2017 UNDERWATER BRIDGE INSPECTION REPORT. TWP 332 over ROOT RIVER. Date of Inspection: Equipment Used: 10/22/2016. Town or Township Highway Agency

Size: px
Start display at page:

Download "2017 UNDERWATER BRIDGE INSPECTION REPORT. TWP 332 over ROOT RIVER. Date of Inspection: Equipment Used: 10/22/2016. Town or Township Highway Agency"

Transcription

1 2017 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # L4870 TWP 332 over ROOT RIVER DISTRICT: District 6 COUNTY: Fillmore CITY/TOWNSHIP: JORDAN STATE: Minnesota Date of Inspection: Equipment Used: 10/22/2016 Owner: Town or Township Highway Agency Inspected By: Stromberg, Dan Report Written By: Dan Stromberg Report Reviewed By: Final Report Date:

2 TABLE OF CONTENTS PAGE NUMBER UNDERWATER SUMMARY 3 UNDERWATER INSPECTION 4 UNDERWATER INSPECTION PROCEDURES 6 STRUCTURE INVENTORY 7 ELEMENTS 8 PICTURES 11 BRIDGE L4870 UNDERWATER INSPECTION DRAWINGS

3 UNDERWATER INSPECTION REPORT SUMMARY The substructure units inspected at Bridge L4870, the North and South Abutments, were found to be in satisfactory to fair condition with no defects of notable structural significance below water. Random areas of section loss were observed along the submerged abutment walls with average penetrations of 6 to 12 inches, and in some instances, with exposed and corroded reinforcing steel. A section of the concrete facing was undermined/undercut along the South Abutment exposing the underlying original masonry wall, which was generally in good condition. Additionally, a section of the concrete facing was undermined/undercut along the North Abutment, but the face of the original masonry abutment was not encountered. Overall, the channel bottom configuration appeared to be in stable condition, with no notable scour depressions observed and just some minor general aggradation of bottom material since the last inspection. INSPECTION FINDINGS 1. The channel bottom at both abutments consisted of riprap allowing no probe rod penetration. Along the face of the South Abutment there was up to 6 inches of soft silty infill. 2. An area of poor consolidation, 3 feet wide, was observed on the east corner of the South Abutment extending from 6 inches below to 1 1/2" inches above the waterline with 5 inches of maximum penetration. 3. A 6 inch band of poorly consolidated concrete was observed at the waterline extending from the downstream 1/4 point to the east wingwall of the South Abutment. 4. The upstream half (from 12 feet downstream of the upstream corner to the upstream corner) of the South Abutment concrete wall facing exhibited undermining that was 1.5 feet high with up to 1.5 feet of penetration, which exposed the underlying masonry (original construction). Random areas of section loss were observed on the submerged portion of the South Abutment facing with average penetrations of 6 inches exposing heavily corroded vertical reinforcing steel near the center of the abutment. 5. A concrete ledge was located at 1.4 feet below the waterline at the South Abutment and 1.2 feet below the waterline at the North Abutment. The concrete was irregular with up to 12 inch deep irregularities. The North Abutment step was undercut toward the channel bottom up to 18 inches. The face of the original masonry abutment was not encountered along the undercut. 6. Random areas of section loss were observed on the submerged portion of the North Abutment with average penetrations of 12 inches and no exposed reinforcing steel detected. 7. A formed steel angle was exposed due to an area of section loss, up to 1 foot wide and 4 inches deep, on the west corner of the South Abutment extending from 4 feet above to 1.5 foot below the waterline. RECOMMENDATIONS (A) Reinspect the submerged substructure units at the normal maximum recommended (NBIS) interval of sixty (60) months. Contractor: Contractor Job Number: Collins Engineers, Inc Page 3 of 17

4 UNDERWATER INSPECTION 1. BRIDGE DATA Bridge #: Feature Intersected: Facility Carried: District: L4870 ROOT RIVER TWP 332 District 6 County: Fillmore Bridge Description: The superstructure consists of a single span, multiple steel stringer structure supporting a timber deck. The superstructure is supported by two masonry stone/concrete faced (encased) abutments. No design drawings or plans were available for this bridge; therefore, the type of substructure foundation is not known. 2. INSPECTION DATA Professional Engineer/Team Leader: Inspection Diver: Date of Underwater Inspection: Weather Conditions: Underwater Visibility (feet): Waterway Velocity (ft/sec): Daniel G. Stromberg Daniel G. Stromberg 10/22/2016 Sunny, 65 F 3 feet 0.5 ft/sec 3. SUBSTRUCTURE INSPECTION DATA Substructure(s) Inspected: The North and South Abutments. General Shape: The abutments consist of a masonry breastwall covered by a concrete facing (encasement) with two adjoining skewed wingwalls. Maximum Water Depth at Substructure(s) Inspected (feet): 5.0 feet 4. WATERLINE DATUM Water Level Reference: Waterline Elevation (feet): Description: The bottom of the outermost steel stringer on the east side of the North Abutment feet The waterline was located approximately 8.9 feet below the reference. 5. NBIS CODING INFORMATION (Minnesota specific codes are used for 92B and 113) Item 60: Substructure: Item 61: Channel and Channel Protection: Item 62: Culvert: Item 92B: Underwater Inspection: Code: Code: Code: Code: 5 6 Y 48 10/2016 Page 4 of 17

5 Item 113: Scour Critical Bridge: Code: R Bridge is scour critical because abutment or pier foundation is rated as unstable due to observed scour at bridge site. Yes X No (Mark your selection with an X) 6. STRUCTURAL ELEMENT CONDITION RATING Conditions ELEM # Element Description Quantity Unit CS1 CS2 CS3 CS4 215 Reinforced Concrete Abutment 73 LF Scour 1 EA 1 Page 5 of 17

6 UNDERWATER INSPECTION INSPECTION PROCEDURES The routine underwater inspection of Bridge L4870 (TWP 332 over Root River) was completed on October 22, The underwater inspection was conducted from the shore. The inspection was conducted by a team consisting of a Professional Engineer Diver with a valid MnDOT Team Leader certification, a backup diver and dive tender. The inspection utilized commercial dive equipment and techniques (SSA and/or SCUBA) in accordance with OSHA regulations. Profiles were taken along the upstream and downstream faces of the bridge and around the periphery of substructure units to determine the presence, location, and area of scour. The bridge elements inspected consisted of two masonry stone/concrete faced (encased) abutments. No design drawings or plans were available for this bridge; therefore, the type of substructure foundation is not known. Inspection procedures followed FHWA guidance and the MnDOT Bridge and Structure Inspection Program Manual with channel bottom probing to search for foundations. The maximum routine underwater inspection frequency is recommended to remain at 60 months based on those findings and risk factors. Also, inspection procedures should continue to follow the above approach and standard guidance with 100% Level I and 10% Level II intensity efforts. Page 6 of 17

7 Minnesota Structure Inventory Report Bridge ID: L4870 TWP 332 over ROOT RIVER Date: 01/17/ G E N E R A L + + R O A D W A Y + + I N S P E C T I O N + Agency Br. No. Crew Bridge Match ID (TIS) 0 Userkey 63 District 06 County Fillmore Route Sys 08 - TWNS Number 332 Functionally Obsolete City Sect., Twp., Range Main Span Type 3 - Steel Median Width On Bridge Main Span Design Main Span Detail Appr. Span Type Appr. Span Design Appr. Span Detail Skew 0 Culvert Type Barrel Length Cantilever ID MAIN: 1 Main Span Length Structure Length 01 - Beam Span Number of Spans APPR: 0 TOTAL: 52.4 ft. Deck Width (Out-to-Out) 16.0 ft. Deck Material Wear Surf Type Wear Surf Install Year Wear Course/Fill Depth Deck Membrane Deck Rebars Deck Rebars Install Year Structure Area (Out-to-Out) 963 sq. ft. Roadway Area (Curb-to-Curb) Sidewalk Width 50A. Lt 0.00 Curb Height 0.5 MI S OF JCT CSAH 5 Level of Service 1 - MAINLINE N - 12W Roadway Type Latitude ' '' Control Section (TH Only) Status Longitude ' 9.38 '' Reference Point Custodian Owner 03 - Town or Township Highway 03 - Town or Township Highway Lt 8 - Wood or Timber 8 - Gravel 0.08 ft. 0 - None N - Not Applicable (no deck) + M I S C. Structure Flared Parallel Structure Field Conn. ID Abutment Foundation (Material/Type) Pier Foundation (Material/Type) Historic Status 0 - UNKNOWN N - N/A N - N/A Underwater 60 Pinned Asbly. Spec. Feat ft. Navigation Control Year Painted 883 sq. ft. Traffic ft. 50B. Rt ft. Rt Painted Area Posted Load B R I D G E D A T A No flare 5 - Not eligible + P A I N T + ft. Bridge Railing 0 - SUBSTANDARD ft. N - No parallel structure GR Transition Appr. Guardrail GR Termini 1 - CONC Frac. Critical 0 - Not Required 0 - Not Required ft. Horizontal 1 - Object Markers 0.42 ft. Vertical Unsound Paint % Roadway Name or Description Township JORDAN TWNS 332 Desc. Loc. BMU Agreement Year Built 1938 MN Year Reconstructed FHWA Year Reconstructed MN Temporary Status Bridge Plan Location Date Opened to Traffic Maint. Area Roadway O/U Key N - Not Applicable + I N Drainage Area (sq. mi.) + W A T E R W A Y + Waterway Opening (sf.) 663 Pier Protection Posting VEH: Rating Date 02/01/2011 N - NOT REQUIRED N - NOT REQUIRED N - NOT REQUIRED D E P T H I N S P. + Y/N Freq Date 10/22/ No nav. control on Rail Type Lt 32 Rt 32 A N - N/A B N - N/A C N - N/A sq. ft. Nav. Clr. (ft.) Nav. Vert. Lift Bridge Clear. (ft.) Primer Type 0 - Other - non 3309 MN Scour Code R - CRIT - Year 2009 Finish Type L - Other (Unknown) MONITOR + C A P A C I T Y R A T I N G S + + B R I D G E 3 - One lane bridge for 2-way traffic Detour Length 5.0 mi. Lanes Route On Structure On - Off System 0 - OFF Roadway Width ft. Legislative District 27B Vertical Clearance ft. Potential ABC 2 - N/A Max. Vert. Clear. ft. Service On 1 - Highway Appr. Surface Width Service Under 0 - NO PLAN 12/1/ S T R U C T U R E + HCADT Functional Class If Divided + R D W Y Horizontal Clear. Lateral Clearance ON 1 UNDER ADT 5 - Waterway Bridge Roadway Width YEAR 1973 ADTT 09 - Rural - Local 20.0 ft. S I G N S + ft. ft. ft. ft. Structurally Deficient Sufficiency Rating 64.6 Routine Inspection Date 04/06/2015 Routine Inspection Frequency 24 Inspector Name + N B I Design Load Operating Rating Stromberg, Dan A - Open C O N D I T I O N Deck 5 Unsound Superstructure 5 Deck % Underclearances Waterway Adequacy 8 ft. ft. Approach Alignment 3 ft. 0 D I M E N S I O N S + NB-EB % SB-WB Substructure Channel 6 Culvert + N B I Structure Evaluation 5 Deck Geometry 6 SEMI: Overweight Permit Codes _ Vert. 0.0 Horiz. 0 - Other/Unknown 2 - HS TRUCK R A T I N G S + Inventory Rating 2 - HS TRUCK N Y N A P P R A I S A L R A T I N G S + N + S A F E T Y F E A T U R E S + DBL: Page 7 of 17

8 01/30/2017 MINNESOTA BRIDGE INSPECTION REPORT BRIDGE L4870 TWP 332 OVER ROOT RIVER County: City: Township: Fillmore Location: 0.5 MI S OF JCT CSAH 5 Route: 08 - TWNS 332 Ref. Pt.: JORDAN Control Section: Section: 24 Township: 104N Range: 12W Maint. Area: Span Type: 3 - Steel 2 - Stringer/Multi-beam or Local Agency Bridge Nbr.: List: Girder NBI Deck: 5 Super: 5 Sub: 5 Chan: 6 Culv: N Open, Posted, Closed: A - Open MN Scour Code: R - CRIT - MONITOR Appraisal Ratings - Approach: 3 Waterway: 8 Required Bridge Signs - Load Posting: 0 - Not Required Traffic: 0 - Not Required Horizntal: 1 - Object Markers Vertical: N - Not Applicable Length: 60.2 ft. Deck Width: 16.0 ft. Rdwy. Area/ Pct. Unsnd: 883 sq. ft. / % Paint Area/ Pct. Unsnd: sq. ft. / % Culvert: N/A Postings: Unofficial Structurally Deficient N Unofficial Functionally Obsolete Y Unofficial Sufficiency Rating 64.6 ELEM NBR ELEMENT NAME REPORT TYPE INSP. DATE QUANTITY CS 1 CS 2 CS 3 CS 4 Timber Deck 01/17/ SF Underwater 11/21/ SF Notes: [2003] - there is minor splitting, cracking, and crushing of the timber throughout the deck the top of the deck can not be viewed. [2011] - moderate deterioration throughout, 12 plank at approx. 12' long has moderate rot, splitting and decay. [2013] - removed gravel in several locations revealing moderate decay,rot and splitting present. [2015] - moderate splitting, decay and cracking throughout based off of 25% of deck revealed. Steel Open Girder/Beam 01/17/ LF Underwater 11/21/ LF Notes: [2005] - all beams are pitted along the bottom flanges and laminated along the top flanges. the West facia beam is slightly out of alignment. [2007] - There is extensive flaking rust along the upper flange of all beams. The bottom flange of all beams are pitted with prevalent surface corrosion the 1st beam from the west is out of alignment. [2011] - no change 2007/2009. [2013] - no change high water would not allow good evaluation. [2015] - all beams have severe corrosion and extensive flaking rust along the upper flange of all beams. there is 100% paint loss. Able to view all beams from north abutment Steel Protective Coating Underwater 01/17/ SF /21/2016 Notes: [2016] Migrator assumed quantity of 999 SF and estimated the condition states. 999 SF Reinforced Concrete Abutment 01/17/ LF Underwater 11/21/ LF Notes: [2016] Migrator added 40 LF to abutment quantity to account for wingwalls (CS1:0 CS2:40 CS3:0 CS4:0). [2003] - both abutments have minor cracking and spalling. [2007] - There is moderate deterioration throughout both abutments. [2011] - no change [2013] - There is a large spall at the NE corner and a large structure crack at the NW corner. [2015] - no change from 2013 notes. Wingwall notes: [2003] - all wings have minor cracking and spalling. [2011] - SE wing has large waterline, remainder minor cracks & spalls. [2013] - no notes. [2015] - minor cracks and spalls throughout. the WE wing has a large spall at waterline. Page 8 of 17

9 BRIDGE L4870 TWP 332 OVER ROOT RIVER ELEM NBR ELEMENT NAME REPORT TYPE INSP. DATE QUANTITY CS 1 CS 2 CS 3 CS 4 Metal Bridge Railing 01/17/ LF Underwater 11/21/ LF Notes: [2005] - there is minor surface corrosion. there is minor impact damage at the NW corner. [2007] - Surface corrosion is prevalent throughout both railings the NW 7' of rail has impact damage with corner connections severed. [2011] - no change 2007/2009. [2012] - rail noted above in 2009 has been repaired. [2013] - no change % paint failure. [2015] - moderate impact damage to the north 7' of west rail. surface corrosion is prevalent throughout both railings Steel Protective Coating Underwater 01/17/ SF /21/2016 Notes: [2016] Migrator assumed CS1 and a quantity of 999 SF. 999 SF Critical Deficiencies or Safety Hazards 01/17/ EA Underwater Notes: [2013] - no finding [2015] - no findings. 11/21/ EA Gravel Approach Roadway 01/17/ EA Underwater 11/21/ EA Notes: [2005] - moderate rutting and potholes on both approaches. [2007] - The approaches are in good condition. [2011] - no change [2012] - no notes [2013] - both approaches have moderate rutting. [2015] - moderate rutting throughout both approaches. Steel Section Loss 01/17/ EA Underwater Notes: [2005] - there is measurable loss on all beams. [2011] - approx. 5% section loss all upper flange. [2013] - no notes. [2015] - <5% section loss on upper flanges. 11/21/ EA Scour 01/17/ EA Underwater 11/21/ EA Notes: [2009] R - Scour critical. Monitoring required. [2013] - high water would not allow probing of abutments. [2015] - probing revealed no scour at north abutment. could not probe south abutment due too water depth. Other Bridge Signing 01/17/ EA Underwater 11/21/ EA Notes: Signs Required: Horizontal Clearance [2005] - the West delineators are missing. the East delineators are damaged. [2011] - no change [2013] - no change [2015] - west delineators are missing. east have extensive deterioration. Slopes & Slope Protection 01/17/ EA Underwater Notes: Use this element to rate the condition of slopes and slope protection. 11/21/ EA Deck & Approach Drainage 01/17/ EA Underwater Notes: Use this element to rate the condition, function, and adequacy of the drainage system. 11/21/ EA Page 9 of 17

10 BRIDGE L4870 TWP 332 OVER ROOT RIVER ELEM NBR ELEMENT NAME REPORT TYPE INSP. DATE QUANTITY CS 1 CS 2 CS 3 CS 4 Sidewalk, Curb, & Median 01/17/ EA Underwater Notes: [2003] - both curbs have minor superficial cracks. [2011] - minor deterioration both curbs. [2013] - minor deterioration both curbs. [2015] - minor deterioration throughout. 11/21/ EA Protected Species 01/17/ EA Underwater Notes: Use this element to track the presence of protected species living on this structure. 11/21/ EA General Notes: 58. Deck NBI: [2001] DECK, WEAR STRIPS AND CURBS HAVE BEEN REPLACED. [2003] - inspected by TM, DS - slope protection has been replaced. banks have been covered with riprap. [2005] - inspected by TM, DS. There is possible scour under the bridge. there is minor lateral streambed movement towards the NW wing. [2007] - inspected by DS. There is moderate bank erosion throughout the channel. There is possible scour along the South abutment. [2009] - inspected by DS, JT - there is moderate upstream and downstream bank erosion. there is a large tree growing by the NE wing. [2011] - no change [2012] - Special inspection performed by HDR Engineering on 10/19/2010 for the purpose of load rating the structure. No load posting recommended! [2013] - Approx. 6 1/2' of freeboard during inspection. There is minor bank erosion upstream and downstream. the channel has migrated and eroded NW bank due too alignment of channel. [2015] - inspected by DS - minor bank erosion upstream and downstream. see element 31 36A. Brdg Railings NBI: 36B. Transitions NBI: 36C. Appr Guardrail NBI: 36D. Appr Guardrail Terminal NBI: 59. Superstructure NBI: 60. Substructure NBI: see element 107 notes. see element 215 notes. 61. Channel NBI: 62. Culvert NBI: 71. Waterway Adeq NBI: 72. Appr Roadway Alignment NBI: Basically intolerable requiring high priority Inspector's Signature Reviewer's Signature Page 10 of 17

11 Pictures Photo 1 - Overall View of Upstream Fascia, Looking Northeast Photo 2 - Overall View of Downstream Fascia, Looking Southwest Page 11 of 17

12 Pictures Photo 3 - View of North Abutment, Looking Northeast Photo 4 - View of North Abutment, Looking Northwest Page 12 of 17

13 Pictures Photo 5 - View of South Abutment, Looking Southwest Photo 6 - View of South Abutment, Looking Southeast Page 13 of 17

14 Pictures Photo 7 - Section Loss and Undercutting at Concrete Ledge at North Abutment, Looking East Photo 8 - Poor Consolidation at Southeast Corner of South Abutment, Looking Southwest Page 14 of 17

15 Pictures Photo 9 - Section Loss at South Abutment Exposing Steel Angle, Looking Southeast Page 15 of 17

16 Page 16 of 17

17 Page 17 of 17

2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # CR

2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # CR 2016 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # 88756 CR 597 over RICE RIVER DISTRICT: District 1 COUNTY: St. Louis CITY/TOWNSHIP: ANGORA STATE: Minnesota Date of Inspection: Equipment Used: 06/21/2016

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7685 CSAH 24 OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 4992 CSAH NO. 4 OVER THE CLEARWATER RIVER (DAM) DISTRICT 2 - CLEARWATER COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7883 CRANE LAKE ROAD OVER HAWKINSON CREEK ST. LOUIS COUNTY JUNE 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 36508 CSAH NO. 6 OVER A BRANCH OF THE CALDWELL CREEK DISTRICT 1 - KOOCHICHING COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 89188 7 th STREET OVER THE ZUMBRO RIVER CITY OF ROCHESTER OCTOBER 2, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

Four simply supported steel plate girders (appear to be an old railcar).

Four simply supported steel plate girders (appear to be an old railcar). BRIDGE INSPECTION BRIDGE NO./NAME N4-005: Akolkolex Crawford FSR (19.0 km) Inspection Date: September 22 nd, 2012 Inspected By: M. Hanson, R. Veitch Year Built: 1982 Number of Spans: 1 Span Lengths: Superstructure

More information

2011 BRIDGE INSPECTION REPORT

2011 BRIDGE INSPECTION REPORT 2011 BRIDGE INSPECTION REPORT BYRD PARK PUMP STATION BRIDGE OVER KANAWHA CANAL April 2011 FINAL December 2011 Looking - from Abutment B to Abutment A Prepared by: WHITMAN, REQUARDT, & ASSOCIATES, LLP 9030

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT

VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT VIRGINIA DEPARTMENT OF TRANSPORTATION NORTHERN VIRGINIA DISTRICT STATE BRIDGE NO. 6081 CITY OR COUNTY 053 LOUDOUN TYPE OF BRIDGE REPORT: REGULAR INSPECTION JANUARY 2016 BRIDGE NAME: DIRECTION: FOREST MILLS

More information

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection

Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection Questions and Answers on VDOT's Supplement to the AASHTO Manual for Bridge Element Inspection No. 1 2/26/2016 830 MSE Wall V 26 Is ADE 830 MSE Wall to be used in conjunction with NBE 218 Other Abutment

More information

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report

Executive Summary RPT-GEN November 28. Bridge No Quartz Creek Bridge Inspection Report Executive Summary The No. 01607 carries the Trans-Canada Highway over Quartz Creek, approximately 45 km northwest of Golden, BC. As part of an Enhanced Bridge Inspection Program, the BC Ministry of Transportation

More information

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017

Introduction. Substructure Inspection and Rating. Introduction. Introduction 28/03/2017 Introduction Substructure Inspection and Rating That portion of the bridge located below the bearings Abutments Piers Rated separately Purpose is to: Receive the loads from the superstructure Transfer

More information

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK

ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK ACCELERATED BRIDGE CONSTRUCTION PROJECT: THE REPLACEMENT OF MD 362 OVER MONIE CREEK Joseph Navarra, P.E, Maryland State Highway Administration, 410-545-8315, jnavarra@sha.state.md.us ABSTRACT The MDSHA

More information

Conditional assessment of Kiri Bridge in Shkoder, Albania

Conditional assessment of Kiri Bridge in Shkoder, Albania Conditional assessment of Kiri Bridge in Shkoder, Albania Gentian Rexhaj 1, Enea Mustafaraj 2 1 2 Department of Civil Engineering, Epoka University, Albania 2 Department of Civil Engineering, Epoka University,

More information

Appendix B. Shallow Foundations Report

Appendix B. Shallow Foundations Report 12/10/2013 GEOTECHNICAL MANUAL Appendix B. Shallow Foundations Report PLEASE NOTE A sample foundations report is included here for reference. It is provided as an example of content, format, and organization

More information

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN

SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN SEPTEMBER, 2006 ROAD DESIGN MANUAL 7-0(1) CHAPTER 7 PAVEMENT DESIGN 7-1.0 INTRODUCTION 7-2.0 RIGID PAVEMENT DESIGN 7-2.01 Cross Sections 7-2.02 Ramps and Loops with Storage Area 7-2.03 Major Forks, Branch

More information

Bridge Office Trunk Highway Bridge Flood Response Plan

Bridge Office Trunk Highway Bridge Flood Response Plan Bridge Office Trunk Highway Bridge Flood Response Plan Updated 7/18/2012 Purpose Bridges are vulnerable to damage and failure during flooding. Scour may undermine the bridge foundations or remove the protection

More information

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue

ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue FHWA Rhode Island Showcase October 30, 2014 Accent image here Primary Image here Presentation Outline Overview of the Project Scope ABC Project

More information

Ahmed Mongi, M.S., P.E. Engineering Division

Ahmed Mongi, M.S., P.E. Engineering Division 1 Ahmed Mongi, M.S., P.E. Engineering Division 2 Honey Creek Bridge Completed in 2006 at a cost of $2.6 Million Precast pier caps and abutments. 3 Honey Creek Bridge Bridge closed for 60 days Simple span

More information

Inspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin.

Inspection Report. River Falls Hydroelectric Project FERC Project No. P Junction Falls Dam River Falls, Wisconsin. Inspection Report River Falls Hydroelectric Project FERC Project No. P-10489 Junction Falls Dam River Falls, Wisconsin Prepared for: River Falls Municipal Utilities River Falls, Wisconsin December 2009

More information

Bank Erosion and Bridge Scour

Bank Erosion and Bridge Scour JULY 2017 NCHRP PRACTICE-READY SOLUTIONS FOR Bank Erosion and Bridge Scour NCHRP NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM RESEARCH TOPIC HIGHLIGHTS INTRODUCTION Bank Erosion and Bridge Scour: NCHRP

More information

Integral Abutment Bridge Design with Soil Structure Interaction

Integral Abutment Bridge Design with Soil Structure Interaction Integral Abutment Bridge Design with Soil Structure Interaction Thursday, May 11, 2017 3:00 PM 4:00 PM EST Speaker Engineer: Suthichai Saelim Project Location WESTBOROUGH Railroad HOPKINTON Project Location

More information

New AASHTO Bridge Inspection Process

New AASHTO Bridge Inspection Process New AASHTO Bridge Inspection Process Gary L. Bowling, Oregon DOT Oregon Department of Transportation How we got to where we are today The current AASHTO CoRe Element CS Descriptions use numerous general

More information

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS

STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS Louis J. Ruzzi P.E., PennDOT District 11-0 Bridge Engineer John Myler, PennDOT Assistant Construction Engineer, District 11-0 Bala

More information

Winona Bridge Visual Quality Review Committee

Winona Bridge Visual Quality Review Committee Winona Bridge Visual Quality Review Committee Summary of Preferred Features October 7, 2014 Creating Bridges As Art 1 Summary of Preferred Features Based on Visual Quality Review Committee Final Design

More information

Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota

Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota Two-Dimensional Computer Modeling of Pomme de Terre River at Highways 12 and 22 in Minnesota Kamal Saffarinia 1, G. Kenneth Young 2, J. Sterling Jones 3, and Stuart Stein 4 This paper investigates two-dimensional

More information

\\H\15\ PH9 Inspection Photos

\\H\15\ PH9 Inspection Photos SHOP SLIDE Photo 1. at cracking across the footpath at the end of the Hwy 2 EB to Hwy 684 SB off ramp at the 99 Ave. intersection. Drop in asphalt trail (background) has worsened since 2013 and is now

More information

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA

Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA Three Bridges at I-64/Mercury Boulevard Interchange in Hampton, VA IRFAN A. ALVI, P.E., Alvi Associates, Inc., Baltimore, MD IBC-02-25 KEYWORDS: box girder, counterweight abutment, curved girder, high-performance

More information

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge

Modular Steel Bridges. Stark County Fischer Bridge Bottineau County Oak Creek Bridge Modular Steel Bridges Stark County Fischer Bridge Bottineau County Oak Creek Bridge This John Deere grain hauler was too heavy for the bridge. OOPS! An excavator and tow truck are needed to remove the

More information

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse)

IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT. Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) IL 115 OVER GAR CREEK ACCELERATED BRIDGE REPLACEMENT Chad Hodel, S.E., P.E. (WHKS) Stan Kaderbek, S.E., P.E. (Milhouse) AGENDA Project Overview and Need Design and Special Provisions Construction Engineering

More information

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563 Interstate Power and Light Company Burlington Generation Station CCR Surface Impoundment Annual Inspection Report 154.018.012.001 Report issued: December 21, 2016 Hard Hat Services ph: 877-630-7428 hardhatinc.com

More information

Emergency Bridge Stabilization at Mile Watrous Subdivision

Emergency Bridge Stabilization at Mile Watrous Subdivision Emergency Bridge Stabilization at Mile 189.70 Watrous Subdivision Christophe Deniaud, Ph.D., P.Eng. Bridge Engineer, CN 10004-104 Avenue Edmonton, Alberta, Canada T5J 0K2 Tel: (780) 421-6021 Fax: (780)

More information

Appendix C Guidelines for Design of Integral Abutments March 3, 2003

Appendix C Guidelines for Design of Integral Abutments March 3, 2003 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT s and the UK Highways Agency. They provide guidance and outline the issues that need to be considered and should

More information

Culvert Safety Inspection Report (CSIR)

Culvert Safety Inspection Report (CSIR) Conference Workshop Culvert Safety Inspection Report (CSIR) Rich Kathrens MDOT Bridge Safety Inspection Engineer kathrens@michigan.gov March 22, 2015 Culvert Safety Inspection Updates Pre 2015 CSIR CSIR

More information

PENNDOT e-notification

PENNDOT e-notification PENNDOT e-notification Bureau of Design Engineering Computing Management Division BRADD No. 027 August 30, 2010 Release of Version 3.1.5.0 PennDOT's Bridge Automated Design and Drafting Software (BRADD)

More information

County of Orange. Presented to the Flood Division August 13, 2001 by Nadeem Majaj

County of Orange. Presented to the Flood Division August 13, 2001 by Nadeem Majaj Using HECRAS TO Evaluate Scour At Bridges County of Orange Presented to the Flood Division August 3, 200 by Nadeem Majaj Approximately 575,000 bridges are built over waterways in the US. The most common

More information

Sign Retroreflectivity A Minnesota Toolkit

Sign Retroreflectivity A Minnesota Toolkit Sign Retroreflectivity A Minnesota Toolkit Mike Marti, Primary Author SRF Consulting Group June 2010 Research Project Final Report #2010RIC02 VISUAL NIGHTTIME INSPECTION Method Description: The retroreflectivity

More information

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill.

Technology. Reinforced Earth Wall Typical Section. Traffic Barrier. Roadway. Select Granular Material. Facing Panel Random Backfill. Bridge Applications Technology The Reinforced Earth Company (RECo) offers a variety of bridge abutment and bridge crossing solutions, each are based on project specific requirements. Bridge abutments are

More information

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and

Rebuilding and widening the 54- year-old Jane Addams Memorial Tollway into a state-of-the-art corridor linking Rockford to Elgin (three lanes) and Overview Design criteria for I-90 over Kishwaukee Integral Abutment Bridges (IAB) Design Criteria Design analysis, details and construction Lessons Learned during construction Instrumentation by Illinois

More information

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION

SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION SUMMARY OF NOVEMBER 2018 REVISIONS - VERSION 3.2.5.0 Since the release of BRADD Version 3.2.4.3, several operational issues have been addressed. This release of BRADD Version 3.2.5.0 contains the following

More information

CHAPTER 11 APPENDIX D

CHAPTER 11 APPENDIX D OFFICE OF STRUCTURES STRUCTURE HYDROLOGY AND HYDRAULICS DIVISION CHAPTER 11 APPENDIX D SCOUR COUNTERMEASURES FOR PIERS AND ABUTMENTS MAY 2015 Maryland SHA Office of Structures, Chapter 11, Appendix D May2015Page

More information

APPENDIX A INTEGRAL ABUTMENTS

APPENDIX A INTEGRAL ABUTMENTS APPENDIX A INTEGRAL ABUTMENTS Appendix A Guidelines for Design of Integral Abutments Rev. 1 - September, 2007 These guidelines draw on the experiences and practices from Ontario, the FHWA, various DOT

More information

American Society of Highway. Beardsley Connector Project. Jacob Dean

American Society of Highway. Beardsley Connector Project. Jacob Dean American Society of Highway Engineers (ASHE) Beardsley Connector Project Gary Fromm, PE Design Manager Jacobs Jacob Dean Project Manager Haydon Building Corp. Thinking Outside the Box: Why Go In Circles?

More information

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure

Lesner Bridge Replacement. April 24, 2017 Update. Construction Camera. Rendering of the Completed Lesner Bridge Structure Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A construction camera has been installed to view images of the bridge construction. Images are updated on

More information

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8

Filed: , EB , Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Filed: 2018-07-04, EB-2018-0108, Exhibit B, Tab 1, Schedule 1, Attachment 3, Page 1 of 8 Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889

More information

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39

STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 SITE NUMBER AND NAME: NC 52 Pembina River Bridge LEGAL DESCRIPTION: SE 1-50-9-W5M STONY PLAIN REGION GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM HIGHWAY AND KM: Hwy 621:02, km 16.39 NAD 83 COORDINATES:

More information

ABSCOUR 9 USERS MANUAL

ABSCOUR 9 USERS MANUAL OFFICE OF STRUCTURES BRIDGE SCOUR PROGRAM CHAPTER 11 APPENDIX A ABSCOUR 9 USERS MANUAL PART 1: DERIVATION OF METHODOLOGY APRIL 2011 Preface ABSCOUR 9, Build 2.3 is the current version of this program as

More information

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014

Webinar Q&A Documentation Slide In Bridge Construction (SIBC) Construction/Contractor Perspective March 6, 2014 Updated: 5/15/14 1 What was driver for deciding to slide vs. roll? Overall weight? 2 1. Why the two different slide methods? 2. How much experience should your contractor have to perform the slide work?

More information

v Feature Stamping SMS 13.0 Tutorial Prerequisites Requirements Map Module Mesh Module Scatter Module Time minutes

v Feature Stamping SMS 13.0 Tutorial Prerequisites Requirements Map Module Mesh Module Scatter Module Time minutes v. 13.0 SMS 13.0 Tutorial Objectives Learn how to use conceptual modeling techniques to create numerical models which incorporate flow control structures into existing bathymetry. The flow control structures

More information

CORRIENTE RESOURCES INC.

CORRIENTE RESOURCES INC. CORRIENTE RESOURCES INC. MIRADOR PROJECT Bridge Review from Site to Puerto Bolivar, Ecuador OVER20YEARSOF SERVICE ConsultantsInternational Inc. 1983-2003 1212-750West Pender Street Vancouver BritishColumbia

More information

MBW3-45 ELR: No coring surveys have been found for this structure. There are no records of any previous inspections of the structure.

MBW3-45 ELR: No coring surveys have been found for this structure. There are no records of any previous inspections of the structure. Scour Assessment Report Location Plan: Scale 1:5,000 MBW3-45 Score: 16.86 ELR: Contains Ordnance Survey data Crown copyright and database right 2010 Category: HIGH Assessment Date: 19/11/2010 Contract:

More information

Semi-Integral Abutment Bridges

Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Leslie Street Over Hwy 407 Semi-Integral Abutment Bridges Ministry of Transportation Report BO-99-03 Bridge Office Semi-Integral Abutment Bridges

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: FEBRUARY 12 THROUGH FEBRUARY

More information

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples

Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples Reducing Bridge Damage Caused by Pavement Forces Part 1: Some Examples BY MARTIN P. BURKE, JR. Innumerable bridges both in the U.S. and abroad have been, and continue to be, damaged by the restrained growth

More information

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015

Fort Goff Creek Bridge R04 ABC Project. Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge R04 ABC Project Dorie Mellon, PE Structure Policy & Innovation Division of Engineering Services Caltrans May 20, 2015 Fort Goff Creek Bridge Lead Adopter SHRP2 Solutions Innovative

More information

Using the sharp-crested weir formula the outflow was:

Using the sharp-crested weir formula the outflow was: Date: 2009 July 16 11:00 AM 14 Island Lake Dam Inspection Report Persons Present: Bryon Keene, P.Eng. Harry Stinson Brett Dark (14 Island Lake Association) Peter Peart (14 Island Lake Association) The

More information

A STEP IN THE RIGHT DIRECTION: Presented By. Part I Problems Underfoot EFFECTIVE SIDEWALK MAINTENANCE MANAGEMENT. It Didn t Happen Overnight

A STEP IN THE RIGHT DIRECTION: Presented By. Part I Problems Underfoot EFFECTIVE SIDEWALK MAINTENANCE MANAGEMENT. It Didn t Happen Overnight 1 A STEP IN THE RIGHT DIRECTION: EFFECTIVE SIDEWALK MAINTENANCE MANAGEMENT FINAL,Sept 6, 07 1 Presented By Overland Park, Kansas, Public Works Department Dave Bergner, Superintendent Janet Luessenheide,

More information

Urban Drainage and Flood Control District. Goldsmith Iliff Pond E-19 Survey

Urban Drainage and Flood Control District. Goldsmith Iliff Pond E-19 Survey Urban Drainage and Flood Control District Goldsmith Gulch @ Iliff Pond E-19 Survey GOLDSMITH GULCH @ ILIFF ALERT ID: 653/654 LID: ILFC2 Prepared by: HDR Engineering, Inc. 303 E 17 th Ave. Suite 700 Denver

More information

OVERVIEW AND IMPLEMENTATION of the TUNNEL MANAGEMENT SYSTEM. TRB Tunnel Workshop. January 11, 2009 Washington, DC

OVERVIEW AND IMPLEMENTATION of the TUNNEL MANAGEMENT SYSTEM. TRB Tunnel Workshop. January 11, 2009 Washington, DC OVERVIEW AND IMPLEMENTATION of the TUNNEL MANAGEMENT SYSTEM TRB Tunnel Workshop January 11, 2009 Washington, DC PRESENTATION TEAM Chester Allen, P.E. Martha Averso, P.E. Rick Patrick, P.E. DISCUSSION TOPICS

More information

Prepared for Friends of the Corte Madera Creek Watershed. By Ross Taylor and Associates

Prepared for Friends of the Corte Madera Creek Watershed. By Ross Taylor and Associates CATALOG OF STREAM CROSSINGS WITH CULVERTS AND OTHER MANMADE IMPEDIMENTS TO FISH PASSAGE LOCATED ON ANADROMOUS STREAM REACHES WITHIN FAIRFAX CREEK, CORTE MADERA CREEK WATERSHED, MARIN COUNTY, CA. Prepared

More information

STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END

STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END STUDY OF THE REASONS THAT INDUCE CRACKS AT BRIDGE DECK END by Zhengyu Liu Research Team: Zhengyu Liu, Graduate Research Student, Bridge Engineering Center, Iowa State University Brent M Phares, Director,

More information

Modified Sheet Pile Abutment for Low-Volume Road Bridge

Modified Sheet Pile Abutment for Low-Volume Road Bridge Modified Sheet Pile Abutment for Low-Volume Road Bridge Ryan R. Evans Department of Civil, Construction, and Environmental Engineering Iowa State University 176 Town Engineering Ames, IA 50011 ryevans@iastate.edu

More information

1 Study the drawings and the installation. 2 Ensure that you have the correct components. 3 Follow the manufacturer s instructions

1 Study the drawings and the installation. 2 Ensure that you have the correct components. 3 Follow the manufacturer s instructions 1 Study the drawings and the installation plan ahead of time. Consider laying the components out in the approximate order in which they will be installed. This will help workers become familiar with the

More information

Flume Installation Instructions

Flume Installation Instructions Flume Installation Instructions To ensure a successful installation, it is important to keep the following points in mind: 1) There should be no bend, dips, elbows, or flow junction immediately upstream

More information

Low-Volume Road Abutment Design Standards

Low-Volume Road Abutment Design Standards Low-Volume Road Abutment Design Standards V.W. Robbins HNTB Corporation 7450 W. 130th St., Suite 400 Overland Park, KS 66213 vrobbins@hntb.com F. Wayne Klaiber Bridge Engineering Center 418 Town Engineering

More information

Shifting the Canning Bus Bridge Sideways

Shifting the Canning Bus Bridge Sideways Shifting the Canning Bus Bridge Sideways Ros MacKinlay Design Engineer, Wyche Consulting SYNOPSIS The Perth Mandurah railway proposed in 2002 required the replacement of an existing Kwinana Freeway bus

More information

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION

SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION SUMMARY OF NOVEMBER 2013 REVISIONS - VERSION 3.2.0.0 Since the release of BRADD Version 3.1.6.2, several major enhancements have been made to the software and many reported operational issues have been

More information

5 DAMAGE TO TRANSPORTATION FACILITIES

5 DAMAGE TO TRANSPORTATION FACILITIES 5 DAMAGE TO TRANSPORTATION FACILITIES In the Kocaeli, Turkey earthquake of August 17, 1999, extensive damage of transportation facilities occurred in the Kocaeli and Sakarya region, Turkey as shown in

More information

Stairways and Ladders. OSHA Office of Training & Education 1

Stairways and Ladders. OSHA Office of Training & Education 1 Stairways and Ladders OSHA Office of Training & Education 1 Hazards Stairways and ladders cause many injuries and fatalities among construction workers About half the injuries caused by slips, trips and

More information

Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3

Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3 F. W. Klaiber, D. J. White, T. J. Wipf, B. M. Phares, V. W. Robbins Development of Abutment Design Standards for Local Bridge Designs Volume 1 of 3 Development of Design Methodology August 2004 Sponsored

More information

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint

Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint Potential For Fracture To Occur In Iowa DOT Steel Girder Bridges Due to Triaxial Constraint Introduction The purpose of this white paper is to provide information regarding the potential for fractures

More information

Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways

Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways Overturning Forces at Bridge Abutments and the Interaction of Horizontal Forces from Adjacent Roadways ANNUAL REPORT FOR FY 2011 ODOT SPR ITEM NUMBER 2228 Submitted to: John Bowman, P.E. Planning and Research

More information

State-Aid Bridge News August 2, 2005

State-Aid Bridge News August 2, 2005 State-Aid Bridge News August 2, 2005 Bridge Hydraulic Information The FHWA has been inquiring about our Scour Program. In particular, there are two areas of concern; 1. Are our Scour Action Plans current

More information

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report

research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report Final Report VTRC 06-R35 Virginia Transportation Research Council research report Field Measurements on Skewed Semi-Integral Bridge With Elastic Inclusion: Instrumentation Report http:/www.virginiadot.org/vtrc/main/online_reports/pdf/06-r35.pdf

More information

EFFECTS OF SKEWED ABUTMENTS ON CURVED BRIDGE CONSTRUCTION RESPONSE. Tyler Goodman. Spring 2013

EFFECTS OF SKEWED ABUTMENTS ON CURVED BRIDGE CONSTRUCTION RESPONSE. Tyler Goodman. Spring 2013 THE PENNSYLVANIA STATE UNIVERSITY SCHREYER HONORS COLLEGE DEPARTMENT OF CIVIL AND ENVIROMENTAL ENGINEERING EFFECTS OF SKEWED ABUTMENTS ON CURVED BRIDGE CONSTRUCTION RESPONSE Tyler Goodman Spring 2013 A

More information

Draft. Not yet Approved. Natural Waterways 2012

Draft. Not yet Approved. Natural Waterways 2012 Natural Waterways 2012 3.1 General 1 3 5 3.1.1 Scope (2012) 1 3 5 3.1.2 Importance (1992) R(2012) 1 3 5 3.2 Hydrologic Capacity of Waterway Openings1 1 3 5 3.2.1 General (2012) 1 3 5 3.2.2 Drainage Basin

More information

COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES.

COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES. COMBINED APPLICATION OF ULTRASONIC INSPECTION AND ACOUSTIC EMISSION MONITORING FOR EVALUATION OF FRACTURE CRITICAL MEMBERS IN RAILWAY BRIDGES Authors D. Nyborg, Research Physicist, TISEC Inc., Montreal;

More information

OVER US 6 LATERAL BRIDGE SLIDE: I-75

OVER US 6 LATERAL BRIDGE SLIDE: I-75 LATERAL BRIDGE SLIDE: I-75 OVER US 6 Bob Beasley, PE, Ohio Bridge Manager, Arcadis U.S., Inc. Todd Lezon, Regional Manager, Kokosing Construction Company, Inc. November 4, 2016 1 Agenda Design Bob Beasley,

More information

Hydrau-Tech, Inc. Engineering & Software

Hydrau-Tech, Inc. Engineering & Software Hydrau-Tech, Inc. Engineering & Software HYDRAU-TECH, INC. H ydrau-tech, Inc. is an engineering consulting firm specializing since 1986 in openchannel hydraulics, watershed, river, and reservoir sedimentation,

More information

1 Exam Prep. SMACNA Architectural Sheet Metal Questions

1 Exam Prep. SMACNA Architectural Sheet Metal Questions 1 Exam Prep SMN rchitectural Sheet Metal Questions 1. Which of the following is not an advantage of terne? Lightweight High expansion rate Low expansion rate urable 2. ownspouts should be constructed with

More information

EAH 422 ADVANCED WATER RESOURCES ENGINEERING

EAH 422 ADVANCED WATER RESOURCES ENGINEERING EAH 422 ADVANCED WATER RESOURCES ENGINEERING Bridge Hydraulics Prof. Aminuddin Ab. Ghani References The Art And Science Of River Engineering Bridge Failure Pier scour Pier scour Pier scour Bridge Failure

More information

Simplified Analytical Model of a Covered Queen-Post-Truss Timber Bridge

Simplified Analytical Model of a Covered Queen-Post-Truss Timber Bridge Simplified Analytical Model of a Covered Queen-Post-Truss Timber Bridge Fouad Fanous, Douglas Rammer & Terry Wipf, Bridge Engineering Center Forest Product Laboratory Study Scope Objective Develop a simple

More information

ACCELERATED BRIDGE REPLACEMENT

ACCELERATED BRIDGE REPLACEMENT Christopher Beck Chief Engineer: Bridge & Structures Northern Indiana Commuter Transportation District 601 North Roeske Avenue Michigan City, IN chris.beck@nictd.com Accelerated Bridge Replacement (ABR)

More information

Feature Stamping SURFACE WATER MODELING SYSTEM. 1 Introduction. 2 Opening a Background Image

Feature Stamping SURFACE WATER MODELING SYSTEM. 1 Introduction. 2 Opening a Background Image SURFACE WATER MODELING SYSTEM Feature Stamping 1 Introduction In this lesson you will learn how to use conceptual modeling techniques to create numerical models that incorporate flow control structures

More information

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri

Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri Geosynthetic Reinforced Soil (GRS) Integrated Bridge Systems (IBS) John Bowders University of Missouri Adams et al. (2012), FHWA Geosynthetic Reinforced Soil Integrated Bridge System Interim Implementation

More information

Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures

Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures InTrans Project Reports Institute for Transportation 9-2015 Evaluation of the Need for Longitudinal Median Joints in Bridge Decks on Dual Structures Brent Phares Institute for Transportation, bphares@iastate.edu

More information

Identifying Number MPC-354. Project Title: Geotechnical Limit to Scour at Spill-through Abutments. University: The University of Wyoming

Identifying Number MPC-354. Project Title: Geotechnical Limit to Scour at Spill-through Abutments. University: The University of Wyoming Identifying Number MPC-354 Project Title: Geotechnical Limit to Scour at Spill-through Abutments University: The University of Wyoming Principal Investigators: Robert Ettema PhD, PE College of Engineering

More information

Technical Report Documentation Page

Technical Report Documentation Page Technical Report Documentation Page 1. Report No. 2. Government Accession No. 4. Title and Subtitle Design and In-situ Load Testing of Bridge No. 2210010 County Road 6210 - Phelps County, MO 7. Author/s

More information

Service Life of Aluminized Type 2 Coated Steel Pipe: Predictions vs. Actual

Service Life of Aluminized Type 2 Coated Steel Pipe: Predictions vs. Actual Service Life of Aluminized Type 2 Coated Steel Pipe: Predictions vs. Actual Resource # 07-135 (04/16) 2 2016 American Concrete Pipe Association, all rights reserved. The last comprehensive inspection of

More information

Effect of Pile Orientation in Skewed Integral Abutment Bridges

Effect of Pile Orientation in Skewed Integral Abutment Bridges Effect of Pile Orientation in Skewed Integral Abutment Bridges RABIH NAJIB, Ph.D., PE, Alpha Corporation, Baltimore, Maryland and AMDE M. AMDE, Ph.D., PE, University of Maryland, College Park, Maryland

More information

v Feature Stamping SMS 12.0 Tutorial Prerequisites Requirements TABS model Map Module Mesh Module Scatter Module Time minutes

v Feature Stamping SMS 12.0 Tutorial Prerequisites Requirements TABS model Map Module Mesh Module Scatter Module Time minutes v. 12.0 SMS 12.0 Tutorial Objectives In this lesson will teach how to use conceptual modeling techniques to create numerical models that incorporate flow control structures into existing bathymetry. The

More information

EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT

EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT Norton et al. Word Count: 8400 Tables: 5 Figures: 13 1 EXAMINATION OF THE RESPONSE OF SKEWED STEEL BRIDGE SUPERSTRUCTURE DURING DECK PLACEMENT Date submitted: 08/01/02 Date Revised and Resubmitted: 11/15/02

More information

Non-Destructive Testing of Drilled Shafts Current Practices and New Methods

Non-Destructive Testing of Drilled Shafts Current Practices and New Methods Non-Destructive Testing of Drilled Shafts Current Practices and New Methods Brent Robinson, Pile Dynamics, Inc. 2012 Pile Dynamics, Inc. Foundation & Geotechnical Engineering Why Test Integrity? Survey

More information

Drainage and Detention Report. for. Charity Auto Sales. located at: East 116 th Street North Collinsville, OK Revised August 22, 2016

Drainage and Detention Report. for. Charity Auto Sales. located at: East 116 th Street North Collinsville, OK Revised August 22, 2016 Drainage and Detention Report for Charity Auto Sales located at: 9 East 6 th Street North Collinsville, OK 742 Revised August 22, 26 Olsson Associates, Inc. 9 N. Birch Street, Suite 2 Owasso, OK 74 (98)

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Fly Ash Pond Big Sandy Plant Louisa, Kentucky October, 2016 Prepared for: Kentucky Power Big Sandy Plant Louisa, Kentucky Prepared by: American Electric Power

More information

Project Cost Estimating System

Project Cost Estimating System ect Cost Estimating System SUMMARY PAGE UPC: **** DISTRICT PROJECT NUMBER CULPEPER Alternative A-1 CONSTRUCTION END YEAR FY2018 UPC **** AD YEAR ESTIMATE YEAR FY2015 FY2014 RATE OF INFLATION TO AD 1.80%

More information

Pennsylvania s Experience with LRFD Implementation. By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation

Pennsylvania s Experience with LRFD Implementation. By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation Pennsylvania s Experience with LRFD Implementation By: Thomas Macioce, P.E. Beverly Miller, P.E. Pennsylvania Department of Transportation Overview Case History Spread Footing Width and Braking force Approach

More information