2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # CR

Size: px
Start display at page:

Download "2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # CR"

Transcription

1 2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # CR 597 over RICE RIVER DISTRICT: District 1 COUNTY: St. Louis CITY/TOWNSHIP: ANGORA STATE: Minnesota Date of Inspection: Equipment Used: 06/21/2016 Owner: County Highway Agency Inspected By: Janulis, Lukas Report Written By: Lukas Janulis Report Reviewed By: Final Report Date:

2 TABLE OF CONTENTS PAGE NUMBER UNDERWATER SUMMARY 3 UNDERWATER INSPECTION 4 UNDERWATER INSPECTION PROCEDURES 6 STRUCTURE INVENTORY 7 ELEMENTS 8 PHOTOGRAPHS 11 BRIDGE UNDERWATER INSPECTION DRAWINGS

3 UNDERWATER INSPECTION REPORT SUMMARY The substructure units inspected at Bridge No , the North Abutment and Bent 1, were found to be in fair to poor condition, with only minor defects of structural significance. The timber piles were typically sound with random splitting extending from the pile cap down up to 4 feet. Pile A of Bent 1 had a 1 inch wide by 8 inch deep split extending from the pile cap down 2.5 feet. The timber around the split was unsound and a hollow core was visible through the split with an estimated 15 percent loss of pile section. The overall condition of the structure has not significantly changed since the previous underwater inspection. INSPECTION FINDINGS (A) The channel bottom material typically consisted of gravel and sandy silt with a maximum probe rod penetration of 6 inches. (B) The timber piles were typically heavily weathered with checking and splitting up to 1/4 inch wide. The outer 2 inches of the upper 4 feet of the timber pile shells were typically unsound. (C) Pile A of Bent 1 had a 1 inch split extending from the pile cap down 2.5 feet with up to 8 inches of penetration. The pile was unsound along the length of the split. A hollow core was visible though the crack, with an estimated 15 percent loss of pile section. (D) Pile C of Bent 1 had a 1/2 inch split extending from the pile cap to 1.4 feet below the waterline with up to 4 inches of penetration. (E) The south cross-brace at Bent 1 exhibited heavy decay on the upstream end with up to 40 percent loss of section. (F) Backwall timbers were typically sound and tight with no notable gaps, deterioration, or loss of backfill. RECOMMENDATIONS (A) Repair Piles A and C of Bent 1 by splicing/posting in a new upper 5 feet of the member or by another method such as a structural jacket. (B) Reinspect the submerged substructure at the normal maximum recommended (NBIS) interval of sixty (60) months. Contractor: Contractor Job Number: Collins Engineers, Inc Page 3 of 15

4 UNDERWATER INSPECTION 1. BRIDGE DATA Bridge #: Feature Intersected: Facility Carried: District: RICE RIVER CR 597 District 1 County: St. Louis Bridge Description: The superstructure consists of a timber deck supported by steel I-beams. The superstructure is supported by two abutments consisting of five 12-inch-diameter timber piles and a pile bent consisting of five 12-inch-diameter timber piles. 2. INSPECTION DATA Professional Engineer/Team Leader: Inspection Diver: Date of Underwater Inspection: Weather Conditions: Underwater Visibility (feet): Waterway Velocity (ft/sec): Lukas Janulis Lukas Janulis 06/21/2016 Sunny, 70 F 1 foot Negligible 3. SUBSTRUCTURE INSPECTION DATA Substructure(s) Inspected: The North Abutment and Bent 1. General Shape: The North Abutment consists of five timber 12-inch-diameter piles with a 12 inch by 12 inch timber pile cap. The backwall and wingwalls were comprised of 3 inch by 12 inch timber boards. Bent 1 consisted of five timber 12-inch-diameter piles with a 12 inch by 12 inch timber pile cap and two 3 inch by 12 inch diagonal cross-brace boards. Maximum Water Depth at Substructure(s) Inspected (feet): 5.2 feet 4. WATERLINE DATUM Water Level Reference: Waterline Elevation (feet): Description: Top of the pile cap at the downstream end of Bent feet The waterline was approximately 3.2 feet below the reference. 5. NBIS CODING INFORMATION (Minnesota specific codes are used for 92B and 113) Item 60: Substructure: Item 61: Channel and Channel Protection: Item 62: Culvert: Code: Code: Code: 4 5 Page 4 of 15

5 Item 92B: Underwater Inspection: Item 113: Scour Critical Bridge: Code: Code: Y 48 06/16 K Bridge is scour critical because abutment or pier foundation is rated as unstable due to observed scour at bridge site. Yes X No (Mark your selection with an X) 6. STRUCTURAL ELEMENT CONDITION RATING Conditions ELEM # Element Description Quantity Unit CS1 CS2 CS3 CS4 216 Timber Abutment 87 LF Timber Piling 23 EA Scour 1 EA 1 Page 5 of 15

6 UNDERWATER INSPECTION INSPECTION PROCEDURES The routine underwater inspection of Bridge (CR 597 over Rice River) was completed on June 21, The underwater inspection was conducted from shore. The inspection was conducted by a team consisting of a Professional Engineer Diver with a valid MnDOT Team Leader certification, a backup diver and dive tender. The inspection utilized commercial dive equipment and techniques in accordance with OSHA regulations. Channel bottom profiles were taken along the upstream and downstream faces of the bridge and around the periphery of substructure units to determine the presence, location, and area of scour. The bridge elements inspected consisted of a timber abutment and a timber bent. According to the bridge inventory, Bent 1 and the North Abutment are founded on timber piles. Inspection procedures followed FHWA guidance and the MnDOT Bridge and Structure Inspection Program Manual with channel bottom probing to search for foundations. The maximum routine underwater inspection frequency is recommended to remain at 60 months based on those findings and risk factors. Also, inspection procedures should continue to follow the above approach and standard guidance with 100% Level I and 10% Level II intensity efforts. Page 6 of 15

7 Bridge ID: Minnesota Structure Inventory Report CR 597 over RICE RIVER Date: 12/14/ G E N E R A L + + R O A D W A Y + + I N S P E C T I O N + Agency Br. No. 355 Crew Bridge Match ID (TIS) 0 Userkey 109 District 01 County St. Louis Route Sys 07 - CNTY Number 597 Functionally Obsolete City Sect., Twp., Range Main Span Type 3 - Steel Median Width On Bridge Main Span Design Main Span Detail Appr. Span Type Appr. Span Design Appr. Span Detail Skew 0 Culvert Type Barrel Length Cantilever ID MAIN: 2 Main Span Length Structure Length 01 - Beam Span Number of Spans APPR: 0 TOTAL: 23.0 Deck Width (Out-to-Out) 19.5 Deck Material Wear Surf Type Wear Surf Install Year Wear Course/Fill Depth Deck Membrane Deck Rebars Deck Rebars Install Year Structure Area (Out-to-Out) 956 sq. Roadway Area (Curb-to-Curb) Sidewalk Width 50A. Lt 0.00 Curb Height 0.3 MI N OF JCT CR936 Level of Service 1 - MAINLINE N - 18W Roadway Type Latitude ' 6.04 '' Control Section (TH Only) Status Lt 8 - Wood or Timber 6 - Bituminous None N - Not Applicable (no deck) + M I S C. Structure Flared Parallel Structure Field Conn. ID Abutment Foundation (Material/Type) Pier Foundation (Material/Type) Historic Status 4 - PILE BENT 2 - TIMBER 4 - PILE BENT Underwater 60 Pinned Asbly. Spec. Feat Navigation Control Year Painted 926 sq. Traffic 50B. Rt Rt Painted Area Primer Type Posted Load B R I D G E D A T A No flare 5 - Not eligible + P A I N T + Bridge Railing 0 - SUBSTANDARD N - No parallel structure GR Transition Appr. Guardrail GR Termini 2 - TIMBER Frac. Critical 2 - Vehicle & Semi (Type R12-5) 0 - Not Required Horizontal 1 - Object Markers 0.50 Vertical Unsound Paint % Finish Type + B R I D G E 2-2-way traffic Longitude ' '' Reference Point Custodian Owner 02 - County Highway Agency 02 - County Highway Agency Roadway Name or Description Township ANGORA CR 597 Desc. Loc. BMU Agreement Year Built 1956 MN Year Reconstructed FHWA Year Reconstructed MN Temporary Status Bridge Plan Location Date Opened to Traffic Maint. Area Roadway O/U Key Detour Length 99 mi. Lanes Route On Structure On - Off System 0 - OFF Roadway Width Legislative District 05A Vertical Clearance Potential ABC 2 - N/A Max. Vert. Clear. Service On 1 - Highway Appr. Surface Width Service Under 0 - NO PLAN + S T R U C T U R E + HCADT Functional Class If Divided + R D W Y Horizontal Clear. Lateral Clearance ON 2 UNDER ADT 5 - Waterway Bridge Roadway Width YEAR 2003 N - Not Applicable + I N Drainage Area (sq. mi.) + W A T E R W A Y + Waterway Opening (sf.) 360 Pier Protection Posting Rating Date 02/21/2015 N - NOT REQUIRED N - NOT REQUIRED N - NOT REQUIRED D E P T H I N S P. + Y/N Freq Date 06/21/ No nav. control on VEH: 34 SEMI: 40 DBL: 40 Overweight Permit Codes Rail Type Lt 37 Rt 37 A N - N/A B N - N/A C N - N/A sq. ADTT 09 - Rural - Local 27.0 S I G N S + Structurally Deficient Sufficiency Rating 59.9 Inspection Date 06/28/2016 Inspection Frequency 12 Inspector Name + N B I Nav. Clr. () Nav. Vert. Lift Bridge Clear. () Vert. 0.0 Horiz. 0.0 MN Scour Code K - LIMITED RISK Year C A P A C I T Y R A T I N G S + Design Load Operating Rating Janulis, Lukas P - Posted for Load C O N D I T I O N Deck 5 Unsound Superstructure 6 Deck % Underclearances Waterway Adequacy 8 Approach Alignment 8 0 D I M E N S I O N S + NB-EB % SB-WB Substructure Channel 5 Culvert + N B I Structure Evaluation 4 Deck Geometry Other/Unknown 2 - HS TRUCK R A T I N G S Inventory Rating 2 - HS TRUCK Y N N A P P R A I S A L R A T I N G S + N + S A F E T Y F E A T U R E S + Page 7 of 15

8 12/19/2016 Inspector: CO Bridge MINNESOTA BRIDGE INSPECTION REPORT BRIDGE County: City: Township: Section: 29 Township: 061N Range: 18W Maint. Area: Span Type: 3 - Steel 2 List: St. Louis ANGORA NBI Deck: 5 Super: 6 Sub: 4 Chan: 5 Culv: N Appraisal Ratings - Approach: Required Bridge Signs - Load Posting: CR 597 OVER RICE RIVER 8 Waterway: 8 Horizntal: Location: Route: Control Section: 2 - Vehicle & Semi (Type R12-5) 1 - Object Markers 0.3 MI N OF JCT CR CNTY 597 Local Agency Bridge Nbr.: 355 Open, Posted, Closed: MN Scour Code: Traffic: Vertical: Ref. Pt.: P - Posted for Load K - LIMITED RISK 0 - Not Required N - Not Applicable Length: Deck Width: Rdwy. Area/ Pct. Unsnd: 926 sq. / % Paint Area/ Pct. Unsnd: Culvert: N/A sq. / % Postings: Unofficial Structurally Deficient Unofficial Functionally Obsolete Unofficial Sufficiency Rating 59.9 Y N ELEM NBR ELEMENT NAME REPORT TYPE INSP. DATE QUANTITY CS 1 CS 2 CS 3 CS 4 Timber Deck 12/14/ SF Underwater Notes: [2016] Water leaking through deck removing timber preservative. 06/28/ SF Wearing Surfaces Underwater 12/14/ SF /28/ SF Notes: [ ] Bituminous peeled off on north end. Potholes forming in bituminous overlay with bituminous breaking up. Bituminous has cracks throughout deck. Steel Open Girder/Beam 12/14/ LF Underwater 06/28/ LF Notes: [ ] 9 lines of beams, simple span (S.S.), between abuts and piers. Paint flaking on most beams. Paint gone at abutments. Little rust above abutments. No section loss Steel Protective Coating Underwater 12/14/ SF /28/2016 Notes: [2016] Paint flaking on most beams. Paint gone at abutments 2218 SF Timber Abutment 12/14/ LF Underwater 06/28/ LF Notes: [2016] Added 48 LF to abutment quantity to account for wingwalls. [ ] Possible backfill loss north abutment. Gap under bottom backing board, most noticeable west end of abutment. Moderate weathering with splits and checks. N. abut cap rotating slightly out of alignment. N. Piles constantly in water and exhibiting moderate decay of internally and in the shell. Wings have moderate weathering with splits and checks. Damage to end of SW wing from equipment during brush clearing. North abutment pushing in slightly. North wings are stiffened with railroad rail horizontally fixed with cables to wings. Timber Pile 12/14/ EA Underwater 06/28/ EA Notes: [2016] Added 8 piles for wing piles. All piles have moderate to extensive decay. [ ] North Piles and pier piles constantly in water and exhibits moderate to severe decay. East pile north abutment has shell delamination, dented when hit about 1' below cap. West pile on pier has 1/2" wide split on south side top 3' to center of pile. North abutment piles stiffened with beams fixed vertically. Second pile from west stiffener fell off. Moderate weathering with splits and checks. Timber Pier Cap 12/14/ LF Underwater 06/28/ LF Notes: [ ] Pier cap W. end, slight crack, rotated 1 degree, and slight loss of bearing on West end. South abutment cap 100% bearing and sitting normal to caps. North abutment cap rotating 1 degree. N abut, W end, pile cap slight crack at end. Page 8 of 15

9 BRIDGE CR 597 OVER RICE RIVER ELEM NBR ELEMENT NAME REPORT TYPE INSP. DATE QUANTITY CS 1 CS 2 CS 3 CS 4 Fixed Bearing 12/14/ EA Underwater 06/28/ EA Notes: [ ] Minor surface corrosion on fixed bearings at abutments with little to no section loss. Pier bearings have some flaking paint with exposed steel having minor surface corrosion. Metal Bridge Railing 12/14/ LF Underwater 06/28/ LF Notes: [ ] The protective coating has failed with surface corrosion on about 75% of flexbeam. [ ] Flex beam has corrosion and scrapes throughout. Angle iron posts have paint flaking with minor surface corrosion. No section loss. Flex Beam w/ Angle Iron Posts Steel Protective Coating Underwater 12/14/ SF /28/2016 Notes: [2016] 75% of paint has failed. Rest of paint is flaking. 276 SF Critical Deficiencies or Safety Hazards 12/14/ EA Underwater Notes: [ ] No critical deficiencies or safety hazards found during this inspection. 06/28/ EA Gravel Approach Roadway 12/14/ EA Underwater Notes: [2016] Potholes in approaches have been fixed by grading of roadway. [2015] Potholes along south edge of deck with no significant increase in traffic impact. [ ] No signs of settlement or undermining. 06/28/ EA Substructure Settlement & Movement 12/14/ EA Underwater Notes: [ ] Movement appears to have arrested. 06/28/ EA Scour 12/14/ EA Underwater Notes: [ ] No signs of scour present. K - Limited risk. Monitoring required. 890 Load Posting or Vertical Clearance Underwater Signing 06/28/ EA /14/ EA /28/ EA Notes: [2016] Correct posting in place with no deterioration. [2015 Update] 34T/40T/40T Load posting signs placed at bridge that match February 2015 load rating. Other Bridge Signing 12/14/ EA Underwater Notes: [2016] South delineators are slightly bent. [2015] All signs present with no notable deterioration. [ ] 4 Delineators present. SE delineator leaning North. 06/28/ EA Slopes & Slope Protection 12/14/ EA Underwater 06/28/ EA Notes: [ ] Possible backfill loss North abutment, gap under bottom backing board most noticeable at West end of abutment. No riprap in place. Deck & Approach Drainage 12/14/ EA Underwater 06/28/ EA Notes: [ ] Minor ponding on deck from bituminous deterioration. Scuppers free of debris. Some gravel along gutterline of deck. No drainage related slope erosion. Page 9 of 15

10 BRIDGE CR 597 OVER RICE RIVER ELEM NBR ELEMENT NAME REPORT TYPE INSP. DATE QUANTITY CS 1 CS 2 CS 3 CS 4 Sidewalk, Curb, & Median 12/14/ EA Underwater Notes: [ ] North end of east curb coming loose. [2013] Scuppers. Minor weathering with splits and checks. 06/28/ EA Protected Species 12/14/ EA Underwater Notes: [2016] Swallow nest present span 2 beam 2 06/28/ EA General Notes: 58. Deck NBI: 36A. Brdg Railings NBI: 36B. Transitions NBI: 36C. Appr Guardrail NBI: 36D. Appr Guardrail Terminal NBI: 59. Superstructure NBI: 60. Substructure NBI: 61. Channel NBI: SLC District 3 Inspected by: [2016] CG, JB : [2015] CG, TM : [2015 Update] CG : [ ] CG, BH. [2015 Update] Update inspection to update signing element due to load posting signs being placed at bridge and to upload date stamped photos. Went under with boat '09, 2012 [ ] Bituminous peeled off on north end. Potholes forming in bituminous overlay with bituminous breaking up. Water leaking through deck removing timber preservative. Flexbeam with angle iron posts. Bridge is wider than approach and ADT < 400, guardrail not required. Bridge is wider than approach and ADT < 400, guardrail not required. Bridge is wider than approach and ADT < 400, guardrail not required. [ ] 9 lines of beams, simple span (S.S.), between abuts and piers. Paint flaking on most beams. Paint gone at abutments. Little rust above abutments. No section loss. [ ] Pier piles have large splits near top. Pile 1B has extensive splitting and decay. [2013] Possible backfill loss North abutment, gap under bottom backing board most noticeable at West end of abutment. Moderate to significant weathering and decay with splits and checks. N. abut cap rotating slightly out of alignment. N. Piles constantly in water and exhibiting moderate to significant decay of internally and in the shell. North abutment pushing in slightly. [ ] Channel shows signs of movement to the north. No slope along north abutment. 62. Culvert NBI: 71. Waterway Adeq NBI: 72. Appr Roadway Alignment NBI: [2016] Approach north and south of bridge slightly lower than bridge. Approaches would overtop before bridge. [ ] No sight distance issues or speed reduction required. Inventory Notes: Inspector's Signature Reviewer's Signature Page 10 of 15

11 Pictures Photo 1 - Upstream Fascia, Looking Northwest Photo 2 - Downstream Fascia, Looking Southeast Page 11 of 15

12 Pictures Photo 3 - Bent 1, Looking Southeast Photo 4 - North Abutment, Looking Northeast Page 12 of 15

13 Pictures Photo 5 - Split in Pile C of Bent 1, Looking South Page 13 of 15

14 N ~ S. Abutment ~ Bent 1 ~ N. Abutment 23' 23' INSPECTION NOTES: 1 The channel bottom material typically consisted of gravel and sandy silt with a maximum probe rod penetration of 6 inches The timber piles were typically heavily weathered with checking and n/a spliting up to inch wide. The outer 2 inches of timber pile shells A were typically unsound. 3 Pile A of Bent 1 had a 1 inch split extending from the pile cap down 2.5 feet with up to 8 inches of penetration. The pile was unsound 1 B along the length of the split. A hollow core was visible though the crack with an estimated 15 percent loss of pile section. 4 Pile C of Bent 1 had a 1/2 inch split extending from the pile cap to (Typ.) Flow Rice River 6 C D 1.4 feet below the waterline with up to 4 inches of penetration. 5 The south cross-brace at Bent 1 exhibited heavy decay on the upstream end with up to 40 percent loss of section. 6 Backwall timbers were typically sound and tight with no notable gaps, deterioration, or loss of backfill. GENERAL NOTES: 5 E 1. The North Abutment and Bent 1 were inspected during the underwater inspection n/a n/a 2. At the time of inspection on June 21, 2016, the waterline was located approximately 3.2 feet below the top of the pile cap at the downstream end of the Bent 1. Since elevation information was not available a reference elevation of was assumed. Based on the assumed reference the waterline elevation was SOUNDING PLAN Shoreline (Typ.) 3. Soundings indicate the water depth at the time of inspection and are measured in feet. 3" x 12" Timber Backwall Board (Typ.) 12" Timber Pile (Typ.) 3"x12" Timber Cross-Bracing Legend -5.2 Sounding Depth from Waterline (6/21/2016) MINNESOTA 12" Timber Pile (Typ.) -4.5 Sounding Depth from Waterline (9/19/2012) DEPARTMENT OF TRANSPORTATION UNDERWATER BRIDGE INSPECTION A Pile Identification Designation STRUCTURE NO CR 597 0VER THE RICE RIVER DISTRICT 1, ST. LOUIS COUNTY 12-inch Diameter Timber Pile INSPECTION AND SOUNDING PLAN TYPICAL END VIEW OF ABUTMENTS TYPICAL END VIEW OF BENT Abandoned 12-inch Diameter Timber Pile DRAWN BY: MBP 123 North Wacker Drive DATE: JUNE 21, 2016 Page 14 of 15 1 Inspection Note Number CHECKED BY: LJ CODE: Suite 900 Chicago, Il (312) SCALE: NTS FIGURE NO.: 1

15 ~ South Abutment ~ Bent 1 ~ North Abutment 23' 23' Shoreline Shoreline W.L. El Channel Bottom on 9/19/2012 Channel Bottom 90.0 on 6/21/ DOWNSTREAM FASCIA PROFILE ~ South Abutment ~ Bent 1 ~ North Abutment 23' 23' Shoreline Shoreline W.L. El Channel Bottom on 9/19/ Channel Bottom on 6/21/ UPSTREAM FASCIA PROFILE Note: Refer to Figure 1 for General Notes. MINNESOTA DEPARTMENT OF TRANSPORTATION UNDERWATER BRIDGE INSPECTION STRUCTURE NO CR 597 OVER THE RICE RIVER DISTRICT 1, ST. LOUIS COUNTY UPSTREAM AND DOWNSTREAM FASCIA PROFILES DRAWN BY: MBP 123 North Wacker Drive DATE: JUNE 21, 2016 CHECKED BY: LJ Suite 900 Chicago, Il (312) SCALE: 1"=5'-0" Page 15 of 15 CODE: FIGURE NO.: 2

2017 UNDERWATER BRIDGE INSPECTION REPORT. TWP 332 over ROOT RIVER. Date of Inspection: Equipment Used: 10/22/2016. Town or Township Highway Agency

2017 UNDERWATER BRIDGE INSPECTION REPORT. TWP 332 over ROOT RIVER. Date of Inspection: Equipment Used: 10/22/2016. Town or Township Highway Agency 2017 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # L4870 TWP 332 over ROOT RIVER DISTRICT: District 6 COUNTY: Fillmore CITY/TOWNSHIP: JORDAN STATE: Minnesota Date of Inspection: Equipment Used: 10/22/2016

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7685 CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7883 CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 4992 CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 89188 7 th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER OCTOBER 2, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 36508 CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS

More information

2011 BRIDGE INSPECTION REPORT

2011 BRIDGE INSPECTION REPORT 2011 BRIDGE INSPECTION REPORT BYRD PARK PUMP STATION BRIDGE OVER KANAWHA CANAL April 2011 FINAL December 2011 Looking - from Abutment B to Abutment A Prepared by: WHITMAN, REQUARDT, & ASSOCIATES, LLP 9030

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT STATE BRIDGE NO. 6081 CITY OR COUNTY 053 LOUDOUN TYPE OF BRIDGE REPORT: REGULAR INSPECTION JANUARY 2016 BRIDGE NAME: DIRECTION: FOREST MILLS

More information

Four simply supported steel plate girders (appear to be an old railcar).

Four simply supported steel plate girders (appear to be an old railcar). BRIDGE INSPECTION BRIDGE NO./NAME N4-005: Akolkolex Crawford FSR (19.0 km) Inspection Date: September 22 nd, 2012 Inspected By: M. Hanson, R. Veitch Year Built: 1982 Number of Spans: 1 Span Lengths: Superstructure

More information

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017 Introduction Substructure Inspection and Rating That portion of the bridge located below the bearings Abutments Piers Rated separately Purpose is to: Receive the loads from the superstructure Transfer

More information

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection No. 1 2/26/2016 830 MSE Wall V 26 Is ADE 830 MSE Wall to be used in conjunction with NBE 218 Other Abutment

More information

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report Executive Summary The No. 01607 carries the Trans-Canada Highway over Quartz Creek, approximately 45 km northwest of Golden, BC. As part of an Enhanced Bridge Inspection Program, the BC Ministry of Transportation

More information

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK Joseph Navarra, P.E, Maryland State Highway Administration, 410-545-8315, jnavarra@sha.state.md.us ABSTRACT The MDSHA

More information

Conditional assessment of Kiri Bridge in Shkoder, Albania

Conditional assessment of Kiri Bridge in Shkoder, Albania Conditional assessment of Kiri Bridge in Shkoder, Albania Gentian Rexhaj 1, Enea Mustafaraj 2 1 2 Department of Civil Engineering, Epoka University, Albania 2 Department of Civil Engineering, Epoka University,

More information

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue FHWA Rhode Island Showcase October 30, 2014 Accent image here Primary Image here Presentation Outline Overview of the Project Scope ABC Project

More information

Ahmed Mongi, M.S., P.E. Engineering Division

Ahmed Mongi, M.S., P.E. Engineering Division 1 Ahmed Mongi, M.S., P.E. Engineering Division 2 Honey Creek Bridge Completed in 2006 at a cost of $2.6 Million Precast pier caps and abutments. 3 Honey Creek Bridge Bridge closed for 60 days Simple span

More information

Appendix B. Shallow Foundations Report

Appendix B. Shallow Foundations Report 12/10/2013 GEOTECHNICAL MANUAL Appendix B. Shallow Foundations Report PLEASE NOTE A sample foundations report is included here for reference. It is provided as an example of content, format, and organization

More information

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN 7-1.0 INTRODUCTION 7-2.0 RIGID PAVEMENT DESIGN 7-2.01 Cross Sections 7-2.02 Ramps and Loops with Storage Area 7-2.03 Major Forks, Branch

More information

Integral Abutment Bridge Design with Soil Structure Interaction

Integral Abutment Bridge Design with Soil Structure Interaction Integral Abutment Bridge Design with Soil Structure Interaction Thursday, May 11, 2017 3:00 PM 4:00 PM EST Speaker Engineer: Suthichai Saelim Project Location WESTBOROUGH Railroad HOPKINTON Project Location

More information

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA IRFAN A. ALVI, P.E., Alvi Associates, Inc., Baltimore, MD IBC-02-25 KEYWORDS: box girder, counterweight abutment, curved girder, high-performance

More information

Bridge Office Trunk Highway Bridge Flood Response Plan

Bridge Office Trunk Highway Bridge Flood Response Plan Bridge Office Trunk Highway Bridge Flood Response Plan Updated 7/18/2012 Purpose Bridges are vulnerable to damage and failure during flooding. Scour may undermine the bridge foundations or remove the protection

More information

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse)

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) AGENDA Project Overview and Need Design and Special Provisions Construction Engineering

More information

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS Louis J. Ruzzi P.E., PennDOT District 11-0 Bridge Engineer John Myler, PennDOT Assistant Construction Engineer, District 11-0 Bala

More information

Appendix C Guidelines for Design of Integral Abutments March 3, 2003

Appendix C Guidelines for Design of Integral Abutments March 3, 2003 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT s and the UK Highways Agency. They provide guidance and outline the issues that need to be considered and should

More information

APPENDIX A INTEGRAL ABUTMENTS

APPENDIX A INTEGRAL ABUTMENTS APPENDIX A INTEGRAL ABUTMENTS Appendix A Guidelines for Design of Integral Abutments Rev. 1 - September, 2007 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT

More information

\\H\15\ PH9 Inspection Photos

\\H\15\ PH9 Inspection Photos SHOP SLIDE Photo 1. at cracking across the footpath at the end of the Hwy 2 EB to Hwy 684 SB off ramp at the 99 Ave. intersection. Drop in asphalt trail (background) has worsened since 2013 and is now

More information

Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota

Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota Kamal Saffarinia 1, G. Kenneth Young 2, J. Sterling Jones 3, and Stuart Stein 4 This paper investigates two-dimensional

More information

Winona Bridge Visual Quality Review Committee

Winona Bridge Visual Quality Review Committee Winona Bridge Visual Quality Review Committee Summary of Preferred Features October 7, 2014 Creating Bridges As Art 1 Summary of Preferred Features Based on Visual Quality Review Committee Final Design

More information

Stairways and Ladders. OSHA Office of Training & Education 1

Stairways and Ladders. OSHA Office of Training & Education 1 Stairways and Ladders OSHA Office of Training & Education 1 Hazards Stairways and ladders cause many injuries and fatalities among construction workers About half the injuries caused by slips, trips and

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: FEBRUARY 12 THROUGH FEBRUARY

More information

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill. Bridge Applications Technology The Reinforced Earth Company (RECo) offers a variety of bridge abutment and bridge crossing solutions, each are based on project specific requirements. Bridge abutments are

More information

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge Modular Steel Bridges Stark County Fischer Bridge Bottineau County Oak Creek Bridge This John Deere grain hauler was too heavy for the bridge. OOPS! An excavator and tow truck are needed to remove the

More information

Inspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin.

Inspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin. Inspection Report River Falls Hydroelectric Project FERC Project No. P-10489 Junction Falls Dam River Falls, Wisconsin Prepared for: River Falls Municipal Utilities River Falls, Wisconsin December 2009

More information

Sign Retroreflectivity A Minnesota Toolkit

Sign Retroreflectivity A Minnesota Toolkit Sign Retroreflectivity A Minnesota Toolkit Mike Marti, Primary Author SRF Consulting Group June 2010 Research Project Final Report #2010RIC02 VISUAL NIGHTTIME INSPECTION Method Description: The retroreflectivity

More information

Emergency Bridge Stabilization at Mile Watrous Subdivision

Emergency Bridge Stabilization at Mile Watrous Subdivision Emergency Bridge Stabilization at Mile 189.70 Watrous Subdivision Christophe Deniaud, Ph.D., P.Eng. Bridge Engineer, CN 10004-104 Avenue Edmonton, Alberta, Canada T5J 0K2 Tel: (780) 421-6021 Fax: (780)

More information

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 SITE NUMBER AND NAME: NC 52 Pembina River Bridge LEGAL DESCRIPTION: SE 1-50-9-W5M STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 NAD 83 COORDINATES:

More information

Bank Erosion and Bridge Scour

Bank Erosion and Bridge Scour JULY 2017 NCHRP PRACTICE-READY SOLUTIONS FOR Bank Erosion and Bridge Scour NCHRP NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM RESEARCH TOPIC HIGHLIGHTS INTRODUCTION Bank Erosion and Bridge Scour: NCHRP

More information

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint Introduction The purpose of this white paper is to provide information regarding the potential for fractures

More information

County of Orange. Presented to the Flood Division August 13, 2001 by Nadeem Majaj

County of Orange. Presented to the Flood Division August 13, 2001 by Nadeem Majaj Using HECRAS TO Evaluate Scour At Bridges County of Orange Presented to the Flood Division August 3, 200 by Nadeem Majaj Approximately 575,000 bridges are built over waterways in the US. The most common

More information

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014 Updated: 5/15/14 1 What was driver for deciding to slide vs. roll? Overall weight? 2 1. Why the two different slide methods? 2. How much experience should your contractor have to perform the slide work?

More information

Using the sharp-crested weir formula the outflow was:

Using the sharp-crested weir formula the outflow was: Date: 2009 July 16 11:00 AM 14 Island Lake Dam Inspection Report Persons Present: Bryon Keene, P.Eng. Harry Stinson Brett Dark (14 Island Lake Association) Peter Peart (14 Island Lake Association) The

More information

1 Study the drawings and the installation. 2 Ensure that you have the correct components. 3 Follow the manufacturer s instructions

1 Study the drawings and the installation. 2 Ensure that you have the correct components. 3 Follow the manufacturer s instructions 1 Study the drawings and the installation plan ahead of time. Consider laying the components out in the approximate order in which they will be installed. This will help workers become familiar with the

More information

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report Final Report VTRC 06-R35 Virginia Transportation Research Council research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report http:/www.virginiadot.org/vtrc/main/online_reports/pdf/06-r35.pdf

More information

MBW3-45 ELR: No coring surveys have been found for this structure. There are no records of any previous inspections of the structure.

MBW3-45 ELR: No coring surveys have been found for this structure. There are no records of any previous inspections of the structure. Scour Assessment Report Location Plan: Scale 1:5,000 MBW3-45 Score: 16.86 ELR: Contains Ordnance Survey data Crown copyright and database right 2010 Category: HIGH Assessment Date: 19/11/2010 Contract:

More information

PENNDOT e-notification

PENNDOT e-notification PENNDOT e-notification Bureau of Design Engineering Computing Management Division BRADD No. 027 August 30, 2010 Release of Version 3.1.5.0 PennDOT's Bridge Automated Design and Drafting Software (BRADD)

More information

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION 3.2.5.0 Since the release of BRADD Version 3.2.4.3, several operational issues have been addressed. This release of BRADD Version 3.2.5.0 contains the following

More information

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and Overview Design criteria for I-90 over Kishwaukee Integral Abutment Bridges (IAB) Design Criteria Design analysis, details and construction Lessons Learned during construction Instrumentation by Illinois

More information

State-Aid Bridge News August 2, 2005

State-Aid Bridge News August 2, 2005 State-Aid Bridge News August 2, 2005 Bridge Hydraulic Information The FHWA has been inquiring about our Scour Program. In particular, there are two areas of concern; 1. Are our Scour Action Plans current

More information

Shifting the Canning Bus Bridge Sideways

Shifting the Canning Bus Bridge Sideways Shifting the Canning Bus Bridge Sideways Ros MacKinlay Design Engineer, Wyche Consulting SYNOPSIS The Perth Mandurah railway proposed in 2002 required the replacement of an existing Kwinana Freeway bus

More information

Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways

Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways ANNUAL REPORT FOR FY 2011 ODOT SPR ITEM NUMBER 2228 Submitted to: John Bowman, P.E. Planning and Research

More information

OVER US 6 LATERAL BRIDGE SLIDE: I-75

OVER US 6 LATERAL BRIDGE SLIDE: I-75 LATERAL BRIDGE SLIDE: I-75 OVER US 6 Bob Beasley, PE, Ohio Bridge Manager, Arcadis U.S., Inc. Todd Lezon, Regional Manager, Kokosing Construction Company, Inc. November 4, 2016 1 Agenda Design Bob Beasley,

More information

Culvert Safety Inspection Report (CSIR)

Culvert Safety Inspection Report (CSIR) Conference Workshop Culvert Safety Inspection Report (CSIR) Rich Kathrens MDOT Bridge Safety Inspection Engineer kathrens@michigan.gov March 22, 2015 Culvert Safety Inspection Updates Pre 2015 CSIR CSIR

More information

Flume Installation Instructions

Flume Installation Instructions Flume Installation Instructions To ensure a successful installation, it is important to keep the following points in mind: 1) There should be no bend, dips, elbows, or flow junction immediately upstream

More information

Urban Drainage and Flood Control District. Goldsmith Iliff Pond E-19 Survey

Urban Drainage and Flood Control District. Goldsmith Iliff Pond E-19 Survey Urban Drainage and Flood Control District Goldsmith Gulch @ Iliff Pond E-19 Survey GOLDSMITH GULCH @ ILIFF ALERT ID: 653/654 LID: ILFC2 Prepared by: HDR Engineering, Inc. 303 E 17 th Ave. Suite 700 Denver

More information

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563 Interstate Power and Light Company Burlington Generation Station CCR Surface Impoundment Annual Inspection Report 154.018.012.001 Report issued: December 21, 2016 Hard Hat Services ph: 877-630-7428 hardhatinc.com

More information

Modified Sheet Pile Abutment for Low-Volume Road Bridge

Modified Sheet Pile Abutment for Low-Volume Road Bridge Modified Sheet Pile Abutment for Low-Volume Road Bridge Ryan R. Evans Department of Civil, Construction, and Environmental Engineering Iowa State University 176 Town Engineering Ames, IA 50011 ryevans@iastate.edu

More information

ACCELERATED BRIDGE REPLACEMENT

ACCELERATED BRIDGE REPLACEMENT Christopher Beck Chief Engineer: Bridge & Structures Northern Indiana Commuter Transportation District 601 North Roeske Avenue Michigan City, IN chris.beck@nictd.com Accelerated Bridge Replacement (ABR)

More information

American Society of Highway. Beardsley Connector Project. Jacob Dean

American Society of Highway. Beardsley Connector Project. Jacob Dean American Society of Highway Engineers (ASHE) Beardsley Connector Project Gary Fromm, PE Design Manager Jacobs Jacob Dean Project Manager Haydon Building Corp. Thinking Outside the Box: Why Go In Circles?

More information

v Feature Stamping SMS 13.0 Tutorial Prerequisites Requirements Map Module Mesh Module Scatter Module Time minutes

v Feature Stamping SMS 13.0 Tutorial Prerequisites Requirements Map Module Mesh Module Scatter Module Time minutes v. 13.0 SMS 13.0 Tutorial Objectives Learn how to use conceptual modeling techniques to create numerical models which incorporate flow control structures into existing bathymetry. The flow control structures

More information

Semi-Integral Abutment Bridges

Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Leslie Street Over Hwy 407 Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Semi-Integral Abutment Bridges

More information

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Filed: 2018-07-04, EB-2018-0108, Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889

More information

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A construction camera has been installed to view images of the bridge construction. Images are updated on

More information

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge R04 ABC Project Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge Lead Adopter SHRP2 Solutions Innovative

More information

5 DAMAGE TO TRANSPORTATION FACILITIES

5 DAMAGE TO TRANSPORTATION FACILITIES 5 DAMAGE TO TRANSPORTATION FACILITIES In the Kocaeli, Turkey earthquake of August 17, 1999, extensive damage of transportation facilities occurred in the Kocaeli and Sakarya region, Turkey as shown in

More information

New AASHTO Bridge Inspection Process

New AASHTO Bridge Inspection Process New AASHTO Bridge Inspection Process Gary L. Bowling, Oregon DOT Oregon Department of Transportation How we got to where we are today The current AASHTO CoRe Element CS Descriptions use numerous general

More information

CHAPTER 11 APPENDIX D

CHAPTER 11 APPENDIX D OFFICE OF STRUCTURES STRUCTURE HYDROLOGY AND HYDRAULICS DIVISION CHAPTER 11 APPENDIX D SCOUR COUNTERMEASURES FOR PIERS AND ABUTMENTS MAY 2015 Maryland SHA Office of Structures, Chapter 11, Appendix D May2015Page

More information

CORRIENTE RESOURCES INC.

CORRIENTE RESOURCES INC. CORRIENTE RESOURCES INC. MIRADOR PROJECT Bridge Review from Site to Puerto Bolivar, Ecuador OVER20YEARSOF SERVICE ConsultantsInternational Inc. 1983-2003 1212-750West Pender Street Vancouver BritishColumbia

More information

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples BY MARTIN P. BURKE, JR. Innumerable bridges both in the U.S. and abroad have been, and continue to be, damaged by the restrained growth

More information

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes

Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes Analyses of State Highway Bridges Damaged in the Darfield and Christchurch Earthquakes J. H. Wood John Wood Consulting, Lower Hutt. ABSTRACT: 2012 NZSEE Conference Twelve State Highway (SH) bridges subjected

More information

Prepared for Friends of the Corte Madera Creek Watershed. By Ross Taylor and Associates

Prepared for Friends of the Corte Madera Creek Watershed. By Ross Taylor and Associates CATALOG OF STREAM CROSSINGS WITH CULVERTS AND OTHER MANMADE IMPEDIMENTS TO FISH PASSAGE LOCATED ON ANADROMOUS STREAM REACHES WITHIN FAIRFAX CREEK, CORTE MADERA CREEK WATERSHED, MARIN COUNTY, CA. Prepared

More information

Low-Volume Road Abutment Design Standards

Low-Volume Road Abutment Design Standards Low-Volume Road Abutment Design Standards V.W. Robbins HNTB Corporation 7450 W. 130th St., Suite 400 Overland Park, KS 66213 vrobbins@hntb.com F. Wayne Klaiber Bridge Engineering Center 418 Town Engineering

More information

Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3

Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3 F. W. Klaiber, D. J. White, T. J. Wipf, B. M. Phares, V. W. Robbins Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3 Development of Design Methodology August 2004 Sponsored

More information

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments

A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments A Tale of Two Bridges: Comparison between the Seismic Performance of Flexible and Rigid Abutments A.M. Morsy. Department of Civil, Architectural, and Environmental Engineering, The University of Texas

More information

PRELIMINARY GEOTECHNICAL DESIGN

PRELIMINARY GEOTECHNICAL DESIGN PNCC Manawatu River Pedestrian/ Cycle Bridge PRELIMINARY GEOTECHNICAL DESIGN 1 Introduction Opus has been commissioned by the Palmerston North City Council (PNCC) to prepare a Detailed Business Case (DBC)

More information

ABSCOUR 9 USERS MANUAL

ABSCOUR 9 USERS MANUAL OFFICE OF STRUCTURES BRIDGE SCOUR PROGRAM CHAPTER 11 APPENDIX A ABSCOUR 9 USERS MANUAL PART 1: DERIVATION OF METHODOLOGY APRIL 2011 Preface ABSCOUR 9, Build 2.3 is the current version of this program as

More information

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION 3.2.0.0 Since the release of BRADD Version 3.1.6.2, several major enhancements have been made to the software and many reported operational issues have been

More information

Hydrau-Tech, Inc. Engineering & Software

Hydrau-Tech, Inc. Engineering & Software Hydrau-Tech, Inc. Engineering & Software HYDRAU-TECH, INC. H ydrau-tech, Inc. is an engineering consulting firm specializing since 1986 in openchannel hydraulics, watershed, river, and reservoir sedimentation,

More information

Feature Stamping SURFACE WATER MODELING SYSTEM. 1 Introduction. 2 Opening a Background Image

Feature Stamping SURFACE WATER MODELING SYSTEM. 1 Introduction. 2 Opening a Background Image SURFACE WATER MODELING SYSTEM Feature Stamping 1 Introduction In this lesson you will learn how to use conceptual modeling techniques to create numerical models that incorporate flow control structures

More information

Integral bridges and environmental conditions

Integral bridges and environmental conditions Integral bridges and environmental conditions COMISU CLAUDIU-CRISTIAN, BOACĂ GHEORGHITĂ Department of Roads and Foundations Faculty of Civil Engineering and Building Services The "Gheorghe Asachi" Technical

More information

Procedure to Quantify Consequences of Delayed Maintenance of Highway Signs

Procedure to Quantify Consequences of Delayed Maintenance of Highway Signs A P P E N D I X I Procedure to Quantify Consequences of Delayed Maintenance of Highway Signs The purpose of highway signs is to communicate the rules, warnings, guidance, and other highway agency information

More information

Effect of Pile Orientation in Skewed Integral Abutment Bridges

Effect of Pile Orientation in Skewed Integral Abutment Bridges Effect of Pile Orientation in Skewed Integral Abutment Bridges RABIH NAJIB, Ph.D., PE, Alpha Corporation, Baltimore, Maryland and AMDE M. AMDE, Ph.D., PE, University of Maryland, College Park, Maryland

More information

Bengt H. Fellenius. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot. Amsterdam.

Bengt H. Fellenius. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot. Amsterdam. Wick Drains and Piling for Cai Mep Container Port, Vietnam, and the true cost of 5 cent per foot Bengt H. Fellenius Amsterdam May 27, 216 Fellenius, B.H. and Nguyen, M.H., 213. Wick Drains and Piling for

More information

Potholes: Prevent Before They Present

Potholes: Prevent Before They Present : Prevent Before They Present Dave Bergner, M.A., PWLF Mike Hale, P.E., P.L.S, M.S.C.E. TRB/ AASHTO Transportation Infrastructure Maintenance and Operations Conference, July 21, 2015 Des Moines, IA c.

More information

v Feature Stamping SMS 12.0 Tutorial Prerequisites Requirements TABS model Map Module Mesh Module Scatter Module Time minutes

v Feature Stamping SMS 12.0 Tutorial Prerequisites Requirements TABS model Map Module Mesh Module Scatter Module Time minutes v. 12.0 SMS 12.0 Tutorial Objectives In this lesson will teach how to use conceptual modeling techniques to create numerical models that incorporate flow control structures into existing bathymetry. The

More information

Simplified Analytical Model of a Covered Queen-Post-Truss Timber Bridge

Simplified Analytical Model of a Covered Queen-Post-Truss Timber Bridge Simplified Analytical Model of a Covered Queen-Post-Truss Timber Bridge Fouad Fanous, Douglas Rammer & Terry Wipf, Bridge Engineering Center Forest Product Laboratory Study Scope Objective Develop a simple

More information

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri Adams et al. (2012), FHWA Geosynthetic Reinforced Soil Integrated Bridge System Interim Implementation

More information

Service Life of Aluminized Type 2 Coated Steel Pipe: Predictions vs. Actual

Service Life of Aluminized Type 2 Coated Steel Pipe: Predictions vs. Actual Service Life of Aluminized Type 2 Coated Steel Pipe: Predictions vs. Actual Resource # 07-135 (04/16) 2 2016 American Concrete Pipe Association, all rights reserved. The last comprehensive inspection of

More information

Critically damaged bridges & concepts for earthquake recovery

Critically damaged bridges & concepts for earthquake recovery Critically damaged bridges & concepts for earthquake recovery J. Waldin, J. Jennings & P. Routledge Opus International Consultants Ltd, Christchurch, New Zealand 2012 NZSEE Conference ABSTRACT: This paper

More information

1 Exam Prep. SMACNA Architectural Sheet Metal Questions

1 Exam Prep. SMACNA Architectural Sheet Metal Questions 1 Exam Prep SMN rchitectural Sheet Metal Questions 1. Which of the following is not an advantage of terne? Lightweight High expansion rate Low expansion rate urable 2. ownspouts should be constructed with

More information

Update on Seismic Behavior and Design of

Update on Seismic Behavior and Design of Update on Seismic Behavior and Design of Steel Plate Girder Bid Bridges Ahmad M. Itani, Ph.D., P.E., S.E. Professor Department of Civil and Environmental Engineering University of Nevada, Reno Background

More information

Figure 3: Analytic procedure

Figure 3: Analytic procedure International Journal of Scientific and Research ublications, Volume 7, Issue 5, May 2017 567 Investigation of Integral Bridge Effect under Dynamic Loading Haymanmyintmaung *,kyawlinnhtat ** * Department

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Fly Ash Pond Big Sandy Plant Louisa, Kentucky October, 2016 Prepared for: Kentucky Power Big Sandy Plant Louisa, Kentucky Prepared by: American Electric Power

More information

A STEP IN THE RIGHT DIRECTION: Presented By. Part I Problems Underfoot EFFECTIVE SIDEWALK MAINTENANCE MANAGEMENT. It Didn t Happen Overnight

A STEP IN THE RIGHT DIRECTION: Presented By. Part I Problems Underfoot EFFECTIVE SIDEWALK MAINTENANCE MANAGEMENT. It Didn t Happen Overnight 1 A STEP IN THE RIGHT DIRECTION: EFFECTIVE SIDEWALK MAINTENANCE MANAGEMENT FINAL,Sept 6, 07 1 Presented By Overland Park, Kansas, Public Works Department Dave Bergner, Superintendent Janet Luessenheide,

More information

Non-Destructive Testing of Drilled Shafts Current Practices and New Methods

Non-Destructive Testing of Drilled Shafts Current Practices and New Methods Non-Destructive Testing of Drilled Shafts Current Practices and New Methods Brent Robinson, Pile Dynamics, Inc. 2012 Pile Dynamics, Inc. Foundation & Geotechnical Engineering Why Test Integrity? Survey

More information

Earthquake Resistance of Bridges With Friction Slab Abutments

Earthquake Resistance of Bridges With Friction Slab Abutments Earthquake Resistance of s With Friction Slab Abutments J. H. Wood John Wood Consulting, Lower Hutt. ABSTRACT: 2010 NZSEE Conference Findings from experimental and numerical research on the force resistance

More information

COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES.

COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES. COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES Authors D. Nyborg, Research Physicist, TISEC Inc., Montreal;

More information

Design of Dingley Bypass Integral Bridges

Design of Dingley Bypass Integral Bridges Design of Dingley Bypass Integral Bridges Dr. Kabir Patoary Principal Engineer Bridges GHD Elder St South Underpass Tekla Model Presentation Outline 1. Overview of Dingley Bypass 2. Design of Integral

More information