR FY 2011 ODOT SPR ITEM NUMBER 2228 Submitted to: John Bowman, P.E. Planning and Research

More information

Winona Bridge Visual Quality Review Committee

Winona Bridge Visual Quality Review Committee Winona Bridge Visual Quality Review Committee Summary of Preferred Features October 7, 2014 Creating Bridges As Art 1 Summary of Preferred Features Based on Visual Quality Review Committee Final Design

More information

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes J. H. Wood John Wood Consulting, Lower Hutt. ABSTRACT: 2012 NZSEE Conference Twelve State Highway (SH) bridges subjected

More information

DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE

DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE DATA GATHERING AND DESIGN DETAILS OF AN INTEGRAL ABUTMENT BRIDGE Abstract S. Hassiotis M. ASCE Stevens Institute of Technology, Hoboken, N.J. 07030 sophia.hassiotis@stevens.edu An integral-abutment bridge

More information

STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END

STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END by Zhengyu Liu Research Team: Zhengyu Liu, Graduate Research Student, Bridge Engineering Center, Iowa State University Brent M Phares, Director,

More information

Design of Picton Railway Overbridge for Mine Subsidence

Design of Picton Railway Overbridge for Mine Subsidence Design of Picton Railway Overbridge for Mine Subsidence Geraint Jones Long Bai Small Bridges Conference 24 November 2015 Introduction - Presentation Structure >Project Background >Longwall Mining >Location

More information

Design of Dingley Bypass Integral Bridges

Design of Dingley Bypass Integral Bridges Design of Dingley Bypass Integral Bridges Dr. Kabir Patoary Principal Engineer Bridges GHD Elder St South Underpass Tekla Model Presentation Outline 1. Overview of Dingley Bypass 2. Design of Integral

More information

EFFECTS OF SPATIAL VARIATION OF SEISMIC INPUTS ON BRIDGE LONGITUDINAL RESPONSE

EFFECTS OF SPATIAL VARIATION OF SEISMIC INPUTS ON BRIDGE LONGITUDINAL RESPONSE 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 24 Paper No. 64 EFFECTS OF SPATIAL VARIATION OF SEISMIC INPUTS ON BRIDGE LONGITUDINAL RESPONSE Jiachen WANG 1, Athol

More information

THE EFFECT OF EPS GEOFOAM BACKFILL ON THE SEISMIC PERFORMANCE OF INTEGRAL ABUTMENT BRIDGES MEGAN OOMS. A thesis submitted to the

THE EFFECT OF EPS GEOFOAM BACKFILL ON THE SEISMIC PERFORMANCE OF INTEGRAL ABUTMENT BRIDGES MEGAN OOMS. A thesis submitted to the THE EFFECT OF EPS GEOFOAM BACKFILL ON THE SEISMIC PERFORMANCE OF INTEGRAL ABUTMENT BRIDGES By MEGAN OOMS A thesis submitted to the Graduate School-New Brunswick Rutgers, The State University of New Jersey

More information

Integral Abutment Bridges-Development of Soil Model for Soil Structure Interaction in Time History Analysis

Integral Abutment Bridges-Development of Soil Model for Soil Structure Interaction in Time History Analysis International Journal of Engineering Research and Development e-issn: 2278-067X, p-issn: 2278-800X, www.ijerd.com Volume 10, Issue 3 (March 2014), PP.31-40 Integral Abutment Bridges-Development of Soil

More information

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 SITE NUMBER AND NAME: NC 52 Pembina River Bridge LEGAL DESCRIPTION: SE 1-50-9-W5M STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 NAD 83 COORDINATES:

More information

Long-Term Response Prediction of Skewed Integral Bridges under Creep Effects

Long-Term Response Prediction of Skewed Integral Bridges under Creep Effects From the SelectedWorks of Innovative Research Publications IRP India Winter January 1, 215 Long-Term Response Prediction of Skewed Integral Bridges under Creep Effects Innovative Research Publications,

More information

Modified Sheet Pile Abutments for Low-Volume Road Bridges

Modified Sheet Pile Abutments for Low-Volume Road Bridges EERC Publication ERXX-XX Modified Sheet Pile Abutments for Low-Volume Road Bridges Final Report JANUARY 2012 Sponsored by Iowa Highway Research Board (IHRB Project TR-568) Iowa Department of Transportation

More information

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri Adams et al. (2012), FHWA Geosynthetic Reinforced Soil Integrated Bridge System Interim Implementation

More information

300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES

300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES 300 GEORGE ST REDEVELOPMENT IMPACT OF PROPOSED BASEMENT EXCAVATION ON THE ANN STREET ONRAMP STRUCTURES BONACCI GROUP DOCUMENT HISTORY ISSUE REVISION DATE AUTHOR REVIEWER Issued for DTMR Review A October

More information

The Long Term Performance Of Skew Integral Bridges

The Long Term Performance Of Skew Integral Bridges The Long Term Performance Of Skew Integral Bridges Popoola, Oladele.O. Civil Engineering Department Afe Babalola University Ado-Ekiti, Nigeria oladelepope@yahoo.com Wasiu, John Civil Engineering Department

More information

ILLINOIS INTEGRAL ABUTMENT BRIDGES: BEHAVIOR UNDER EXTREME THERMAL LOADING AND DESIGN RECOMMENDATIONS KURT PATRICK HOLLOWAY THESIS

ILLINOIS INTEGRAL ABUTMENT BRIDGES: BEHAVIOR UNDER EXTREME THERMAL LOADING AND DESIGN RECOMMENDATIONS KURT PATRICK HOLLOWAY THESIS ILLINOIS INTEGRAL ABUTMENT BRIDGES: BEHAVIOR UNDER EXTREME THERMAL LOADING AND DESIGN RECOMMENDATIONS BY KURT PATRICK HOLLOWAY THESIS Submitted in partial fulfillment of the requirements for the degree

More information

CORRIENTE RESOURCES INC.

CORRIENTE RESOURCES INC. CORRIENTE RESOURCES INC. MIRADOR PROJECT Bridge Review from Site to Puerto Bolivar, Ecuador OVER20YEARSOF SERVICE ConsultantsInternational Inc. 1983-2003 1212-750West Pender Street Vancouver BritishColumbia

More information

Policy Research CENTER

Policy Research CENTER TRANSPORTATION Policy Research CENTER Value of Travel Time Knowingly or not, people generally place economic value on their time. Wage workers are paid a rate per hour, and service providers may charge

More information

SEISMIC PERFORMANCE OF SEAT- TYPE ABUTMENT HIGHWAY BRIDGES IN ILLINOIS

SEISMIC PERFORMANCE OF SEAT- TYPE ABUTMENT HIGHWAY BRIDGES IN ILLINOIS CIVIL ENGINEERING STUDIES Illinois Center for Transportation Series No. 18-015 UILU-ENG-2018-2015 ISSN: 0197-9191 SEISMIC PERFORMANCE OF SEAT- TYPE ABUTMENT HIGHWAY BRIDGES IN ILLINOIS Prepared By James

More information

Calaveras Dam Replacement Project. Third Party Due-Diligence Review Investigations and Design of the Left Abutment

Calaveras Dam Replacement Project. Third Party Due-Diligence Review Investigations and Design of the Left Abutment San Francisco Public Utilities Commission Calaveras Dam Replacement Project 11 Third Party Due-Diligence Review Investigations and Design of the Left Abutment Presented By: Steve Verigin Senior Vice President,

More information

The Pennsylvania State University. The Graduate School. Department of Civil and Environmental Engineering

The Pennsylvania State University. The Graduate School. Department of Civil and Environmental Engineering The Pennsylvania State University The Graduate School Department of Civil and Environmental Engineering LENGTH LIMITATIONS OF PRESTRESSED CONCRETE GIRDER INTEGRAL ABUTMENT BRIDGES A Thesis in Civil Engineering

More information

Integral Bridge Design. Integral Bridge Design. in Midas Civil. Midas UK

Integral Bridge Design. Integral Bridge Design. in Midas Civil. Midas UK Integral Bridge Design in Midas Civil Midas UK Contents Types of Integral Bridges Why Integral Construction? Do we need Construction Stage Analysis for Integral Bridges? Soil-Structure Interaction at abutments

More information

Keywords: integral abutment bridge, pile head abutment connection, finite element method.

Keywords: integral abutment bridge, pile head abutment connection, finite element method. Global Journal of Researches in Engineering: e Civil And Structural Engineering Volume 15 Issue 1 Version 1.0 Year 2015 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global

More information

Cold In-Place Recycling in Tampa. Ken Holton, P.E. Street Maintenance Engineer

Cold In-Place Recycling in Tampa. Ken Holton, P.E. Street Maintenance Engineer Cold In-Place Recycling in Tampa Ken Holton, P.E. Street Maintenance Engineer City of Tampa Stats Tampa has 2,600 lane miles of roadways Tampa uses the MicroPAVER system Currently the City of Tampa s average

More information

PennDOT Longitudinal Joint Density Efforts

PennDOT Longitudinal Joint Density Efforts PennDOT Longitudinal Joint Density Efforts February 5, 2014 Garth D. Bridenbaugh, P.E. Pennsylvania Department of Transportation PennDOT s History at Joints In 2006, PennDOT specs required joints to be

More information